2020Year Built
1Stories
K1Building Class
R6BZoning
8,404 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
One story retail building · Owner of record: 223 CANAL CORP. · 17,512 sf lot · 0.48 FAR built · Flood zone X
Locations of Work
MechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction4p · 1 filing · 20 docs
Floor 1Under Construction5p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
9612 LIBERTY CORP503/22/2026
NICOOSI BROS INC203/22/2026
223 CANAL1203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SQUARE ARCH, LLC404/06/2026
DOYUN KIM; RA110/04/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KC EXPEDITING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AMERICAN STANDARD PLUMBING &Fire Protection107/08/2026
NY BUILDING ASSOCIATES INGeneral Contractor104/09/2026
AMERICAN STANDARD P&H CORORP.Plumbing107/08/2026
NEPTUNE SIGNS AWNINGSScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244304/06/2026
SQ. ARCH, LLC4802404/06/2026
HUAN DESIGN INC7669111/24/2025
DOYUN KIM; RA7415110/04/2020
Building Lifecycle
All (54)Filed (5)Permit Issued (4)Signed Off (1)Violation (4)Inspection (15)Special Inspection (25)
06/05/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/02/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/07/2026
Special inspection requirement — HVAC-R and service water heating equipment
Kaijin Liang
04/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kaijin Liang
04/07/2026
Special inspection requirement — Sprinkler Systems
NARESH MAHANGU
04/07/2026
Special inspection requirement — Energy Code Compliance Inspections
Kaijin Liang
04/07/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Kaijin Liang
04/07/2026
Special inspection requirement — HVAC-R and service water heating system controls
Kaijin Liang
04/06/2026
Filed — Alteration
RENOVATION OF PROPOSED LAUNDROMAT ESTABLISHMENT WITH, NEW/RELOCATE DRYER, WASHER AND SPRINKLER HEAD, TANKLESS HOT WATER HEATER, UNIT HEATER AND PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01313194-P2
03/31/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
03/26/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/26/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/26/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/25/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/17/2026
Filed — Alteration
RENOVATION OF PROPOSED LAUNDROMAT ESTABLISHMENT WITH, NEW/RELOCATE DRYER, WASHER AND SPRINKLER HEAD, TANKLESS HOT WATER HEATER, UNIT HEATER AND PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01313194-P1
03/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kaijin Liang
03/17/2026
Special inspection requirement — Sprinkler Systems
NARESH MAHANGU
03/17/2026
Special inspection requirement — Energy Code Compliance Inspections
Kaijin Liang
03/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
Kaijin Liang
03/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
Kaijin Liang
03/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Kaijin Liang
02/28/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/27/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/05/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/29/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
12/24/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/12/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
12/12/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/02/2025
Permit issued — Mechanical Systems
S01313194-I1-GC-CX
12/02/2025
Permit issued — Sprinklers
S01313194-S1-PL
12/02/2025
Permit issued — Sprinklers
S01313194-S1-EW-SP
11/24/2025
Filed — Alteration
RENOVATION OF PROPOSED LAUNDROMAT ESTABLISHMENT WITH, NEW/RELOCATE DRYER, WASHER AND SPRINKLER HEAD, TANKLESS HOT WATER HEATER, UNIT HEATER AND PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01313194-I1
11/24/2025
Filed — Alteration
RENOVATION OF PROPOSED LAUNDROMAT ESTABLISHMENT WITH, NEW/RELOCATE DRYER, WASHER AND SPRINKLER HEAD, TANKLESS HOT WATER HEATER, UNIT HEATER AND PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01313194-S1
