| Owner | Filings | Most Recent |
|---|---|---|
| SAMS TRUST | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 1 | 04/02/2024 |
| ROGERS CALVANICO GROUP PLLC | 7 | 08/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| BROOKLYN SOLARWORKS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BROOKLYN SOLARWORKS LLC | General Contractor | 2 | 03/21/2026 |
| HUDSON CONTRACTING GROUP | General Contractor | 2 | 07/08/2026 |
| PHOENIX PLMBG & MECH CORP | Fire Protection | 1 | 07/08/2026 |
| RIDGE ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| ARCO PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| ARCO PLBG AND HTG INC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 1 | 04/02/2024 |
| A TECH ENGINEERING NYC, P | 6738 | 1 | 03/11/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | BROOKLYN SOLARWORKS LLC | 04/10/2024 |
| DOB NOW | Curb Cut | Signed-off | HUDSON CONTRACTING GROUP | 12/26/2023 |
| DOB NOW | Construction Fence | Signed-off | HUDSON CONTRACTING GROUP | 10/05/2023 |
| DOB NOW | Sprinklers | Signed-off | GW MECHANICAL CORP | 05/12/2022 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 10/04/2021 |
| DOB NOW | Sprinklers | Signed-off | ARCO PLBG AND HTG INC | 09/24/2021 |
| DOB NOW | Plumbing | Signed-off | ARCO PLBG AND HTG INC | 09/24/2021 |
| BIS | — | ISSUED | ALCO STORE DEVELOPMENT CORP | 02/01/2023 |
| BIS | — | ISSUED | ALCO STORE DEVELOPMENT CORP | 06/20/2022 |
| BIS | — | ISSUED | ALCO STORE DEVELOPMENT CORP | 01/31/2022 |
| BIS | — | ISSUED | ALCO STORE DEVELOPMENT CORP | 08/09/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/29/2024 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| 07/23/2023 | Complete | RIDGE ELECTRIC CORP. | General Wiring |
| 11/02/2021 | Cancelled | RIDGE ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/12/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 07/17/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/20/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/14/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/08/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/11/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/11/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/29/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/20/2021 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 10/13/2021 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/22/2024 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 03/22/2024 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 03/22/2024 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 03/22/2024 | Final | NARESH MAHANGU | progress |
| 03/22/2024 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 03/09/2021 | Sprinkler Systems | anthony santoro | special |