| Owner | Filings | Most Recent |
|---|---|---|
| LATERRA DEVELOPERS | 12 | 07/08/2026 |
| WINHAM HOLDINGS | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| C&P DESIGN CONSULTANTS | 2 | 05/06/2026 |
| BRIAN GOLDMAN, ARCHITECT | 1 | 09/30/2024 |
| STANLEY M. KREBUSHEVSKI, R.A. | 1 | 03/28/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| PERCIBALLI INDUSTRIES | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LATERRA DEVELOPERS LLC | General Contractor | 4 | 07/08/2026 |
| PERCIBALLI INDUSTRIES INC. | General Contractor | 1 | 04/09/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 2 | 07/21/2025 |
| SRA PLANNING & EXPEDITING | 5677 | 1 | 03/28/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | LATERRA DEVELOPERS LLC | 05/21/2026 |
| DOB NOW | Mechanical Systems | Signed-off | LATERRA DEVELOPERS LLC | 05/11/2026 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 07/29/2025 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 07/24/2025 |
| DOB NOW | Full Demolition | Signed-off | PERCIBALLI INDUSTRIES INC. | 04/23/2025 |
| DOB NOW | Construction Fence | Signed-off | LATERRA DEVELOPERS LLC | 04/08/2025 |
| DOB NOW | Construction Fence | Signed-off | LATERRA DEVELOPERS LLC | 10/03/2024 |
| BIS | — | ISSUED | LATERRA DEVELOPERS LLC | 05/21/2025 |
| BIS | — | ISSUED | LATERRA DEVELOPERS LLC | 05/20/2025 |
| BIS | OT | ISSUED | TIP TOP GENERAL CONTRACT | 11/12/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/28/2023 | Signed-off | FLOW-RIGHT PLBG & HTG COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/20/2025 | Complete | D AND H ELECTRICAL CONST | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/17/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/13/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/31/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/02/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/12/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/04/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/20/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/06/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/01/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/28/2024 | Pass-Final PL - Underground | Pass | View ↗ |