11/04/2025
Special inspection requirement — Mechanical Systems
ZHENHUAN XU
11/04/2025
Special inspection requirement — Fenestration air leakage
Kaijin Liang
11/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Kaijin Liang
11/04/2025
Special inspection requirement — Final
Kaijin Liang
11/04/2025
Special inspection requirement — Energy Code Compliance Inspections
Kaijin Liang
11/04/2025
Special inspection requirement — Fire-Resistance Rated Construction
Kaijin Liang
11/04/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Kaijin Liang
11/04/2025
Special inspection requirement — HVAC-R and service water heating equipment
Kaijin Liang
11/04/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Kaijin Liang
11/04/2025
Special inspection requirement — Air barrier - visual inspection
Kaijin Liang
11/04/2025
Special inspection requirement — Fenestration areas
Kaijin Liang
11/04/2025
Special inspection requirement — HVAC-R and service water heating system controls
Kaijin Liang
11/04/2025
Special inspection requirement — Interior lighting power
Kaijin Liang
05/06/2025
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
05/05/2021
Signed off — Alteration
S00408123-I1
10/31/2020
Permit issued — Sign
S00408123-I1-SG
10/04/2020
Filed — Alteration
S00408123-I1
03/25/2019
Violation issued (ECB, closed)
Construction
03/09/2019
Violation issued (ECB, closed)
Construction
02/15/2007
Violation issued (ECB, closed)
Construction
02/09/2007
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedNY BUILDING ASSOCIATES IN12/02/2025
DOB NOWSprinklersPermit IssuedAMERICAN STANDARD P&H CORORP.12/02/2025
DOB NOWSprinklersPermit IssuedAMERICAN STANDARD PLUMBIN12/02/2025
DOB NOWSignSigned-offNEPTUNE SIGNS&AWNINGS INC10/31/2020
BIS—ISSUEDEMPIRE GROUP NYC LLC01/21/2021
BISPLISSUEDEH PLUMBING & HEATING COR07/14/2020
BISSPISSUEDEMPIRE WATER MAIN&SEWER I06/09/2020
BIS—ISSUEDNON LIMITE INC04/17/2020
BISPLISSUEDWEST SHORE CONSULTING INC03/18/2020
BISEQISSUEDNICOLOSI BROS INC01/15/2020
BIS—ISSUEDNICOLOSI BROS INC03/25/2019
BIS—ISSUEDNICOLOSI BROS INC03/19/2019
BISPLISSUEDWEST SHORE CONSULTING INC12/06/2018
BISEQISSUEDNICOLOSI BROS INC10/22/2018
BIS—ISSUEDNICOLOSI BROS INC10/22/2018
1 project · most recent 04/06/2026
Air Conditioning Systems
FiledStatusContractorScope
04/06/2026Permit IssuedNY BUILDING ASSOCIATES INAir Conditioning Systems
1 project · most recent 04/06/2026
Sprinkler System
FiledStatusContractorScope
04/06/2026Permit IssuedAMERICAN STANDARD PLUMBINSprinkler System
1 project · most recent 04/06/2026
Gas Water/Sanitary
FiledStatusContractorScope
04/06/2026Permit IssuedAMERICAN STANDARD P&H CORGas, Water/Sanitary
4 projects · most recent 04/13/2026
General Wiring
FiledStatusContractorScope
04/13/2026Permit IssuedERIC & NG ELEC'L, INC.2 meters, 1 new_meters
01/02/2026Permit IssuedERIC & NG ELEC'L, INC.General Wiring
08/10/2020CompleteAMRA ELECTRICAL CORPGeneral Wiring
06/08/2020CompleteFICHERA ELECTRIC, INC—
▾Field Inspections (DOB CAP) — 15
DateTypeResultReport
06/05/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/02/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/31/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/26/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/26/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/26/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/25/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/28/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/27/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/05/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/29/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
12/24/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/12/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/12/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/06/2025Certified Sprinkler - SP - RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
