| Owner | Filings | Most Recent |
|---|---|---|
| WALLACE AVENUE CONSTRUCTION | 11 | 07/08/2026 |
| WALLACE AVENUE CONST.LLC | 5 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JOSEPH M. MORACE, A.I.A., ARCHITECT | 3 | 04/17/2025 |
| ISLAND ENGINEERING ASSOCIATES | 5 | 04/08/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| PATRICIA L. GASS | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WALLACE AVENUE CONSTR LLC | General Contractor | 6 | 03/21/2026 |
| DUO PLUMBING & HTG CORP. | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ISLAND ENGINEERING ASSOCI | 264 | 2 | 04/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | WALLACE AVENUE CONSTR LLC | 04/08/2025 |
| DOB NOW | Plumbing | Signed-off | DUO PLUMBING & HTG CORP. | 10/11/2024 |
| DOB NOW | Foundation | Permit Issued | WALLACE AVENUE CONSTR LLC | 09/25/2024 |
| DOB NOW | Plumbing | Signed-off | DUO PLUMBING & HTG CORP. | 09/05/2024 |
| DOB NOW | Construction Fence | Signed-off | WALLACE AVENUE CONSTR LLC | 03/14/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/01/2024 | — | — | 30 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/17/2025 | Signed-off | DUO PLUMBING & HTG CORP. | Storm, Water/Sanitary |
| 03/01/2024 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2024 | Complete | A. J. CARUSO ELECTRICAL I | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/10/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/07/2025 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 04/07/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/31/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 03/31/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/16/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/16/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/18/2025 | Mechanical Systems | WILLIAM DURDEN, P.E. | special |
| 04/18/2025 | Fire-Resistant Penetrations and Joints | WILLIAM DURDEN, P.E. | special |
| 04/18/2025 | Subsurface Investigations (Borings/Test Pits) | WILLIAM DURDEN, P.E. | special |
| 04/18/2025 | Subgrade Inspections | WILLIAM DURDEN, P.E. | special |
| 04/18/2025 | Concrete - Cast-In-Place | WILLIAM DURDEN, P.E. | special |
| 04/18/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | WILLIAM DURDEN, P.E. | special |
| 04/18/2025 | Final | WILLIAM DURDEN, P.E. | progress |
| 04/18/2025 | Footing and Foundation | WILLIAM DURDEN, P.E. | progress |
| 04/18/2025 | Fire-Resistance Rated Construction | WILLIAM DURDEN, P.E. | progress |
| 04/18/2025 | Structural Wood Frame | WILLIAM DURDEN, P.E. | progress |
| 04/18/2025 | Energy Code Compliance Inspections | WILLIAM DURDEN, P.E. | progress |
| 04/18/2025 | Electric vehicle service equipment requirements | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | HVAC-R and service water heating system controls | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Protection of exposed foundation insulation | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Duct leakage testing, insulation and design | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | HVAC-R and service water piping design and insulation | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Air barrier — testing | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | HVAC-R and service water heating equipment | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Maintenance information | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Insulation placement and R values | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Lighting in dwelling units | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Ventilation and air distribution system | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Fenestration and door U-factor and product ratings | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Interior lighting power | WILLIAM DURDEN, P.E. | energy_progress |
| 04/18/2025 | Fenestration air leakage | WILLIAM DURDEN, P.E. | energy_progress |