Locations of Work
ArchitectureStructuralMechanical
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 20 docs
Floor 2Under Construction1 filing · 20 docs
Floor 1Under Construction1 filing · 20 docs
CellarUnder Construction1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSEPH M. MORACE, A.I.A., ARCHITECT507/14/2026
A TECH ENGINEERING NYC, PLLC.110/07/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A TECH ENGINEERING NYC203/21/2026
LARGIME MUJOVIC103/21/2026
VIP EXPEDITING103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MAXIMUM CONTRACTING INCGeneral Contractor507/08/2026
FLOW-RIGHT PLBG & HTG CORPlumbing207/08/2026
B & R ELEC'L CONTR'G, INCElectrical103/22/2026
K.M.D MECHANICAL 1443 LLCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738207/14/2026
Building Lifecycle
All (60)Filed (6)Permit Issued (8)Signed Off (3)Inspection (9)Objection (4)Special Inspection (30)
08/21/2026
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
08/13/2026
Signed off — New Building
INSTALLATION OF PLUMBING FIXTURES FOR A NEW SEMI-DETACHED TWO-FAMILY RESIDENCE.
S01116162-S1
08/11/2026
Signed off — Alteration
INSTALLATION OF NEW FIRE SPRINKLER SYSTEM WITH VALVES AND METERS FOR SAME.
S01249046-I1
08/04/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/04/2026
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
07/29/2026
Special inspection requirement — Permanent certificate
anthony santoro
07/29/2026
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
07/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
07/29/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
anthony santoro
07/29/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
anthony santoro
07/29/2026
Special inspection requirement — Subgrade Inspections
anthony santoro
07/29/2026
Special inspection requirement — Mechanical Systems
anthony santoro
07/29/2026
Special inspection requirement — Final
anthony santoro
07/29/2026
Special inspection requirement — Structural Wood Frame
anthony santoro
07/29/2026
Special inspection requirement — Footing and Foundation
anthony santoro
07/29/2026
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
07/29/2026
Special inspection requirement — Fire-Resistance Rated Construction
anthony santoro
07/29/2026
Special inspection requirement — Insulation placement and R values
anthony santoro
07/29/2026
Special inspection requirement — Air barrier - visual inspection
anthony santoro
07/29/2026
Special inspection requirement — HVAC-R and service water heating system controls
anthony santoro
07/29/2026
Special inspection requirement — Ventilation and air distribution system
anthony santoro
07/29/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
07/29/2026
Special inspection requirement — Interior lighting power
anthony santoro
07/29/2026
Special inspection requirement — Protection of exposed foundation insulation
anthony santoro
07/29/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
anthony santoro
07/29/2026
Special inspection requirement — Lighting in dwelling units
anthony santoro
07/29/2026
Special inspection requirement — Fenestration areas
anthony santoro
07/29/2026
Special inspection requirement — Duct leakage testing, insulation and design
anthony santoro
07/29/2026
Special inspection requirement — Electric vehicle service equipment requirements
anthony santoro
07/29/2026
Special inspection requirement — Maintenance information
anthony santoro
07/29/2026
Special inspection requirement — Air barrier — testing
anthony santoro
07/29/2026
Special inspection requirement — HVAC-R and service water heating equipment
anthony santoro
07/29/2026
Special inspection requirement — Fenestration air leakage
anthony santoro
07/28/2026
Objection raised — Scope
07/28/2026
Objection resolved — Addressed
07/17/2026
Signed off — New Building
INSTALLATION OF PLUMBING FIXTURES FOR A NEW SEMI-DETACHED TWO-FAMILY RESIDENCE.
S01116162-S2
07/14/2026
Filed — New Building
INSTALLATION OF PLUMBING FIXTURES FOR A NEW SEMI-DETACHED TWO-FAMILY RESIDENCE.
