| Firm | Filings | Most Recent |
|---|---|---|
| STEVEN R. SAVINO ARCHITECT PC | 5 | 03/13/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CAPITAL CONTR P&H CORP | Plumbing | 6 | 07/02/2026 |
| HI VOLTAGE ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| AJC RENOVATIONS LLC | General Contractor | 1 | 07/08/2026 |
| CAPITAL CONTR P H | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 4 | 03/13/2026 |
| STEVEN R. SAVINO ARCHIT | 1216 | 1 | 03/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | CAPITAL CONTR P&H CORP | 06/30/2026 |
| DOB NOW | Plumbing | Permit Issued | CAPITAL CONTR P&H CORP | 05/08/2025 |
| DOB NOW | General Construction | Permit Issued | AJC RENOVATIONS LLC | 05/01/2025 |
| BIS | — | ISSUED | AIR-MECHINICAL CORP | 09/01/2004 |
| BIS | — | ISSUED | AIR-MECHINICAL CORP | 03/08/2004 |
| BIS | — | ISSUED | AIR-MECHINICAL CORP | 09/05/2003 |
| BIS | PL | ISSUED | DYNAMIC CONTRACTING CORP | 12/02/2002 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Permit Issued | CAPITAL CONTR P&H CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2025 | Complete | HI VOLTAGE ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/08/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/25/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/13/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/17/2025 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 05/28/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/21/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/21/2025 | Certified Gas-Gas-Piping-Underground | Certified | View ↗ |
| 05/12/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/12/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/13/2026 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | anthony santoro | special |
| 03/13/2026 | On-Site Private Sewage Disposal Systems Installation | anthony santoro | special |
| 11/04/2025 | On-Site Private Sewage Disposal Systems Installation | anthony santoro | special |
| 11/04/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | anthony santoro | special |
| 08/15/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | anthony santoro | special |
| 08/15/2025 | On-Site Private Sewage Disposal Systems Installation | anthony santoro | special |
| 03/10/2025 | Concrete - Cast-In-Place | Steven Savino | special |
| 03/10/2025 | Subgrade Inspections | Steven Savino | special |
| 03/07/2025 | Final | Steven Savino | progress |