| Firm | Filings | Most Recent |
|---|---|---|
| GUY V. MANGOGNA ARCHITECT | 5 | 05/12/2026 |
| A TECH ENGINEERING NYC, PLLC. | 3 | 12/23/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| A TECH ENGINEERING NYC | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J. SMITH CONSTRUCTION INC. | General Contractor | 4 | 07/02/2026 |
| CAPITAL CONTR P&H CORP | Plumbing | 4 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 3 | 07/29/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | J. SMITH CONSTRUCTION INC. | 05/21/2026 |
| DOB NOW | Sprinklers | Signed-off | CAPITAL CONTR P&H CORP | 03/23/2026 |
| DOB NOW | Mechanical Systems | Signed-off | J. SMITH CONSTRUCTION INC | 12/31/2025 |
| DOB NOW | Sprinklers | Signed-off | CAPITAL CONTR P&H CORP | 12/30/2025 |
| DOB NOW | Plumbing | Signed-off | CAPITAL CONTR P&H CORP | 12/29/2025 |
| DOB NOW | General Construction | Permit Issued | J. SMITH CONSTRUCTION INC | 06/25/2025 |
| DOB NOW | General Construction | Permit Issued | J. SMITH CONSTRUCTION INC | 08/16/2024 |
| DOB NOW | Plumbing | Signed-off | CAPITAL CONTR P&H CORP | 01/17/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/12/2026 | Signed-off | J. SMITH CONSTRUCTION INC | Air Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems |
| 07/29/2024 | Signed-off | J. SMITH CONSTRUCTION INC | Air Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/23/2025 | — | — | 62 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/30/2026 | Signed-off | CAPITAL CONTR P&H CORP | Gas, Water/Sanitary |
| 12/23/2025 | Signed-off | CAPITAL CONTR P&H CORP | Water/Sanitary |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/29/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/29/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/28/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/27/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/27/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/23/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/13/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/05/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 02/06/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/16/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/25/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/31/2026 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 03/31/2026 | Energy Code Compliance Inspections | anthony santoro | progress |
| 03/27/2026 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 03/27/2026 | Energy Code Compliance Inspections | anthony santoro | progress |
| 01/06/2026 | Energy Code Compliance Inspections | anthony santoro | progress |
| 01/06/2026 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 12/24/2025 | Sprinkler Systems | anthony santoro | special |
| 12/10/2025 | Sprinkler Systems | — | special |
| 07/29/2024 | Insulation placement and R values | anthony santoro | energy_progress |
| 07/29/2024 | Air barrier - visual inspection | anthony santoro | energy_progress |
| 06/17/2024 | Lighting controls | anthony santoro | energy_progress |
| 06/17/2024 | Interior lighting power | anthony santoro | energy_progress |
| 06/17/2024 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 03/07/2024 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 03/07/2024 | Fire-Resistance Rated Construction | anthony santoro | progress |
| 03/07/2024 | Energy Code Compliance Inspections | anthony santoro | progress |
| 03/07/2024 | Structural Stability – Alterations of existing buildings | anthony santoro | special |
| 03/07/2024 | Masonry | anthony santoro | special |