S01116162-P2
07/13/2026
Special inspection requirement — Concrete - Cast-In-Place
anthony santoro
07/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
07/08/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
06/12/2026
Permit issued — Curb Cut
S01116162-S2-CC
06/09/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/01/2026
Filed — New Building
INSTALLATION OF PLUMBING FIXTURES FOR A NEW SEMI-DETACHED TWO-FAMILY RESIDENCE.
S01116162-S2
05/20/2026
Filed — New Building
INSTALLATION OF PLUMBING FIXTURES FOR A NEW SEMI-DETACHED TWO-FAMILY RESIDENCE.
S01116162-P1
04/18/2026
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
03/13/2026
Permit issued — Structural
S01116162-I1-GC-CX
02/18/2026
Permit issued — Mechanical Systems
S01116162-I1-GC-CX
01/12/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/24/2025
Permit issued — Plumbing
S01249046-I1-PL
10/09/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
10/07/2025
Filed — Alteration
INSTALLATION OF NEW FIRE SPRINKLER SYSTEM WITH VALVES AND METERS FOR SAME.
S01249046-I1
09/23/2025
Permit issued — Plumbing
S95611567-S1-PL
09/19/2025
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
09/11/2025
Permit issued — General Construction
S01116162-I1-FO-EA
09/11/2025
Permit issued — Foundation
S01116162-I1-GC-CX
09/10/2025
Permit issued — Plumbing
S01116162-S1-PL
08/21/2025
Filed — New Building
INSTALLATION OF PLUMBING FIXTURES FOR A NEW SEMI-DETACHED TWO-FAMILY RESIDENCE.
S01116162-S1
06/03/2025
Objection resolved — Addressed
11/14/2024
Objection raised — Scope
10/28/2024
Filed — New Building
INSTALLATION OF PLUMBING FIXTURES FOR A NEW SEMI-DETACHED TWO-FAMILY RESIDENCE.
S01116162-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offMAXIMUM CONTRACTING INC06/12/2026
DOB NOWStructuralPermit IssuedMAXIMUM CONTRACTING INC03/13/2026
DOB NOWMechanical SystemsPermit IssuedMAXIMUM CONTRACTING INC02/18/2026
DOB NOWPlumbingSigned-offFLOW-RIGHT PLBG & HTG COR11/24/2025
DOB NOWPlumbingSigned-offK.M.D MECHANICAL 1443 LLC09/23/2025
DOB NOWGeneral ConstructionSigned-offMAXIMUM CONTRACTING INC09/11/2025
DOB NOWFoundationPermit IssuedMAXIMUM CONTRACTING INC09/11/2025
DOB NOWPlumbingSigned-offFLOW-RIGHT PLBG & HTG COR09/10/2025
1 project · most recent 10/07/2025
FiledStatusContractorScope
10/07/2025——27 heads
2 projects · most recent 07/14/2026
Water/Sanitary Storm Plumbing-Sprinkler
FiledStatusContractorScope
07/14/2026Signed-offFLOW-RIGHT PLBG & HTG CORStorm, Water/Sanitary
10/07/2025Signed-offFLOW-RIGHT PLBG & HTG CORPlumbing-Sprinkler, Water/Sanitary
1 project · most recent 06/08/2026
General Wiring
FiledStatusContractorScope
06/08/2026CompleteB & R ELEC'L CONTR'G, INCGeneral Wiring
1 project · most recent 07/14/2026
Concrete Wood
FiledStatusContractorScope
07/14/2026Signed-offMAXIMUM CONTRACTING INCConcrete, Wood
1 project · most recent 07/14/2026
Earthwork
FiledStatusContractorScope
07/14/2026Signed-offMAXIMUM CONTRACTING INCEarthwork
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
08/21/2026Pass-Final SP - Up to 9 Requested FloorsPassView ↗
08/04/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/04/2026Certified Sprinkler - SP - RoughingCertifiedView ↗
07/08/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
06/09/2026Pass-Final CND-Occupancy InspectionPassView ↗
04/18/2026Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
01/12/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/09/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/19/2025Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 56
DateRequirementInspectorRole
07/29/2026Permanent certificateanthony santoroenergy_progress
07/29/2026Concrete - Cast-In-Placeanthony santorospecial
07/29/2026Fire-Resistant Penetrations and Jointsanthony santorospecial
07/29/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installationanthony santorospecial
07/29/2026Subsurface Investigations (Borings/Test Pits)anthony santorospecial
