| Owner | Filings | Most Recent |
|---|---|---|
| MOLINO DEVELOPMENT | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MICHAEL DERUVO & ASSOC. ARCHITECTS | 3 | 01/13/2026 |
| ROGERS CALVANICO GROUP PLLC | 2 | 08/07/2025 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 05/05/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| A TECH ENGINEERING NYC | 2 | 03/21/2026 |
| PATRICIA L. GASS | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KDC OF STATEN ISLAND INC | General Contractor | 4 | 07/08/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 01/02/2026 |
| DOB NOW | General Construction | Permit Issued | KDC OF STATEN ISLAND INC | 12/23/2025 |
| DOB NOW | General Construction | Permit Issued | KDC OF STATEN ISLAND INC | 09/05/2025 |
| DOB NOW | Curb Cut | Signed-off | KDC OF STATEN ISLAND INC | 08/13/2025 |
| DOB NOW | Construction Fence | Signed-off | KDC OF STATEN ISLAND INC | 05/07/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/18/2026 | Pass-Final Construction Permit Withdrawal | Pass | View ↗ |
| 02/23/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/13/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/07/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/06/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/30/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/11/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 12/20/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/27/2026 | Fire-Resistance Rated Construction | MICHAEL DERUVO | progress |
| 01/27/2026 | Electric vehicle service equipment requirements | MICHAEL DERUVO | energy_progress |
| 01/27/2026 | Air barrier — testing | MICHAEL DERUVO | energy_progress |
| 01/27/2026 | Fenestration and door U-factor and product ratings | MICHAEL DERUVO | energy_progress |
| 01/27/2026 | Insulation placement and R values | MICHAEL DERUVO | energy_progress |
| 01/27/2026 | Fenestration air leakage | MICHAEL DERUVO | energy_progress |
| 01/27/2026 | Air barrier - visual inspection | MICHAEL DERUVO | energy_progress |
| 01/27/2026 | Interior lighting power | MICHAEL DERUVO | energy_progress |
| 01/27/2026 | Fenestration areas | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Fire-Resistance Rated Construction | MICHAEL DERUVO | progress |
| 01/13/2026 | Air barrier — testing | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Fenestration areas | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Fenestration air leakage | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Insulation placement and R values | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Fenestration and door U-factor and product ratings | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Air barrier - visual inspection | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Interior lighting power | MICHAEL DERUVO | energy_progress |
| 01/13/2026 | Electric vehicle service equipment requirements | MICHAEL DERUVO | energy_progress |