Two stories - detached, small or mid-size
93 SYLVIA STREET
STATEN ISLAND · BIN 5135821
💬 Discuss this project
1999Year Built
2Stories
A1Building Class
R3AZoning
2,200 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 3,700 sf lot · 0.59 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CUTRONA ARCHITECTURE PLLC407/31/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PAUL LOPA DESIGNS, INCGeneral Contractor903/21/2026
RITE-FLO P.H.& COOLING INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738407/31/2025
Building Lifecycle
All (42)Filed (4)Permit Issued (4)Signed Off (2)Violation (1)Inspection (7)Special Inspection (24)
05/12/2026
Signed off — Alteration
INTERIOR PARTITION REARRANGEMENT ON THE FIRST FLOOR ONLY. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
S01017760-I1
05/12/2026
Signed off — Alteration
INTERIOR PARTITION REARRANGEMENT ON THE FIRST FLOOR ONLY. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
S01017760-S1
09/09/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/21/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/13/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
anthony santoro
08/13/2025
Special inspection requirement — Permanent certificate
anthony santoro
08/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
08/13/2025
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
08/13/2025
Special inspection requirement — HVAC-R and service water heating system controls
anthony santoro
08/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
08/13/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
anthony santoro
08/13/2025
Special inspection requirement — Tenant Protection Plan Compliance
anthony santoro
08/13/2025
Special inspection requirement — Construction Utilizing CLT or SCL, Type IV
anthony santoro
08/13/2025
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
08/13/2025
Special inspection requirement — Fire-Resistance Rated Construction
anthony santoro
08/13/2025
Special inspection requirement — Final
anthony santoro
08/13/2025
Special inspection requirement — Structural Wood Frame
anthony santoro
08/13/2025
Special inspection requirement — Air barrier - visual inspection
anthony santoro
08/13/2025
Special inspection requirement — Fireplaces
anthony santoro
08/13/2025
Special inspection requirement — Fenestration air leakage
anthony santoro
08/13/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
08/13/2025
Special inspection requirement — Insulation placement and R values
anthony santoro
08/13/2025
Special inspection requirement — Interior lighting power
anthony santoro
08/13/2025
Special inspection requirement — Fenestration areas
anthony santoro
07/31/2025
Filed — Alteration
INTERIOR PARTITION REARRANGEMENT ON THE FIRST FLOOR ONLY. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
S01017760-P1
07/31/2025
Filed — Alteration
INTERIOR PARTITION REARRANGEMENT ON THE FIRST FLOOR ONLY. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
S01017760-P2
05/23/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/06/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/06/2025
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
05/06/2025
Special inspection requirement — HVAC-R and service water heating system controls
anthony santoro
05/06/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
anthony santoro
05/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
05/01/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/26/2025
Permit issued — Structural
S01017760-I1-GC-CX
01/30/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/27/2025
Permit issued — General Construction
S01017760-I1-GC-CX
01/17/2025
Permit issued — Plumbing
S01017760-S1-PL
01/09/2025
Permit issued — Structural
S01017760-I1-GC-CX
04/05/2024
Filed — Alteration
INTERIOR PARTITION REARRANGEMENT ON THE FIRST FLOOR ONLY. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
S01017760-I1
04/05/2024
Filed — Alteration
INTERIOR PARTITION REARRANGEMENT ON THE FIRST FLOOR ONLY. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
S01017760-S1
12/03/1999
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offPAUL LOPA DESIGNS, INC02/26/2025
DOB NOWGeneral ConstructionSigned-offPAUL LOPA DESIGNS, INC01/27/2025
DOB NOWPlumbingSigned-offDJ PLUMBING & HEATING COR01/17/2025
DOB NOWStructuralSigned-offPAUL LOPA DESIGNS, INC01/09/2025
BISOTISSUEDKAMTECH RESTORATION CORP11/21/2022
BISPLISSUEDSTATEN ISLAND MECH LLC01/06/2000
BISEQISSUEDSLATER ASSOCIATES09/14/1999
BIS—ISSUEDSLATER ASSOCIATES09/14/1999
1 project · most recent 07/31/2025
Gas Water/Sanitary
FiledStatusContractorScope
07/31/2025Signed-offRITE-FLO P.H.& COOLING INGas, Water/Sanitary
