Locations of Work
ArchitectureStructural
Floor 21p · 1 filing · 20 docs
Floor 12p · 1 filing · 20 docs
Basement1p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STANLEY M. KREBUSHEVSKI, R.A.209/26/2024
C&P DESIGN CONSULTANTS209/23/2024
WILLIAM MONTAGUE ENGINEER101/24/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
D.R. CONTRACTINGGeneral Contractor1407/08/2026
LMS ELECTRICAL CORPElectrical103/22/2026
PREMIER PL,HTG & MECH INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SRA PLANNING & EXPEDITING5677309/26/2024
C&P DESIGN CONSULTANT8472109/23/2024
Building Lifecycle
All (71)Filed (5)Permit Issued (7)Signed Off (3)Inspection (12)Objection (14)Special Inspection (30)
04/07/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/07/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
03/07/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
03/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
02/12/2025
Signed off — New Building
PROPOSED 18' COMBINED CURB CUT - CURB CUT ALSO APPLIES TO 178 CHELSEA STREET - NB APPLICATION#S00872571
S00872570-S1
02/12/2025
Signed off — New Building
PROPOSED 18' COMBINED CURB CUT - CURB CUT ALSO APPLIES TO 178 CHELSEA STREET - NB APPLICATION#S00872571
S00872570-S2
10/28/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/18/2024
Signed off — New Building
PROPOSED 18' COMBINED CURB CUT - CURB CUT ALSO APPLIES TO 178 CHELSEA STREET - NB APPLICATION#S00872571
S00872570-S3
10/16/2024
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
10/11/2024
Special inspection requirement — Insulation placement and R values
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Maintenance information
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Air barrier — testing
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Interior lighting power
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Fenestration air leakage
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Electric vehicle service equipment requirements
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Permanent certificate
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Air barrier - visual inspection
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Concrete - Cast-In-Place
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Structural Steel - Welding
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Combustible Exterior Wall Coverings
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Subgrade Inspections
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Footing and Foundation
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Fire-Resistance Rated Construction
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Structural Wood Frame
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Final
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Metering
WILLIAM MONTAGUE
10/11/2024
Special inspection requirement — Fenestration areas
WILLIAM MONTAGUE
09/26/2024
Filed — New Building
PROPOSED 18' COMBINED CURB CUT - CURB CUT ALSO APPLIES TO 178 CHELSEA STREET - NB APPLICATION#S00872571
S00872570-P1
09/24/2024
Permit issued — Mechanical Systems
S00872570-S2-MS
09/23/2024
Filed — New Building
PROPOSED 18' COMBINED CURB CUT - CURB CUT ALSO APPLIES TO 178 CHELSEA STREET - NB APPLICATION#S00872571
S00872570-S2
09/05/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/04/2024
Permit issued — Foundation
S00872570-I1-GC
05/30/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
05/30/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/19/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
03/14/2024
Permit issued — Curb Cut
S00872570-S3-CC
03/13/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
03/08/2024
Permit issued — General Construction
S00872570-I1-ST
03/07/2024
Permit issued — Plumbing
S00872570-S1-PL
02/24/2024
Filed — New Building
PROPOSED 18' COMBINED CURB CUT - CURB CUT ALSO APPLIES TO 178 CHELSEA STREET - NB APPLICATION#S00872571
S00872570-S1
02/23/2024
Permit issued — General Construction
S00872570-I1-FO
02/21/2024
Permit issued — Structural
S00872570-I1-GC
01/24/2024
Filed — New Building
PROPOSED 18' COMBINED CURB CUT - CURB CUT ALSO APPLIES TO 178 CHELSEA STREET - NB APPLICATION#S00872571
S00872570-S3
01/20/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
WILLIAM MONTAGUE
01/20/2024
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM MONTAGUE
01/20/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
WILLIAM MONTAGUE
01/20/2024
Special inspection requirement — Maintenance information
WILLIAM MONTAGUE
01/20/2024
Special inspection requirement — Permanent certificate
WILLIAM MONTAGUE
01/20/2024
Special inspection requirement — HVAC-R and service water heating equipment
WILLIAM MONTAGUE
01/20/2024
Special inspection requirement — HVAC-R and service water heating system controls
WILLIAM MONTAGUE
01/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM MONTAGUE
01/12/2024
Objection resolved — Addressed
11/06/2023
Objection resolved — Addressed
11/04/2023
Objection resolved — Addressed
11/04/2023
Objection resolved — Addressed
Latest 60 of 71 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offD.R. CONTRACTING09/24/2024
DOB NOWFoundationPermit IssuedD.R. CONTRACTING09/04/2024
DOB NOWCurb CutSigned-offD.R. CONTRACTING03/14/2024