07/29/2026Subgrade Inspectionsanthony santorospecial
07/29/2026Mechanical Systemsanthony santorospecial
07/29/2026Finalanthony santoroprogress
07/29/2026Structural Wood Frameanthony santoroprogress
07/29/2026Footing and Foundationanthony santoroprogress
07/29/2026Energy Code Compliance Inspectionsanthony santoroprogress
07/29/2026Fire-Resistance Rated Constructionanthony santoroprogress
07/29/2026Insulation placement and R valuesanthony santoroenergy_progress
07/29/2026Air barrier - visual inspectionanthony santoroenergy_progress
07/29/2026HVAC-R and service water heating system controlsanthony santoroenergy_progress
07/29/2026Ventilation and air distribution systemanthony santoroenergy_progress
07/29/2026Fenestration and door U-factor and product ratingsanthony santoroenergy_progress
07/29/2026Interior lighting poweranthony santoroenergy_progress
07/29/2026Protection of exposed foundation insulationanthony santoroenergy_progress
07/29/2026HVAC-R and service water piping design and insulationanthony santoroenergy_progress
07/29/2026Lighting in dwelling unitsanthony santoroenergy_progress
07/29/2026Fenestration areasanthony santoroenergy_progress
07/29/2026Duct leakage testing, insulation and designanthony santoroenergy_progress
07/29/2026Electric vehicle service equipment requirementsanthony santoroenergy_progress
07/29/2026Maintenance informationanthony santoroenergy_progress
Latest 25 of 56.
▾Documents — 53 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/18/2026S01249046-I1Request digital key ↗
08/16/2026S01116162-S2Request digital key ↗
08/16/2026S01116162-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits1
▸BISBPP-5 - Authorization to the Department of Transportation1
08/15/2024540264079Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/15/2026S01116162-P2Open ↗
08/13/2026S01116162-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/15/2026S01116162-P2Open ↗
08/13/2026S01116162-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S01116162-I1Open ↗
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/16/2026S01116162-P2Open ↗
08/16/2026S01116162-S2Open ↗
08/16/2026S01116162-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
08/28/2026S01116162-P2Open ↗
08/28/2026S01116162-P2Open ↗
08/28/2026S01116162-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026S01116162-P2Open ↗
08/28/2026S01116162-P2Open ↗
08/26/2026S01116162-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
05/28/2024540264079Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/28/2024540264079Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026S01116162-I1Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/15/2026S01116162-P2Open ↗
08/13/2026S01116162-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/16/2026S01116162-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/16/2026S01116162-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S01116162-I1Open ↗
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT2
08/15/2026S01116162-P2Open ↗
08/13/2026S01116162-I1Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
05/28/2024540264079Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
05/28/2024540264079Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S01116162-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
08/15/2024540264079Open ↗
▸BISDOT PED RAMP APPROVAL1
07/25/2024540264079Open ↗
▸Other Documents10
▸DOB NOWSite Survey: Initial2
08/15/2026S01116162-P2Open ↗
08/13/2026S01116162-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/15/2026S01116162-P2Open ↗
08/13/2026S01116162-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/16/2026S01116162-I1Open ↗
08/15/2026S01116162-P2Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
07/25/2024540264079Open ↗
▸BISWAIVER OF CURB ALIGNMENT1
07/25/2024540264079Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
05/28/2024540264079Open ↗
▸DOB NOWFinal Survey1
08/16/2026S01116162-I1Open ↗