← Back
Two stories - detached, small or mid-size
15 WATERFORD COURT
STATEN ISLAND · Grasmere-Arrochar-South Beach-Dongan Hills · BIN 5045975
💬 Discuss this project
1970Year Built
1Stories
A1Building Class
R3-1Zoning
2,444 sfGross Floor Area
1Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Two stories - detached, small or mid-size · Owner of record: MORSHYN TRUST · 3,800 sf lot · 0.64 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Floor 26p · 2 filings · 20 docs
Floor 15p · 1 filing · 20 docs
Cellar8p · 2 filings · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
WILLY C. YUIN ARCH. PLLC707/21/2026
TAMBOK LLC105/06/2026
PARKER AND WEST ENGINEERING, PLLC101/09/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
TAMBOK STUDIO503/21/2026
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ADIR STUCCO INCGeneral Contractor1007/08/2026
CITY PLUMBING INCPlumbing207/08/2026
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738307/21/2026
PARKER AND WEST ENGINEERI5272101/09/2024
Building Lifecycle
All (68)Filed (9)Permit Issued (8)Signed Off (5)Violation (4)Inspection (8)Objection (4)Special Inspection (30)
08/14/2026
Signed off — Alteration CO
PROPOSED SECOND STORY ADDITION TO EXISTING ONE FAMILY RESIDENCE WITH INTERIOR ALTERATION TO FIRST FLOOR AND CELLAR. NO CHANGE IN USE, EGRESS OR OCCUPANCY
S00860290-I1
07/21/2026
Filed — Alteration CO
PROPOSED SECOND STORY ADDITION TO EXISTING ONE FAMILY RESIDENCE WITH INTERIOR ALTERATION TO FIRST FLOOR AND CELLAR. NO CHANGE IN USE, EGRESS OR OCCUPANCY
S00860290-P3
07/21/2026
Special inspection requirement — Fenestration areas
anthony santoro
07/21/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
07/21/2026
Special inspection requirement — Interior lighting power
anthony santoro
07/21/2026
Special inspection requirement — Fenestration air leakage
anthony santoro
07/21/2026
Special inspection requirement — Permanent certificate
anthony santoro
07/21/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
07/21/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
anthony santoro
07/21/2026
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
07/21/2026
Special inspection requirement — Final
anthony santoro
07/21/2026
Special inspection requirement — Fire-Resistance Rated Construction
anthony santoro
07/21/2026
Special inspection requirement — Structural Wood Frame
anthony santoro
07/21/2026
Special inspection requirement — Air barrier - visual inspection
anthony santoro
07/21/2026
Special inspection requirement — Insulation placement and R values
anthony santoro
07/21/2026
Special inspection requirement — Maintenance information
anthony santoro
07/17/2026
Signed off — Alteration
REMOVE ECB VIOLATION: 039185994M; REMOVE UNPERMITTED DECK AND FENCE AND RESTORE BACK TO PRIOR LEGAL CONDITION AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
S01395464-I1
06/25/2026
Permit issued — General Construction
S01395464-I1-GC
05/06/2026
Filed — Alteration
REMOVE ECB VIOLATION: 039185994M; REMOVE UNPERMITTED DECK AND FENCE AND RESTORE BACK TO PRIOR LEGAL CONDITION AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
S01395464-I1
04/30/2026
Special inspection requirement — Final
Jennifer TAM
04/24/2026
Violation issued (ECB, closed)
Zoning
04/24/2026
Violation issued (ECB, closed)
Construction
04/24/2026
Violation issued (ECB, closed)
Construction
04/24/2026
Violation issued (ECB, open)
Construction
08/05/2025
Signed off — Alteration
Installation of new bathroom and kitchen fixtures, Replacement and installation of new heating system. Plumbing work filed in Conjunction with ALT CO: S00860290
S00860300-I1
02/24/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/10/2025
Objection resolved — Addressed
02/06/2025
Objection raised — Scope
01/31/2025
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S00977612-I1
01/31/2025
Filed — Alteration CO
PROPOSED SECOND STORY ADDITION TO EXISTING ONE FAMILY RESIDENCE WITH INTERIOR ALTERATION TO FIRST FLOOR AND CELLAR. NO CHANGE IN USE, EGRESS OR OCCUPANCY
