| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/31/2022 | Signed-off | A.G.M. P & H INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2023 | Complete | AROUND ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/22/2021 | Permit Issued | L & J MASONRY LLC | Fence |
| Firm | Filings | Most Recent |
|---|---|---|
| ACV DESIGN LTD | 7 | 02/26/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JONICO CONSTRUCTION LLC | General Contractor | 3 | 03/21/2026 |
| L & J MASONRY LLC | General Contractor | 2 | 07/08/2026 |
| A.G.M. P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ACV DESIGN LTD | 3864 | 5 | 02/26/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | JONICO CONSTRUCTION LLC | 01/31/2024 |
| DOB NOW | Plumbing | Signed-off | A.G.M. P & H INC | 02/24/2022 |
| DOB NOW | General Construction | Permit Issued | L & J MASONRY LLC | 01/26/2022 |
| DOB NOW | Construction Fence | Permit Issued | L & J MASONRY LLC | 12/03/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/14/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/22/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/22/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/02/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/26/2024 | Concrete - Cast-In-Place | ANTHONY VILLANO | special |
| 02/26/2024 | Exterior Insulation and Finish Systems (EIFS) | ANTHONY VILLANO | special |
| 02/26/2024 | Fire-Resistant Penetrations and Joints | ANTHONY VILLANO | special |
| 02/26/2024 | Masonry | ANTHONY VILLANO | special |
| 02/26/2024 | Structural Stability – Alterations of existing buildings | ANTHONY VILLANO | special |
| 02/26/2024 | Energy Code Compliance Inspections | ANTHONY VILLANO | progress |
| 02/26/2024 | Fire-Resistance Rated Construction | ANTHONY VILLANO | progress |
| 12/27/2023 | Fire-Resistance Rated Construction | ANTHONY VILLANO | progress |
| 12/27/2023 | Concrete - Cast-In-Place | ANTHONY VILLANO | special |
| 12/27/2023 | Exterior Insulation and Finish Systems (EIFS) | ANTHONY VILLANO | special |
| 12/27/2023 | Fire-Resistant Penetrations and Joints | ANTHONY VILLANO | special |
| 12/27/2023 | Masonry | ANTHONY VILLANO | special |
| 12/27/2023 | Structural Stability – Alterations of existing buildings | ANTHONY VILLANO | special |
| 12/27/2023 | Energy Code Compliance Inspections | ANTHONY VILLANO | progress |
| 02/10/2022 | HVAC-R and service water heating equipment | ANTHONY VILLANO | energy_progress |
| 02/10/2022 | HVAC-R and service water piping design and insulation | ANTHONY VILLANO | energy_progress |
| 02/10/2022 | Maintenance information | ANTHONY VILLANO | energy_progress |
| 02/10/2022 | Fire-Resistant Penetrations and Joints | ANTHONY VILLANO | special |
| 02/10/2022 | HVAC-R and service water heating system controls | ANTHONY VILLANO | energy_progress |
| 10/20/2021 | Maintenance information | ANTHONY VILLANO | energy_progress |
| 10/20/2021 | Fenestration areas | ANTHONY VILLANO | energy_progress |
| 10/20/2021 | Permanent certificate | ANTHONY VILLANO | energy_progress |
| 10/20/2021 | Fire-Resistant Penetrations and Joints | ANTHONY VILLANO | special |
| 10/20/2021 | Masonry | ANTHONY VILLANO | special |
| 10/20/2021 | Structural Stability – Alterations of existing buildings | ANTHONY VILLANO | special |