1985Year Built
1Stories
B2Building Class
R3XZoning
2,250 sfGross Floor Area
2Units
7 Open Violations 1 unresolved · 6 paperwork only ▸FDNY Report ↗
Two family frame · 6,500 sf lot · 0.35 FAR built · Flood zone X
Locations of Work
Architecture
Permit Issued — active, not yet Signed-off
Floor 2Under Construction9p · 1 filing · 20 docs
Floor 1Under Construction9p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NAN103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BAALBAKI&ASSOCIATES ENGINEERING, PC305/29/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
B A INSPECTIONS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MKSSKR CONSULTING SERVICEGeneral Contractor109/25/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BZINSPECTION8294205/29/2026
Building Lifecycle
All (27)Filed (3)Permit Issued (1)Violation (7)Special Inspection (16)
09/24/2026
Permit issued — General Construction
S01333681-I1-GC-CX
06/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Barry Berg
06/25/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Barry Berg
06/25/2026
Special inspection requirement — Concrete - Cast-In-Place
Barry Berg
06/25/2026
Special inspection requirement — Energy Code Compliance Inspections
Mohammad Baalbaki
06/25/2026
Special inspection requirement — Final
Barry Berg
06/25/2026
Special inspection requirement — Fenestration areas
Mohammad Baalbaki
06/25/2026
Special inspection requirement — Fenestration air leakage
Mohammad Baalbaki
06/25/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Mohammad Baalbaki
05/29/2026
Filed — Alteration
Plumbing Work in Conjunction with Job # S01333681
S01333681-P1
05/28/2026
Special inspection requirement — Concrete - Cast-In-Place
Barry Berg
05/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Barry Berg
05/28/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Barry Berg
05/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Mohammad Baalbaki
05/28/2026
Special inspection requirement — Final
Barry Berg
05/28/2026
Special inspection requirement — Fenestration areas
Mohammad Baalbaki
05/28/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Mohammad Baalbaki
05/28/2026
Special inspection requirement — Fenestration air leakage
Mohammad Baalbaki
04/18/2026
Filed — Alteration
Plumbing Work in Conjunction with Job # S01333681
S01333681-S1
01/29/2026
Filed — Alteration
Plumbing Work in Conjunction with Job # S01333681
S01333681-I1
10/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/14/2025
Violation issued (ECB, open)
Construction
10/14/2025
Violation issued (ECB, open)
Construction
10/14/2025
Violation issued (ECB, open)
Construction
10/14/2025
Violation issued (ECB, open)
Construction
10/14/2025
Violation issued (ECB, open)
Unknown
10/14/2025
Violation issued (ECB, open)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedMKSSKR CONSULTING SERVICE09/24/2026
BISOTISSUEDSUNRUN INSTALLATION SVC09/18/2017
BISOTISSUEDSUNRUN INSTALLATION SVC06/15/2016
BISPLISSUEDJ.P.B. MECHANICAL CORP.03/01/1994
BISOTISSUEDN/A02/18/1994
1 project · most recent 05/29/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
05/29/2026——Gas, Storm, Water/Sanitary
1 project · most recent 05/29/2026
Concrete Wood
FiledStatusContractorScope
05/29/2026Permit IssuedMKSSKR CONSULTING SERVICEConcrete, Wood
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
06/25/2026Fire-Resistant Penetrations and JointsBarry Bergspecial
06/25/2026Structural Stability – Alterations of existing buildingsBarry Bergspecial
06/25/2026Concrete - Cast-In-PlaceBarry Bergspecial
06/25/2026Energy Code Compliance InspectionsMohammad Baalbakiprogress
06/25/2026FinalBarry Bergprogress
06/25/2026Fenestration areasMohammad Baalbakienergy_progress
06/25/2026Fenestration air leakageMohammad Baalbakienergy_progress
06/25/2026Fenestration and door U-factor and product ratingsMohammad Baalbakienergy_progress
05/28/2026Concrete - Cast-In-PlaceBarry Bergspecial
05/28/2026Fire-Resistant Penetrations and JointsBarry Bergspecial
05/28/2026Structural Stability – Alterations of existing buildingsBarry Bergspecial
05/28/2026Energy Code Compliance InspectionsMohammad Baalbakiprogress
05/28/2026FinalBarry Bergprogress
05/28/2026Fenestration areasMohammad Baalbakienergy_progress
05/28/2026Fenestration and door U-factor and product ratingsMohammad Baalbakienergy_progress
05/28/2026Fenestration air leakageMohammad Baalbakienergy_progress
▾Documents — 81 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/16/2026S01333681-P1Request digital key ↗
08/16/2026S01333681-S1Request digital key ↗
08/16/2026S01333681-I1Request digital key ↗
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸BISWORK PERMIT APPLICATION2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram3
08/16/2026S01333681-P1Open ↗
08/16/2026S01333681-I1Open ↗
08/13/2026S01333681-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/16/2026S01333681-P1Open ↗
08/13/2026S01333681-I1Open ↗
▸Seals & Professional Certifications25
▸DOB NOWProgress Inspector Seal & Signature10
09/01/2026S01333681-I1Open ↗
09/01/2026S01333681-I1Open ↗
09/01/2026S01333681-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/01/2026S01333681-I1Open ↗
09/01/2026S01333681-I1Open ↗
09/01/2026S01333681-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/16/2026S01333681-P1Open ↗
08/16/2026S01333681-S1Open ↗
08/13/2026S01333681-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/16/2026S01333681-P1Open ↗
08/16/2026S01333681-S1Open ↗
08/13/2026S01333681-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
01/05/2018540135245Open ↗
09/15/2017540135245Open ↗
08/19/2016540106197Open ↗
Showing 3 of 4 on file for this type
▸BISSOLAR TAX ABATEMENT APPLICATION3
01/09/2018540135245Open ↗
01/05/2018540135245Open ↗
08/19/2016540106197Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
01/05/2018540135245Open ↗
08/19/2016540106197Open ↗
▸BISNYCECC ANALYSIS2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY4
01/05/2018540135245Open ↗
09/15/2017540135245Open ↗
08/19/2016540106197Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs6
▸BISUtility Company PV System Interconnection Acknowledgement Letter2
01/09/2018540135245Open ↗
08/19/2016540106197Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
01/05/2018540135245Open ↗
08/19/2016540106197Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
01/05/2018540135245Open ↗
08/19/2016540106197Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
01/05/2018540135245Open ↗
09/15/2017540135245Open ↗
08/19/2016540106197Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET2
09/15/2017540135245Open ↗
06/14/2016540106197Open ↗
▸Other Documents6
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/16/2026S01333681-P1Open ↗
08/13/2026S01333681-I1Open ↗
▸DOB NOWPlot Diagram2
08/16/2026S01333681-P1Open ↗
08/13/2026S01333681-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/16/2026S01333681-P1Open ↗
08/13/2026S01333681-I1Open ↗