DOB NOWGeneral ConstructionSigned-offD.R. CONTRACTING03/08/2024
DOB NOWPlumbingSigned-offPREMIER PL,HTG & MECH INC03/07/2024
DOB NOWGeneral ConstructionSigned-offD.R. CONTRACTING02/23/2024
DOB NOWStructuralPermit IssuedD.R. CONTRACTING02/21/2024
1 project · most recent 06/06/2024
General Wiring
FiledStatusContractorScope
06/06/2024CompleteLMS ELECTRICAL CORPGeneral Wiring
1 project · most recent 09/26/2024
Wood
FiledStatusContractorScope
09/26/2024Signed-offD.R. CONTRACTINGWood
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
04/07/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/07/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
03/07/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
03/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/07/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/28/2024Pass-Final CND-Occupancy InspectionPassView ↗
10/16/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
09/05/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/30/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
05/30/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/19/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
03/13/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
10/11/2024Insulation placement and R valuesWILLIAM MONTAGUEenergy_progress
10/11/2024Maintenance informationWILLIAM MONTAGUEenergy_progress
10/11/2024Air barrier — testing WILLIAM MONTAGUEenergy_progress
10/11/2024Interior lighting powerWILLIAM MONTAGUEenergy_progress
10/11/2024Fenestration air leakageWILLIAM MONTAGUEenergy_progress
10/11/2024Electric vehicle service equipment requirementsWILLIAM MONTAGUEenergy_progress
10/11/2024Fenestration and door U-factor and product ratingsWILLIAM MONTAGUEenergy_progress
10/11/2024Permanent certificateWILLIAM MONTAGUEenergy_progress
10/11/2024Air barrier - visual inspectionWILLIAM MONTAGUEenergy_progress
10/11/2024Subsurface Investigations (Borings/Test Pits)WILLIAM MONTAGUEspecial
10/11/2024Fire-Resistant Penetrations and JointsWILLIAM MONTAGUEspecial
10/11/2024Concrete - Cast-In-PlaceWILLIAM MONTAGUEspecial
10/11/2024Structural Steel - WeldingWILLIAM MONTAGUEspecial
10/11/2024Combustible Exterior Wall CoveringsWILLIAM MONTAGUEspecial
10/11/2024Subgrade InspectionsWILLIAM MONTAGUEspecial
10/11/2024Footing and FoundationWILLIAM MONTAGUEprogress
10/11/2024Fire-Resistance Rated ConstructionWILLIAM MONTAGUEprogress
10/11/2024Energy Code Compliance InspectionsWILLIAM MONTAGUEprogress
10/11/2024Structural Wood FrameWILLIAM MONTAGUEprogress
10/11/2024FinalWILLIAM MONTAGUEprogress
10/11/2024MeteringWILLIAM MONTAGUEenergy_progress
10/11/2024Fenestration areasWILLIAM MONTAGUEenergy_progress
01/20/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationWILLIAM MONTAGUEspecial
01/20/2024Energy Code Compliance InspectionsWILLIAM MONTAGUEprogress
01/20/2024HVAC-R and service water piping design and insulationWILLIAM MONTAGUEenergy_progress
Latest 25 of 30.
▾Documents — 45 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/20/2026S00872570-P1Request digital key ↗
08/20/2026S00872570-S3Request digital key ↗
08/20/2026S00872570-S2Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits1
▸BISBPP-5 - Authorization to the Department of Transportation1
06/14/2023540251172Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026S00872570-P1Open ↗
08/13/2026S00872570-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026S00872570-I1Open ↗
08/13/2026S00872570-P1Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
06/02/2023540251172Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00872570-I1Open ↗
▸Seals & Professional Certifications14
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/20/2026S00872570-P1Open ↗
08/20/2026S00872570-S3Open ↗
08/20/2026S00872570-S2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/27/2026S00872570-S1Open ↗
08/27/2026S00872570-S1Open ↗
08/26/2026S00872570-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/27/2026S00872570-S1Open ↗
08/26/2026S00872570-I1Open ↗
08/26/2026S00872570-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
06/02/2023540251172Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/02/2023540251172Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026S00872570-P1Open ↗
08/13/2026S00872570-I1Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/13/2026S00872570-I1Open ↗
08/13/2026S00872570-P1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026S00872570-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00872570-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026S00872570-I1Open ↗
▸Inspections & Test Reports4
▸DOB NOWSOIL REPORT2
08/13/2026S00872570-I1Open ↗
08/13/2026S00872570-P1Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
06/02/2023540251172Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00872570-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
06/14/2023540251172Open ↗
▸Other Documents7
▸DOB NOWSite Survey: Initial2
08/13/2026S00872570-P1Open ↗
08/13/2026S00872570-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026S00872570-P1Open ↗
08/13/2026S00872570-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/20/2026S00872570-P1Open ↗
08/20/2026S00872570-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
06/02/2023540251172Open ↗