| Owner | Filings | Most Recent |
|---|---|---|
| D R CONTRACTING | 3 | 03/22/2026 |
| 4075 HYLAN BLVD LLC | 2 | 03/22/2026 |
| MARIANO REALTY LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RYAN DESIGN ARCHITECTURE | 7 | 11/14/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| D.R. CONTRACTING | General Contractor | 5 | 07/08/2026 |
| AL SAEED CONSTRUCTION | General Contractor | 4 | 09/15/2026 |
| KCM PLUMBING & HEATING CO | Plumbing | 2 | 07/08/2026 |
| CAM ENERGY HTG&MECH CORP | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RYAN DESIGN ARCHITECTURE | 7159 | 5 | 11/05/2025 |
| A TECH ENGINEERING NYC, P | 6738 | 1 | 09/15/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | AL SAEED CONSTRUCTION | 09/14/2026 |
| DOB NOW | Plumbing | Permit Issued | CAM ENERGY HTG&MECH CORP | 04/03/2026 |
| DOB NOW | General Construction | Permit Issued | AL SAEED CONSTRUCTION | 12/12/2025 |
| DOB NOW | Plumbing | Permit Issued | KCM PLUMBING & HEATING CO | 09/05/2025 |
| DOB NOW | Construction Fence | Permit Issued | AL SAEED CONSTRUCTION | 08/26/2025 |
| DOB NOW | General Construction | Permit Issued | AL SAEED CONSTRUCTION | 08/22/2025 |
| DOB NOW | Plumbing | Permit Issued | KCM PLUMBING & HEATING CO | 08/30/2024 |
| DOB NOW | Construction Fence | Permit Issued | D.R. CONTRACTING | 08/16/2024 |
| DOB NOW | Construction Fence | Permit Issued | D.R. CONTRACTING | 03/29/2024 |
| DOB NOW | General Construction | Permit Issued | D.R. CONTRACTING | 02/01/2024 |
| BIS | FP | ISSUED | WILLIAM HIRD & CO INC | 12/11/2015 |
| BIS | OT | ISSUED | ACME AWNING CO. INC. | 04/13/1995 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/14/2025 | Permit Issued | CAM ENERGY HTG&MECH CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Permit Issued | BERGER QUALITY ELEC'L CON | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/14/2025 | Permit Issued | AL SAEED CONSTRUCTION | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/14/2025 | Permit Issued | AL SAEED CONSTRUCTION | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/28/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/22/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/14/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/14/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/11/2025 | Subsurface Investigations (Borings/Test Pits) | Daniel Ryan | special |
| 12/11/2025 | Fire-Resistant Penetrations and Joints | Daniel Ryan | special |
| 12/11/2025 | Concrete - Cast-In-Place | Daniel Ryan | special |
| 12/11/2025 | Subgrade Inspections | Daniel Ryan | special |
| 12/11/2025 | Fire-Resistance Rated Construction | Daniel Ryan | progress |
| 12/11/2025 | Energy Code Compliance Inspections | Daniel Ryan | progress |
| 12/11/2025 | Fenestration areas | Daniel Ryan | energy_progress |
| 12/11/2025 | Air barrier - visual inspection | Daniel Ryan | energy_progress |
| 12/11/2025 | Fenestration and door U-factor and product ratings | Daniel Ryan | energy_progress |
| 12/11/2025 | Insulation placement and R values | Daniel Ryan | energy_progress |
| 12/11/2025 | Fenestration air leakage | Daniel Ryan | energy_progress |
| 12/11/2025 | Metering | Daniel Ryan | energy_progress |
| 12/11/2025 | Interior lighting power | Daniel Ryan | energy_progress |
| 07/21/2025 | Fenestration air leakage | Daniel Ryan | energy_progress |
| 07/21/2025 | Concrete - Cast-In-Place | Daniel Ryan | special |
| 07/21/2025 | Interior lighting power | Daniel Ryan | energy_progress |
| 07/21/2025 | Insulation placement and R values | Daniel Ryan | energy_progress |
| 07/21/2025 | Fenestration and door U-factor and product ratings | Daniel Ryan | energy_progress |
| 07/21/2025 | Metering | Daniel Ryan | energy_progress |
| 07/21/2025 | Fire-Resistant Penetrations and Joints | Daniel Ryan | special |
| 07/21/2025 | Subgrade Inspections | Daniel Ryan | special |
| 07/21/2025 | Subsurface Investigations (Borings/Test Pits) | Daniel Ryan | special |
| 07/21/2025 | Energy Code Compliance Inspections | Daniel Ryan | progress |
| 07/21/2025 | Fire-Resistance Rated Construction | Daniel Ryan | progress |
| 07/21/2025 | Air barrier - visual inspection | Daniel Ryan | energy_progress |