4 projects · most recent 05/06/2025
General Wiring
FiledStatusContractorScope
05/06/2025CompleteRIDGE ELECTRIC CORP.General Wiring
08/20/2023CompletePOWERHOUSE ELEC'L CONT IGeneral Wiring
12/07/2022CompleteBERGER QUALITY ELEC'L CON—
06/20/2022CompletePOWERHOUSE ELEC'L CONT IGeneral Wiring
1 project · most recent 07/31/2025
Wood
FiledStatusContractorScope
07/31/2025Signed-offPAUL LOPA DESIGNS, INCWood
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
09/09/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/23/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/06/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/01/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/30/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/30/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
08/13/2025HVAC-R and service water piping design and insulationanthony santoroenergy_progress
08/13/2025Permanent certificateanthony santoroenergy_progress
08/13/2025Fire-Resistant Penetrations and Jointsanthony santorospecial
08/13/2025Energy Code Compliance Inspectionsanthony santoroprogress
08/13/2025HVAC-R and service water heating system controlsanthony santoroenergy_progress
08/13/2025Fire-Resistant Penetrations and Jointsanthony santorospecial
08/13/2025Structural Stability – Alterations of existing buildingsanthony santorospecial
08/13/2025Tenant Protection Plan Complianceanthony santorospecial
08/13/2025Construction Utilizing CLT or SCL, Type IVanthony santorospecial
08/13/2025Energy Code Compliance Inspectionsanthony santoroprogress
08/13/2025Fire-Resistance Rated Constructionanthony santoroprogress
08/13/2025Finalanthony santoroprogress
08/13/2025Structural Wood Frameanthony santoroprogress
08/13/2025Air barrier - visual inspectionanthony santoroenergy_progress
08/13/2025Fireplacesanthony santoroenergy_progress
08/13/2025Fenestration air leakageanthony santoroenergy_progress
08/13/2025Fenestration and door U-factor and product ratingsanthony santoroenergy_progress
08/13/2025Insulation placement and R valuesanthony santoroenergy_progress
08/13/2025Interior lighting poweranthony santoroenergy_progress
08/13/2025Fenestration areasanthony santoroenergy_progress
05/06/2025Energy Code Compliance Inspectionsanthony santoroprogress
05/06/2025HVAC-R and service water heating system controlsanthony santoroenergy_progress
05/06/2025HVAC-R and service water piping design and insulationanthony santoroenergy_progress
05/06/2025Fire-Resistant Penetrations and Jointsanthony santorospecial
▾Documents — 43 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/21/2026S01017760-P2Request digital key ↗
08/21/2026S01017760-I1Request digital key ↗
08/21/2026S01017760-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
11/18/2022540240951Open ↗
01/11/2018520321081Open ↗
▸BISWORK PERMIT APPLICATION1
11/21/2022540240951Open ↗
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026S01017760-I1Open ↗
09/01/2026S01017760-I1Open ↗
09/01/2026S01017760-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/13/2026S01017760-P2Open ↗
08/13/2026S01017760-I1Open ↗
08/13/2026S01017760-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026S01017760-I1Open ↗
09/01/2026S01017760-I1Open ↗
09/01/2026S01017760-P1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
11/18/2022540240951Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
01/11/2018520321081Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/11/2018520321081Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST1
01/11/2018520321081Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
11/21/2022540240951Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
01/19/2023540240951Open ↗
11/18/2022540240951Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
11/18/2022540240951Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
01/19/2023540240951Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
01/19/2023540240951Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
01/11/2018520321081Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
01/19/2023540240951Open ↗
11/18/2022540240951Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
01/23/2023540240951Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
01/11/2018520321081Open ↗
▸BISFINAL ELECTRICAL SIGNOFF1
01/23/2023540240951Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
01/19/2023540240951Open ↗
11/18/2022540240951Open ↗
01/11/2018520321081Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET1
01/11/2018520321081Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/18/2022540240951Open ↗
▸Other Documents1
▸BISTax Abatement Miscellaneous1
01/23/2023540240951Open ↗