04/07/2026HVAC-R and service water heating equipmentKaijin Liangenergy_progress
04/07/2026Fire-Resistant Penetrations and JointsKaijin Liangspecial
04/07/2026Sprinkler SystemsNARESH MAHANGUspecial
04/07/2026Energy Code Compliance InspectionsKaijin Liangprogress
04/07/2026HVAC-R and service water piping design and insulationKaijin Liangenergy_progress
04/07/2026HVAC-R and service water heating system controlsKaijin Liangenergy_progress
03/17/2026Fire-Resistant Penetrations and JointsKaijin Liangspecial
03/17/2026Sprinkler SystemsNARESH MAHANGUspecial
03/17/2026Energy Code Compliance InspectionsKaijin Liangprogress
03/17/2026HVAC-R and service water heating equipmentKaijin Liangenergy_progress
03/17/2026HVAC-R and service water heating system controlsKaijin Liangenergy_progress
03/17/2026HVAC-R and service water piping design and insulationKaijin Liangenergy_progress
11/04/2025Mechanical SystemsZHENHUAN XUspecial
11/04/2025Fenestration air leakageKaijin Liangenergy_progress
11/04/2025Fire-Resistant Penetrations and JointsKaijin Liangspecial
11/04/2025FinalKaijin Liangprogress
11/04/2025Energy Code Compliance InspectionsKaijin Liangprogress
11/04/2025Fire-Resistance Rated ConstructionKaijin Liangprogress
11/04/2025Fenestration and door U-factor and product ratingsKaijin Liangenergy_progress
11/04/2025HVAC-R and service water heating equipmentKaijin Liangenergy_progress
11/04/2025HVAC-R and service water piping design and insulationKaijin Liangenergy_progress
11/04/2025Air barrier - visual inspectionKaijin Liangenergy_progress
11/04/2025Fenestration areasKaijin Liangenergy_progress
11/04/2025HVAC-R and service water heating system controlsKaijin Liangenergy_progress
11/04/2025Interior lighting powerKaijin Liangenergy_progress
▾Documents — 168 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch4
08/17/2026S01313194-P2Request digital key ↗
08/17/2026S01313194-P1Request digital key ↗
08/17/2026S01313194-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sign1
08/25/2026S00408123-I1Request digital key ↗
▸Applications & Permits26
▸BISPLAN / WORK APPROVAL APPLICATION13
09/06/2023520279868Open ↗
02/05/2021520304420Open ↗
02/04/2021520304420Open ↗
Showing 3 of 13 on file for this type
▸BISWORK PERMIT APPLICATION11
01/26/2021520279868Open ↗
07/14/2020540135520Open ↗
06/09/2020540135520Open ↗
Showing 3 of 11 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
01/16/2018520304420Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
06/16/2021520279868Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT2
01/20/2018520279868Open ↗
07/25/2017520279868Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
06/16/2017520304420Open ↗
▸BISVERIFY TAX LOT1
01/16/2024520279868Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
05/17/2021520279868Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
05/17/2021520279868Open ↗
▸BISZONING DIAGRAM1
01/20/2018520279868Open ↗
▸Seals & Professional Certifications31
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
06/26/2019520279868Open ↗
06/26/2019520279868Open ↗
05/21/2019520279868Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/23/2026S01313194-S1Open ↗
09/23/2026S01313194-S1Open ↗
09/01/2026S01313194-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/23/2026S01313194-S1Open ↗
09/23/2026S01313194-S1Open ↗
09/01/2026S01313194-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/25/2026S00408123-I1Open ↗
08/17/2026S01313194-S1Open ↗
08/17/2026S01313194-P2Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
09/22/2017540135520Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/22/2017540135520Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
09/22/2017540135520Open ↗
▸Trade Schedules & Equipment9
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE4
12/12/2018520279868Open ↗
12/07/2018520279868Open ↗
08/01/2017520279868Open ↗
Showing 3 of 4 on file for this type
▸BISSEWER CONNECTION: DEP SD1 & SD21
01/20/2018520279868Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
