| Owner | Filings | Most Recent |
|---|---|---|
| 34 MOUNTAINVIEW LLC | 19 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 04/10/2024 |
| SCAGLIONE ARCHITECTS | 6 | 02/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| C P DESIGN CONSULTANTS | 6 | 03/21/2026 |
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DAE DEVELOPMENT CORP | General Contractor | 4 | 03/21/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 07/08/2026 |
| M. EARLY PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 04/10/2024 |
| ROGERS CALVANICO GROUP PL | 1324 | 4 | 02/03/2023 |
| A TECH ENGINEERING NYC, P | 6738 | 2 | 11/11/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 04/17/2024 |
| DOB NOW | Curb Cut | Signed-off | DAE DEVELOPMENT CORP | 12/06/2022 |
| DOB NOW | Structural | Permit Issued | DAE DEVELOPMENT CORP | 08/24/2022 |
| DOB NOW | Plumbing | Signed-off | M. EARLY PLBG & HTG CORP | 07/19/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/10/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 09/23/2022 | Complete | MANGI ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/07/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/07/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/23/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 12/19/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/19/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/30/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/21/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/18/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 03/18/2024 | Final | Walid Abdulla | progress |
| 03/18/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 03/18/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 03/18/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 12/29/2022 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 12/29/2022 | Energy Code Compliance Inspections | Richard Dailey | progress |
| 12/29/2022 | Final | Richard Dailey | progress |
| 12/29/2022 | Fire-Resistance Rated Construction | Richard Dailey | progress |
| 12/29/2022 | Footing and Foundation | Richard Dailey | progress |
| 12/29/2022 | Fenestration and door U-factor and product ratings | Richard Dailey | energy_progress |
| 12/29/2022 | Air barrier — testing | Richard Dailey | energy_progress |
| 12/29/2022 | Lighting in dwelling units | Richard Dailey | energy_progress |
| 12/29/2022 | Fenestration areas | Richard Dailey | energy_progress |
| 12/29/2022 | Air barrier - visual inspection | Richard Dailey | energy_progress |
| 12/29/2022 | Concrete - Cast-In-Place | Richard Dailey | special |
| 12/29/2022 | HVAC-R and service water heating system controls | Richard Dailey | energy_progress |
| 12/29/2022 | HVAC-R and service water heating equipment | Richard Dailey | energy_progress |
| 12/29/2022 | Permanent certificate | Richard Dailey | energy_progress |
| 12/29/2022 | Fenestration air leakage | Richard Dailey | energy_progress |
| 12/29/2022 | Shutoff dampers | Richard Dailey | energy_progress |
| 12/29/2022 | HVAC-R and service water piping design and insulation | Richard Dailey | energy_progress |
| 12/29/2022 | Insulation placement and R values | Richard Dailey | energy_progress |
| 12/29/2022 | Maintenance information | Richard Dailey | energy_progress |
| 12/29/2022 | Fire-Resistant Penetrations and Joints | Richard Dailey | special |