ArchitectureStructuralPlumbingFire ProtectionCivilGeneral
Floor 211p · 1 filing · 20 docs
Floor 17p · 1 filing · 20 docs
Cellar7p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CPMG CUSTOM HOME BUILDERS1307/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ROGERS CALVANICO GROUP PLLC704/04/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ROGERS CALVANICO GROUP603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CPMG CUSTOM HOME BUILDERSGeneral Contractor507/08/2026
FINE MECHANICAL CORPPlumbing107/08/2026
QUALITY PLUMBING, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738304/04/2024
Building Lifecycle
All (57)Filed (7)Permit Issued (5)Signed Off (2)Inspection (11)Objection (2)Special Inspection (30)
04/08/2024
Special inspection requirement — HVAC-R and service water heating equipment
anthony santoro
04/08/2024
Special inspection requirement — Structural Steel - Details
anthony santoro
04/08/2024
Special inspection requirement — Structural Steel - Welding
anthony santoro
04/08/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
anthony santoro
04/08/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
anthony santoro
04/08/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
04/08/2024
Special inspection requirement — Subgrade Inspections
anthony santoro
04/08/2024
Special inspection requirement — Mechanical Systems
anthony santoro
04/08/2024
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
04/08/2024
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
04/08/2024
Special inspection requirement — Fire-Resistance Rated Construction
anthony santoro
04/08/2024
Special inspection requirement — Structural Wood Frame
anthony santoro
04/08/2024
Special inspection requirement — Footing and Foundation
anthony santoro
04/08/2024
Special inspection requirement — Final
anthony santoro
04/08/2024
Special inspection requirement — Air barrier - visual inspection
anthony santoro
04/08/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
anthony santoro
04/08/2024
Special inspection requirement — Interior lighting power
anthony santoro
04/08/2024
Special inspection requirement — Duct leakage testing, insulation and design
anthony santoro
04/08/2024
Special inspection requirement — Protection of exposed foundation insulation
anthony santoro
04/08/2024
Special inspection requirement — Insulation placement and R values
anthony santoro
04/08/2024
Special inspection requirement — Maintenance information
anthony santoro
04/08/2024
Special inspection requirement — Permanent certificate
anthony santoro
04/08/2024
Special inspection requirement — Ventilation and air distribution system
anthony santoro
04/08/2024
Special inspection requirement — Air barrier — testing
anthony santoro
04/08/2024
Special inspection requirement — HVAC-R and service water heating system controls
anthony santoro
04/08/2024
Special inspection requirement — Electric vehicle service equipment requirements
anthony santoro
04/08/2024
Special inspection requirement — Fenestration air leakage
anthony santoro
04/08/2024
Special inspection requirement — Metering
anthony santoro
04/08/2024
Special inspection requirement — Fenestration areas
anthony santoro
04/08/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
04/04/2024
Filed — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-P4
03/04/2024
Signed off — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-S2
02/28/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/28/2024
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
02/18/2024
Signed off — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-S1
01/09/2024
Permit issued — Curb Cut
S00857481-S2-CC
01/08/2024
Filed — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-P3
01/05/2024
Filed — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-S2
12/12/2023
Inspection — Certified Sprinkler (PL)-Sprinkler-Hydro
Certified
View inspection ↗
12/12/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/07/2023
Filed — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-P2
12/07/2023
Filed — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-P1
09/01/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/01/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/16/2023
Permit issued — Structural
S00857481-I1-GC-CX
06/23/2023
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
06/22/2023
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/12/2023
Permit issued — Plumbing
S72057990-S1-PL
05/26/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/18/2023
Permit issued — Plumbing
S00857481-S1-PL
05/15/2023
Filed — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-S1
05/15/2023
Permit issued — Earth Work
S00857481-I1-GC-CX
05/01/2023
Objection raised — Scope
05/01/2023
Objection resolved — Addressed
04/19/2023
Filed — New Building
CONSTRUCT DETACHED TWO FAMILY RESIDENCE WITH ACCESSORY OFF STREET PARKING FOR TWO CARS AND DETACHED ONE CAR GARAGE FILED UNDER SEPARATE APPLICATION.