S00860290-P1
01/29/2025
Special inspection requirement — Fenestration areas
anthony santoro
01/29/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
anthony santoro
01/29/2025
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
01/29/2025
Special inspection requirement — Final
anthony santoro
01/29/2025
Special inspection requirement — Fire-Resistance Rated Construction
anthony santoro
01/29/2025
Special inspection requirement — Structural Wood Frame
anthony santoro
01/29/2025
Special inspection requirement — Air barrier - visual inspection
anthony santoro
01/29/2025
Special inspection requirement — Maintenance information
anthony santoro
01/29/2025
Special inspection requirement — Fenestration air leakage
anthony santoro
01/29/2025
Special inspection requirement — Permanent certificate
anthony santoro
01/29/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
01/29/2025
Special inspection requirement — Insulation placement and R values
anthony santoro
01/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
01/29/2025
Special inspection requirement — Interior lighting power
anthony santoro
11/06/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/04/2024
Special inspection requirement — Permanent certificate
anthony santoro
09/03/2024
Filed — Alteration
Installation of new bathroom and kitchen fixtures, Replacement and installation of new heating system. Plumbing work filed in Conjunction with ALT CO: S00860290
S00860300-P2
08/30/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/14/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/08/2024
Permit issued — Plumbing
S00860300-I1-PL
08/05/2024
Signed off — Alteration
S00864750-I1
07/12/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/03/2024
Filed — Alteration
Installation of new bathroom and kitchen fixtures, Replacement and installation of new heating system. Plumbing work filed in Conjunction with ALT CO: S00860290
S00860300-P1
06/07/2024
Permit issued — Structural
S00860290-I1-GC-CX
01/22/2024
Permit issued — Solar
S00977612-I1-SL
01/18/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/09/2024
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S00977612-I1
12/22/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
11/06/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/22/2023
Permit issued — Plumbing
S00860300-I1-PL
Latest 60 of 68 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPR06/25/2026
DOB NOWPlumbingSigned-offCITY PLUMBING INC08/08/2024
DOB NOWStructuralPermit IssuedADIR STUCCO INC06/07/2024
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC01/22/2024
DOB NOWPlumbingSigned-offCITY PLUMBING INC07/22/2023
DOB NOWGeneral ConstructionPermit IssuedADIR STUCCO INC07/19/2023
DOB NOWConstruction FenceSigned-offADIR STUCCO INC06/22/2023
DOB NOWConstruction FenceSigned-offADIR STUCCO INC05/09/2023
3 projects · most recent 01/09/2024
General Wiring
FiledStatusContractorScope
01/09/2024CompleteSUNRUN SOLAR ELECTL CORPGeneral Wiring
09/17/2023CompleteFALCO ELEC'L SERVICES INC—
08/14/2023CompleteFALCO ELEC'L SERVICES INCGeneral Wiring
1 project · most recent 07/21/2026
Wood
FiledStatusContractorScope
07/21/2026Permit IssuedADIR STUCCO INCWood
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
02/24/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/06/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/30/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/14/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/12/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/18/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/22/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/06/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
07/21/2026Fenestration areasanthony santoroenergy_progress
07/21/2026Fenestration and door U-factor and product ratingsanthony santoroenergy_progress
07/21/2026Interior lighting poweranthony santoroenergy_progress
