| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2024 | Complete | FICHERA ELECTRIC, INC | General Wiring |
| Firm | Filings | Most Recent |
|---|---|---|
| CHRIS PONISI, ARCHITECT | 2 | 11/10/2023 |
| REAL CREATIVE MOTION ENGINEERING SE | 1 | 09/19/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| CHRIS PONISI ARCHITECT | 2 | 03/21/2026 |
| DAWN PONISI | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CLAIRE CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| PATRIOT PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 3 | 11/10/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | CLAIRE CONSTRUCTION CORP | 05/15/2024 |
| DOB NOW | Plumbing | Signed-off | PATRIOT PLBG & HTG INC | 12/11/2023 |
| DOB NOW | Structural | Signed-off | CLAIRE CONSTRUCTION CORP | 11/30/2023 |
| BIS | PL | ISSUED | KCM PLUMBING & HEATING CO | 08/16/2018 |
| BIS | OT | ISSUED | UNIVERSAL CLEANING & MAINCH.INC | 08/03/2018 |
| BIS | OT | ISSUED | 1ST LIGHT ENERGY INC | 03/13/2014 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/21/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/23/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/25/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/22/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/18/2023 | Concrete - Cast-In-Place | anthony santoro | special |
| 10/18/2023 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 10/18/2023 | Subgrade Inspections | anthony santoro | special |
| 10/18/2023 | Structural Stability – Alterations of existing buildings | anthony santoro | special |
| 10/18/2023 | Energy Code Compliance Inspections | anthony santoro | progress |
| 10/18/2023 | Structural Wood Frame | anthony santoro | progress |
| 10/18/2023 | Air barrier - visual inspection | anthony santoro | energy_progress |
| 10/18/2023 | Fenestration air leakage | anthony santoro | energy_progress |
| 10/18/2023 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 10/18/2023 | Fenestration areas | anthony santoro | energy_progress |
| 10/18/2023 | Insulation placement and R values | anthony santoro | energy_progress |
| 10/18/2023 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 10/18/2023 | Interior lighting power | anthony santoro | energy_progress |
| 10/18/2023 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 10/17/2023 | Heating Systems | anthony santoro | special |
| 09/08/2023 | HVAC-R and service water heating equipment | anthony santoro | energy_progress |
| 09/08/2023 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 09/08/2023 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 09/07/2023 | Footing and Foundation | anthony santoro | progress |
| 09/07/2023 | Final | anthony santoro | progress |
| 09/06/2023 | Mechanical Systems | anthony santoro | special |
| 09/06/2023 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 09/06/2023 | Final | anthony santoro | progress |
| 09/06/2023 | Energy Code Compliance Inspections | anthony santoro | progress |