S00857481-I1
08/25/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/12/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offCPMG CUSTOM HOME BUILDERS01/09/2024
DOB NOWStructuralPermit IssuedCPMG CUSTOM HOME BUILDERS08/16/2023
DOB NOWPlumbingSigned-offQUALITY PLUMBING, INC06/12/2023
DOB NOWPlumbingSigned-offFINE MECHANICAL CORP05/18/2023
DOB NOWEarth WorkPermit IssuedCPMG CUSTOM HOME BUILDERS05/15/2023
BISOTISSUEDJ.B.I. CONSTRUCTION GROUP10/17/2023
1 project · most recent 04/04/2024
Sprinkler System
FiledStatusContractorScope
04/04/2024——Sprinkler System
1 project · most recent 04/04/2024
Gas Plumbing-Sprinkler Storm Water/Sanitary
FiledStatusContractorScope
04/04/2024Signed-offFINE MECHANICAL CORPGas, Plumbing-Sprinkler, Storm, Water/Sanitary
2 projects · most recent 02/05/2024
General Wiring
FiledStatusContractorScope
02/05/2024CompleteA. J. CARUSO ELECTRICAL IGeneral Wiring
10/25/2023CompleteJSP ELECTL CNTNG CORP—
1 project · most recent 04/04/2024
Steel Wood
FiledStatusContractorScope
04/04/2024Signed-offCPMG CUSTOM HOME BUILDERSSteel, Wood
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
02/28/2024Pass-Final CND-Occupancy InspectionPassView ↗
02/28/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
12/12/2023Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
12/12/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/01/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/01/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/23/2023Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
06/22/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
05/26/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/25/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/12/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 60
DateRequirementInspectorRole
04/08/2024HVAC-R and service water heating equipmentanthony santoroenergy_progress
04/08/2024Structural Steel - Detailsanthony santorospecial
04/08/2024Structural Steel - Weldinganthony santorospecial
04/08/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installationanthony santorospecial
04/08/2024Subsurface Investigations (Borings/Test Pits)anthony santorospecial
04/08/2024Fire-Resistant Penetrations and Jointsanthony santorospecial
04/08/2024Subgrade Inspectionsanthony santorospecial
04/08/2024Mechanical Systemsanthony santorospecial
04/08/2024Concrete - Cast-In-Placeanthony santorospecial
04/08/2024Energy Code Compliance Inspectionsanthony santoroprogress
04/08/2024Fire-Resistance Rated Constructionanthony santoroprogress
04/08/2024Structural Wood Frameanthony santoroprogress
04/08/2024Footing and Foundationanthony santoroprogress
04/08/2024Finalanthony santoroprogress
04/08/2024Air barrier - visual inspectionanthony santoroenergy_progress
04/08/2024HVAC-R and service water piping design and insulationanthony santoroenergy_progress
04/08/2024Interior lighting poweranthony santoroenergy_progress
04/08/2024Duct leakage testing, insulation and designanthony santoroenergy_progress
04/08/2024Protection of exposed foundation insulationanthony santoroenergy_progress
04/08/2024Insulation placement and R valuesanthony santoroenergy_progress
04/08/2024Maintenance informationanthony santoroenergy_progress
04/08/2024Permanent certificateanthony santoroenergy_progress
04/08/2024Ventilation and air distribution systemanthony santoroenergy_progress
04/08/2024Air barrier — testing anthony santoroenergy_progress
04/08/2024HVAC-R and service water heating system controlsanthony santoroenergy_progress
Latest 25 of 60.
▾Documents — 71 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/23/2026S00857481-P4Request digital key ↗
08/23/2026S00857481-P3Request digital key ↗
08/23/2026S00857481-S2Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
10/16/2023540260091Open ↗
▸BISWORK PERMIT APPLICATION1
10/17/2023540260091Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸DOB NOWZoning Exhibit form (1-5)3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00857481-I1Open ↗
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/23/2026S00857481-P2Open ↗
08/23/2026S00857481-P1Open ↗
08/23/2026S00857481-S1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/24/2026S00857481-I1Open ↗
08/24/2026S00857481-I1Open ↗
08/24/2026S00857481-P4Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/24/2026S00857481-I1Open ↗
08/24/2026S00857481-I1Open ↗
08/24/2026S00857481-P4Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/16/2023540260091Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/16/2023540260091Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/16/2023540260091Open ↗
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
10/17/2023540260091Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026S00857481-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00857481-I1Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
11/28/2023540260091Open ↗
10/16/2023540260091Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/16/2023540260091Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
10/16/2023540260091Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
11/28/2023540260091Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/28/2023540260091Open ↗
▸Inspections & Test Reports6
▸DOB NOWSOIL REPORT3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY2
11/28/2023540260091Open ↗
10/16/2023540260091Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00857481-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISLETTERS - SUPPORTING DOCUMENTATION1
11/29/2023540260091Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
11/29/2023540260091Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
10/16/2023540260091Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
11/28/2023540260091Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
10/16/2023540260091Open ↗
▸Other Documents11
▸DOB NOWSite Survey: Initial3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸DOB NOWProperty Ownership Certification3
08/23/2026S00857481-P1Open ↗
08/14/2026S00857481-I1Open ↗
08/13/2026S00857481-P4Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
11/29/2023540260091Open ↗
▸DOB NOWFinal Survey1
08/13/2026S00857481-I1Open ↗