| Firm | Filings | Most Recent |
|---|---|---|
| ROGERS CALVANICO GROUP PLLC | 4 | 10/05/2021 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TITANIUM CONSTRUCTION SER | General Contractor | 25 | 07/08/2026 |
| PLUMBING NYC INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ROGERS CALVANICO GROUP PL | 1324 | 1 | 09/01/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | TITANIUM CONSTRUCTION SER | 09/13/2024 |
| DOB NOW | Construction Fence | Permit Issued | TITANIUM CONSTRUCTION SER | 09/20/2023 |
| DOB NOW | Structural | Permit Issued | TITANIUM CONSTRUCTION SER | 09/19/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | TITANIUM CONSTRUCTION SER | 10/01/2022 |
| DOB NOW | Construction Fence | Permit Issued | TITANIUM CONSTRUCTION SER | 09/30/2022 |
| DOB NOW | Plumbing | Permit Issued | PLUMBING WORKS NYC INC | 12/20/2021 |
| DOB NOW | General Construction | Permit Issued | TITANIUM CONSTRUCTION SER | 10/07/2021 |
| DOB NOW | Construction Fence | Permit Issued | TITANIUM CONSTRUCTION SER | 10/07/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | TITANIUM CONSTRUCTION SER | 10/06/2021 |
| DOB NOW | Construction Fence | Permit Issued | TITANIUM CONSTRUCTION SER | 09/03/2021 |
| BIS | OT | ISSUED | SOLAR ENERGY NY CORP | 08/13/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/21/2026 | Complete | MACK ELECTRICAL INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/05/2021 | Permit Issued | TITANIUM CONSTRUCTION SER | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/09/2021 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 09/09/2021 | Fenestration air leakage | — | energy_progress |
| 09/09/2021 | Ventilation and air distribution system | — | energy_progress |
| 09/09/2021 | Fenestration areas | — | energy_progress |
| 09/09/2021 | Insulation placement and R values | — | energy_progress |
| 09/09/2021 | Maintenance information | — | energy_progress |
| 09/09/2021 | Mechanical Systems | — | special |
| 09/09/2021 | Structural Stability – Alterations of existing buildings | — | special |
| 09/09/2021 | Energy Code Compliance Inspections | — | progress |
| 09/09/2021 | Final | — | progress |
| 09/09/2021 | Structural Wood Frame | — | progress |
| 09/09/2021 | Duct leakage testing, insulation and design | — | energy_progress |
| 09/09/2021 | Air barrier - visual inspection | — | energy_progress |
| 09/09/2021 | Fireplaces | — | energy_progress |
| 09/09/2021 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 09/09/2021 | HVAC-R and service water heating equipment | — | energy_progress |
| 09/09/2021 | Interior lighting power | — | energy_progress |
| 09/09/2021 | HVAC-R and service water heating system controls | — | energy_progress |
| 09/09/2021 | Permanent certificate | — | energy_progress |