0Year Built
—Stories
V0Building Class
R3-1Zoning
0 sfGross Floor Area
0Units
19 Open Violations ▸FDNY Report ↗
Zoned residential, not Manhattan · Owner of record: H&E TALES CONSTRUCTION LLC · 3,000 sf lot · 0 FAR built · Flood zone X
Locations of Work
PlumbingCivilGeneral
Permit Issued — active, not yet Signed-off
Floor 2Under Construction13p · 2 filings · 20 docs
Floor 1Under Construction14p · 2 filings · 20 docs
CellarUnder Construction12p · 2 filings · 20 docs
BasementUnder Construction1p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
RYAN DESIGN ARCHITECTURE410/07/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ALKA CONTRACTING INCGeneral Contractor104/11/2026
FLOW-RIGHT PLBG & HTG CORPlumbing109/09/2026
QUALITY PLUMBING, INCPlumbing108/30/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738103/10/2025
RYAN DESIGN ARCHITECTURE7159203/10/2025
Building Lifecycle
All (31)Filed (4)Permit Issued (3)Special Inspection (24)
09/08/2026
Permit issued — Plumbing
S67977126-S1-PL
08/27/2026
Permit issued — Plumbing
S00851650-S1-PL
04/09/2026
Permit issued — Earth Work
S00851650-I1-GC-CX
10/07/2025
Filed — New Building
CONSTRUCTION OF NEW 2 FAMILY SEMI DETACHED DWELLING IN COMPLIANCE WITH 2022 BUILDING CODE
S00851650-P1
10/06/2025
Special inspection requirement — Concrete - Cast-In-Place
10/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/06/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
10/06/2025
Special inspection requirement — Subgrade Inspections
10/06/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
10/06/2025
Special inspection requirement — Energy Code Compliance Inspections
10/06/2025
Special inspection requirement — Final
10/06/2025
Special inspection requirement — Fire-Resistance Rated Construction
10/06/2025
Special inspection requirement — Footing and Foundation
10/06/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
10/06/2025
Special inspection requirement — Air barrier — testing
10/06/2025
Special inspection requirement — Electric vehicle service equipment requirements
10/06/2025
Special inspection requirement — Insulation placement and R values
10/06/2025
Special inspection requirement — Air barrier - visual inspection
10/06/2025
Special inspection requirement — Fenestration areas
10/06/2025
Special inspection requirement — HVAC-R and service water heating equipment
10/06/2025
Special inspection requirement — Fenestration air leakage
10/06/2025
Special inspection requirement — HVAC-R and service water heating system controls
10/06/2025
Special inspection requirement — Interior lighting power
10/06/2025
Special inspection requirement — Metering
10/06/2025
Special inspection requirement — Protection of exposed foundation insulation
10/06/2025
Special inspection requirement — Permanent certificate
10/06/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
10/06/2025
Special inspection requirement — Maintenance information
03/10/2025
Filed — New Building
CONSTRUCTION OF NEW 2 FAMILY SEMI DETACHED DWELLING IN COMPLIANCE WITH 2022 BUILDING CODE
S00851650-S1
11/08/2024
Filed — New Building
CONSTRUCTION OF NEW 2 FAMILY SEMI DETACHED DWELLING IN COMPLIANCE WITH 2022 BUILDING CODE
S00851650-S2
06/09/2023
Filed — New Building
CONSTRUCTION OF NEW 2 FAMILY SEMI DETACHED DWELLING IN COMPLIANCE WITH 2022 BUILDING CODE
S00851650-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedROCKLEDGE SCAFFOLD CORP09/08/2026
DOB NOWPlumbingPermit IssuedQUALITY PLUMBING, INC08/27/2026
DOB NOWEarth WorkPermit IssuedALKA CONTRACTING INC04/09/2026
1 project · most recent 10/07/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
10/07/2025Permit IssuedQUALITY PLUMBING, INCGas, Storm, Water/Sanitary
1 project · most recent 08/24/2026
General Wiring
FiledStatusContractorScope
08/24/2026Permit IssuedA2K ELECTRIC CORPGeneral Wiring
1 project · most recent 10/07/2025
FiledStatusContractorScope
10/07/2025Permit IssuedQUALITY PLUMBING, INC3 scope_items
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
10/06/2025Concrete - Cast-In-Place—special
10/06/2025Fire-Resistant Penetrations and Joints—special
10/06/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
10/06/2025Subgrade Inspections—special
10/06/2025Subsurface Investigations (Borings/Test Pits)—special
10/06/2025Energy Code Compliance Inspections—progress
10/06/2025Final—progress
10/06/2025Fire-Resistance Rated Construction—progress
10/06/2025Footing and Foundation—progress
10/06/2025HVAC-R and service water piping design and insulation—energy_progress
10/06/2025Air barrier — testing —energy_progress
10/06/2025Electric vehicle service equipment requirements—energy_progress
10/06/2025Insulation placement and R values—energy_progress
10/06/2025Air barrier - visual inspection—energy_progress
10/06/2025Fenestration areas—energy_progress
10/06/2025HVAC-R and service water heating equipment—energy_progress
10/06/2025Fenestration air leakage—energy_progress
10/06/2025HVAC-R and service water heating system controls—energy_progress
10/06/2025Interior lighting power—energy_progress
10/06/2025Metering—energy_progress
10/06/2025Protection of exposed foundation insulation—energy_progress
10/06/2025Permanent certificate—energy_progress
10/06/2025Fenestration and door U-factor and product ratings—energy_progress
10/06/2025Maintenance information—energy_progress
▾Documents — 40 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/20/2026S00851650-S1Request digital key ↗
08/20/2026S00851650-I1Request digital key ↗
08/20/2026S00851650-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits1
▸BISBPP-5 - Authorization to the Department of Transportation1
10/13/2022540234370Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-P1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-P1Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
10/13/2022540234370Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-S2Open ↗
08/13/2026S00851650-P1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
08/12/2022540234370Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/12/2022540234370Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-P1Open ↗
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00851650-I1Open ↗
▸Inspections & Test Reports7
▸DOB NOWSOIL REPORT3
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-S1Open ↗
08/13/2026S00851650-P1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026S00851650-S1Open ↗
08/13/2026S00851650-I1Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
08/12/2022540234370Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026S00851650-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
10/13/2022540234370Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
08/12/2022540234370Open ↗
▸Other Documents10
▸DOB NOWProperty Ownership Certification2
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-P1Open ↗
▸DOB NOWSite Survey: Initial2
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/20/2026S00851650-I1Open ↗
08/13/2026S00851650-P1Open ↗
▸BISWAIVER OF CURB/SIDEWALK ALIGNMENT1
10/13/2022540234370Open ↗
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form1
10/13/2022540234370Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
08/12/2022540234370Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026S00851650-I1Open ↗