| Owner | Filings | Most Recent |
|---|---|---|
| NNT DEVELOPMENT | 13 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JOSEPH M. MORACE, ARCHITECT | 1 | 12/03/2025 |
| STANLEY M. KREBUSHEVSKI, R.A. | 2 | 03/13/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| PATRICIA L. GASS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NNT DEVELOPMENT CORP | General Contractor | 3 | 04/09/2026 |
| S.T.K. ELECTRICAL CORP. | Electrical | 1 | 03/22/2026 |
| MPC PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ISLAND ENGINEERING ASSOCI | 264 | 2 | 03/13/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | NNT DEVELOPMENT CORP | 12/09/2025 |
| DOB NOW | Plumbing | Signed-off | MPC PLUMBING & HEATING IN | 03/15/2025 |
| DOB NOW | Structural | Permit Issued | NNT DEVELOPMENT CORP | 03/01/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Signed-off | MPC PLUMBING & HEATING IN | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2025 | Complete | S.T.K. ELECTRICAL CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Signed-off | NNT DEVELOPMENT CORP | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/06/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 12/15/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 12/15/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/06/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 10/06/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/02/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/21/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/21/2024 | Concrete - Cast-In-Place | WILLIAM DURDEN, P.E. | special |
| 08/21/2024 | Fire-Resistant Penetrations and Joints | WILLIAM DURDEN, P.E. | special |
| 08/21/2024 | Subgrade Inspections | WILLIAM DURDEN, P.E. | special |
| 08/21/2024 | Subsurface Investigations (Borings/Test Pits) | WILLIAM DURDEN, P.E. | special |
| 08/21/2024 | Energy Code Compliance Inspections | WILLIAM DURDEN, P.E. | progress |
| 08/21/2024 | Fire-Resistance Rated Construction | WILLIAM DURDEN, P.E. | progress |
| 08/21/2024 | Structural Wood Frame | WILLIAM DURDEN, P.E. | progress |
| 08/21/2024 | Final | WILLIAM DURDEN, P.E. | progress |
| 08/21/2024 | Footing and Foundation | WILLIAM DURDEN, P.E. | progress |
| 08/21/2024 | Air barrier — testing | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Maintenance information | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Air barrier - visual inspection | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Metering | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Fenestration air leakage | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Electric vehicle service equipment requirements | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Fenestration and door U-factor and product ratings | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Fenestration areas | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Interior lighting power | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Insulation placement and R values | WILLIAM DURDEN, P.E. | energy_progress |
| 08/21/2024 | Permanent certificate | WILLIAM DURDEN, P.E. | energy_progress |