07/21/2026Fenestration air leakageanthony santoroenergy_progress
07/21/2026Permanent certificateanthony santoroenergy_progress
07/21/2026Fire-Resistant Penetrations and Jointsanthony santorospecial
07/21/2026Structural Stability – Alterations of existing buildingsanthony santorospecial
07/21/2026Energy Code Compliance Inspectionsanthony santoroprogress
07/21/2026Finalanthony santoroprogress
07/21/2026Fire-Resistance Rated Constructionanthony santoroprogress
07/21/2026Structural Wood Frameanthony santoroprogress
07/21/2026Air barrier - visual inspectionanthony santoroenergy_progress
07/21/2026Insulation placement and R valuesanthony santoroenergy_progress
07/21/2026Maintenance informationanthony santoroenergy_progress
04/30/2026FinalJennifer TAMprogress
01/29/2025Fenestration areasanthony santoroenergy_progress
01/29/2025Structural Stability – Alterations of existing buildingsanthony santorospecial
01/29/2025Energy Code Compliance Inspectionsanthony santoroprogress
01/29/2025Finalanthony santoroprogress
01/29/2025Fire-Resistance Rated Constructionanthony santoroprogress
01/29/2025Structural Wood Frameanthony santoroprogress
01/29/2025Air barrier - visual inspectionanthony santoroenergy_progress
01/29/2025Maintenance informationanthony santoroenergy_progress
01/29/2025Fenestration air leakageanthony santoroenergy_progress
01/29/2025Permanent certificateanthony santoroenergy_progress
Latest 25 of 52.
▾Documents — 76 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/23/2026S00860300-P2Request digital key ↗
08/23/2026S00860300-I1Request digital key ↗
08/23/2026S00860300-P1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits3
▸BISBPP-5 - Authorization to the Department of Transportation1
08/14/2023540250627Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
07/13/2023540250627Open ↗
▸BISBPP-16 - Application for waiver of curb alignment and/or sidewalk and curb1
08/14/2023540250627Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZoning Exhibit form (1-5)3
08/20/2026S00860290-P3Open ↗
08/13/2026S00860290-P1Open ↗
08/13/2026S00860290-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram3
08/20/2026S00860290-P3Open ↗
08/13/2026S00860290-P1Open ↗
08/13/2026S00860290-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00860290-I1Open ↗
▸Seals & Professional Certifications31
▸DOB NOWProgress Inspector Seal & Signature16
09/02/2026S00977612-I1Open ↗
09/02/2026S00977612-I1Open ↗
09/02/2026S00977612-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/23/2026S00860300-P2Open ↗
08/23/2026S00860300-I1Open ↗
08/23/2026S00860300-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026S00977612-I1Open ↗
09/02/2026S00977612-I1Open ↗
08/26/2026S00860290-P1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
07/13/2023540250627Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/13/2023540250627Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/23/2026S00860300-P2Open ↗
08/23/2026S00860300-I1Open ↗
08/23/2026S00860300-P1Open ↗
Showing 3 of 7 on file for this type
▸Inspections & Test Reports1
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
08/14/2023540250627Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S00977612-I1Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
07/13/2023540250627Open ↗
▸Other Documents16
▸DOB NOWPlot Diagram3
08/20/2026S00860290-P3Open ↗
08/13/2026S00860290-P1Open ↗
08/13/2026S00860290-I1Open ↗
▸DOB NOWSite Survey: Initial3
08/20/2026S00860290-P3Open ↗
08/13/2026S00860290-I1Open ↗
08/13/2026S00860290-P1Open ↗
▸DOB NOWProperty Ownership Certification3
08/20/2026S00860290-P3Open ↗
08/13/2026S00860290-I1Open ↗
08/13/2026S00860290-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/20/2026S00860290-P3Open ↗
08/13/2026S00860290-P1Open ↗
08/13/2026S00860290-I1Open ↗
▸DOB NOWFinal Survey2
08/20/2026S00860290-I1Open ↗
08/13/2026S00860290-I1Open ↗
▸BISWAIVER OF CURB ALIGNMENT1
07/12/2023540250627Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
07/13/2023540250627Open ↗