| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/11/2023 | Complete | ISLAND ELECTRIC CORP | — |
| 08/02/2021 | Complete | KJK ELECTRIC INC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| NATSKI ENTERPRISES | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MOMENTUM SOLAR | 1 | 12/28/2023 |
| WILLIAM MONTAGUE ENGINEER | 1 | 08/02/2023 |
| CHRIS PONISI, ARCHITECT | 4 | 03/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| DAWN PONISI | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUPERIOR PLUMBING & HEATING | Plumbing | 3 | 07/08/2026 |
| JEFFREY MARINELLO | Electrical | 1 | 03/21/2026 |
| CHRISTIAN CONSTRUCTION LL | General Contractor | 1 | 07/08/2026 |
| HIGH QUALITY CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| M. JORDAN GENERAL CONTRACTING | General Contractor | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MXV SIA LLC | 9281 | 1 | 12/28/2023 |
| A TECH ENGINEERING NYC, P | 6738 | 3 | 03/03/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | MOMENTUM SOLAR | 01/18/2024 |
| DOB NOW | Curb Cut | Signed-off | CHRISTIAN CONSTRUCTION LL | 09/07/2023 |
| DOB NOW | Plumbing | Signed-off | SUPERIOR PLUMBING & HEATI | 12/16/2022 |
| DOB NOW | Construction Fence | Signed-off | M. JORDAN GENERAL CONTRAC | 07/20/2022 |
| DOB NOW | Plumbing | Signed-off | SUPERIOR PLUMBING & HEATI | 06/07/2022 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 03/03/2021 |
| DOB NOW | Construction Fence | Signed-off | HIGH QUALITY CONSTRUCTION | 08/14/2020 |
| BIS | — | ISSUED | M. JORDAN GENERAL CONTRACTING | 07/27/2022 |
| BIS | PL | ISSUED | SUPERIOR PLUMBING & HEATING | 04/12/2022 |
| BIS | — | ISSUED | BNA SERVICES INC | 07/07/2021 |
| BIS | — | ISSUED | BNA SERVICES INC | 11/13/2020 |
| BIS | — | ISSUED | HIGH QUALITY CONSTRUCTION | 09/18/2020 |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/12/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 03/08/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/21/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/16/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/11/2023 | Air barrier - visual inspection | Mina Makar | energy_progress |
| 12/11/2023 | Fire-Resistant Penetrations and Joints | Mina Makar | special |
| 12/11/2023 | Structural Stability – Alterations of existing buildings | Mina Makar | special |
| 12/11/2023 | Energy Code Compliance Inspections | Mina Makar | progress |
| 12/11/2023 | Final | Mina Makar | progress |
| 03/06/2023 | Maintenance information | WILLIAM MONTAGUE | energy_progress |
| 03/06/2023 | HVAC and service water heating equipment | WILLIAM MONTAGUE | energy_progress |
| 03/06/2023 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 03/06/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | anthony santoro | special |
| 03/06/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | anthony santoro | special |
| 03/06/2023 | Energy Code Compliance Inspections | WILLIAM MONTAGUE | progress |
| 03/06/2023 | HVAC insulation and sealing | WILLIAM MONTAGUE | energy_progress |
| 03/03/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | anthony santoro | special |
| 03/03/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | anthony santoro | special |
| 03/03/2023 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 03/03/2023 | Energy Code Compliance Inspections | anthony santoro | progress |
| 03/03/2023 | HVAC insulation and sealing | anthony santoro | energy_progress |
| 03/03/2023 | HVAC and service water heating equipment | anthony santoro | energy_progress |
| 03/03/2023 | Maintenance information | anthony santoro | energy_progress |