← Back
STATEN ISLAND
46GAR KISSEL AVENUE
STATEN ISLAND · BIN 5174955
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Flood zone X500
Locations of Work
Architecture
Floor 12p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SCAGLIONE ARCHITECTS207/07/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MAXIMUM CONTRACTING INCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738207/07/2023
Building Lifecycle
All (23)Filed (2)Permit Issued (1)Inspection (2)Objection (2)Special Inspection (16)
07/10/2023
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
07/10/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
07/10/2023
Special inspection requirement — Subgrade Inspections
anthony santoro
07/10/2023
Special inspection requirement — Masonry
anthony santoro
07/10/2023
Special inspection requirement — Footing and Foundation
anthony santoro
07/10/2023
Special inspection requirement — Lowest Floor Elevation
anthony santoro
07/10/2023
Special inspection requirement — Final
anthony santoro
07/10/2023
Special inspection requirement — Exterior lighting power
anthony santoro
07/07/2023
Filed — New Building
application filed to construct a slab on grade masonry detached two (2) car garage in conjunction with new building applic # 520360582
S00547013-P2
07/07/2023
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
07/07/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
07/07/2023
Special inspection requirement — Masonry
anthony santoro
07/07/2023
Special inspection requirement — Subgrade Inspections
anthony santoro
07/07/2023
Special inspection requirement — Final
anthony santoro
07/07/2023
Special inspection requirement — Footing and Foundation
anthony santoro
07/07/2023
Special inspection requirement — Lowest Floor Elevation
07/07/2023
Special inspection requirement — Exterior lighting power
anthony santoro
05/05/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/30/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/29/2022
Permit issued — General Construction
S00547013-I1-GC-CX
06/07/2022
Objection raised — Scope
06/07/2022
Objection resolved — Addressed
05/16/2022
Filed — New Building
application filed to construct a slab on grade masonry detached two (2) car garage in conjunction with new building applic # 520360582
S00547013-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedMAXIMUM CONTRACTING INC06/29/2022
1 project · most recent 05/21/2023
General Wiring
FiledStatusContractorScope
05/21/2023CompleteSAUSE ELECTRIC CO.General Wiring
1 project · most recent 07/07/2023
FiledStatusContractorScope
07/07/2023Permit IssuedMAXIMUM CONTRACTING INC2 scope_items
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
05/05/2023Pass-Final CND-Occupancy InspectionPassView ↗
01/30/2023Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
07/10/2023Concrete - Cast-In-Placeanthony santorospecial
07/10/2023Fire-Resistant Penetrations and Jointsanthony santorospecial
07/10/2023Subgrade Inspectionsanthony santorospecial
07/10/2023Masonryanthony santorospecial
07/10/2023Footing and Foundationanthony santoroprogress
07/10/2023Lowest Floor Elevationanthony santoroprogress
07/10/2023Finalanthony santoroprogress
07/10/2023Exterior lighting poweranthony santoroenergy_progress
07/07/2023Concrete - Cast-In-Placeanthony santorospecial
07/07/2023Fire-Resistant Penetrations and Jointsanthony santorospecial
07/07/2023Masonryanthony santorospecial
07/07/2023Subgrade Inspectionsanthony santorospecial
07/07/2023Finalanthony santoroprogress
07/07/2023Footing and Foundationanthony santoroprogress
07/07/2023Lowest Floor Elevation—progress
07/07/2023Exterior lighting poweranthony santoroenergy_progress
▾Documents — 30 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/23/2026S00547013-P2Request digital key ↗
08/14/2026S00547013-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026S00547013-P2Open ↗
08/13/2026S00547013-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026S00547013-I1Open ↗
08/13/2026S00547013-P2Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00547013-I1Open ↗
▸Seals & Professional Certifications9
▸DOB NOWProgress Inspector Seal & Signature5
09/23/2026S00547013-P2Open ↗
09/23/2026S00547013-P2Open ↗
08/24/2026S00547013-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/23/2026S00547013-P2Open ↗
08/24/2026S00547013-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/23/2026S00547013-P2Open ↗
08/23/2026S00547013-I1Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026S00547013-I1Open ↗
08/13/2026S00547013-P2Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/13/2026S00547013-I1Open ↗
08/13/2026S00547013-P2Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026S00547013-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026S00547013-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00547013-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026S00547013-I1Open ↗
▸Other Documents6
▸DOB NOWSite Survey: Initial2
08/13/2026S00547013-P2Open ↗
08/13/2026S00547013-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026S00547013-P2Open ↗
08/13/2026S00547013-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026S00547013-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026S00547013-I1Open ↗