05/17/2021520279868Open ↗
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
05/17/2021520279868Open ↗
▸BISRPZ/DDCV TEST REPORT : GEN215B1
06/16/2021540135520Open ↗
▸BISSCHEDULE B - PLUMBING1
09/22/2017540135520Open ↗
▸Safety & Tenant Protection6
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE2
01/26/2021520279868Open ↗
10/22/2018520279868Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
07/25/2017520279868Open ↗
▸BISSTREET TREE CHECKLIST1
05/02/2017520279868Open ↗
▸BISSTREET TREE SIGNOFF1
09/28/2023520279868Open ↗
▸BISSTREET TREES SITE PLAN1
08/10/2023520279868Open ↗
▸Environmental & Asbestos12
▸DOB NOWOER: Notice to Proceed6
08/17/2026S01313194-S1Open ↗
08/17/2026S01313194-P2Open ↗
08/13/2026S01313194-P1Open ↗
Showing 3 of 6 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION3
06/16/2021540135520Open ↗
05/17/2021520304420Open ↗
05/17/2021520279868Open ↗
▸DOB NOWOER: Notice of Satisfaction3
08/13/2026S00408123-I1Open ↗
08/13/2026S01313194-S1Open ↗
08/13/2026S01313194-I1Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
06/26/2019520279868Open ↗
06/26/2019520279868Open ↗
05/21/2019520279868Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
03/24/2021520279868Open ↗
▸BISTR8 INSPECTOR TO CERTIFY THAT AS-BUILT CONDITIONS REFLECT THE COMPLETE APPROVEDECC AUDIT DOCUMENTS1
12/08/2023520279868Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
05/17/2021520279868Open ↗
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY3
03/24/2021540135520Open ↗
03/24/2021520279868Open ↗
09/22/2017540135520Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
01/16/2018520304420Open ↗
▸BISHYDRO FLOW TEST LETTER1
09/22/2017540135520Open ↗
▸BISSOIL PERCOLATE TEST-DRY WELL RS16-P1131
01/20/2018520279868Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
10/22/2018520279868Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
01/20/2018520279868Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
10/22/2018520279868Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
09/22/2017540135520Open ↗
▸BISDEMOLITION (DM) JOB SIGNOFF1
09/28/2023520279868Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
06/16/2021520279868Open ↗
▸Approvals, Objections & Sign-offs11
▸BISSCHEDULE A - OCCUPANCY / USE4
07/24/2018520279868Open ↗
06/12/2018520279868Open ↗
08/01/2017520279868Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
06/16/2017520304420Open ↗
05/02/2017520279868Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
04/20/2020520279868Open ↗
01/16/2018520304420Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
01/16/2018520304420Open ↗
▸BISSUPERSEDING LETTER1
05/05/2020520279868Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
06/14/2023540135520Open ↗
▸Cost, Insurance & Ownership6
▸BISPROJECT-SPECIFIC GL INSURANCE3
01/26/2021520279868Open ↗
03/26/2019520279868Open ↗
10/22/2018520279868Open ↗
▸BISCOST AFFIDAVIT1
09/22/2017540135520Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
06/16/2021540135520Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
01/26/2021520279868Open ↗
▸Filing & Intake Forms24
▸BISADDITIONAL INFORMATION13
09/29/2023520279868Open ↗
05/19/2021520304420Open ↗
02/25/2021520304420Open ↗
Showing 3 of 13 on file for this type
▸BISBOROUGH INTAKE FORM8
01/26/2021520279868Open ↗
06/26/2019520279868Open ↗
05/21/2019520279868Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING COVER SHEET2
06/16/2017520304420Open ↗
05/02/2017520279868Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
09/22/2017540135520Open ↗
▸Other Documents8
▸BISPLOT DIAGRAM2
06/16/2017520304420Open ↗
05/02/2017520279868Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION2
05/19/2021520304420Open ↗
05/19/2021520304420Open ↗
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form1
12/28/2017520304420Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
01/20/2018520279868Open ↗
▸BISWAIVER OF CURB ALIGNMENT1
02/25/2021520304420Open ↗
▸BISSTREET: NEW NAME APPROVED1
05/17/2021520279868Open ↗