Locations of Work
ArchitectureStructural
Permit Issued — active, not yet Signed-off
Floor 2Under Construction10p · 1 filing · 20 docs
Floor 1Under Construction9p · 1 filing · 20 docs
CellarUnder Construction9p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FIRST HEC DESIGN INC.308/19/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
YBL NY203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NY DRILLING INCGeneral Contractor303/21/2026
L&L CONSTRUCTION DEVELOPGeneral Contractor208/18/2026
JJK BUILDING CONSULTINGGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MACIA INSPECTION & TESTIN402208/19/2026
Building Lifecycle
All (43)Filed (3)Permit Issued (4)Inspection (5)Objection (1)Special Inspection (30)
08/19/2026
Filed — New Building
NEW TWO-STORY TWO-FAMILY BUILDING, OBTAIN A NEW C/O.
S01159694-P1
08/19/2026
Special inspection requirement — Concrete - Cast-In-Place
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Masonry
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Final
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Footing and Foundation
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Air barrier — testing
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Fenestration areas
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Air barrier - visual inspection
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Fenestration air leakage
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Permanent certificate
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Lighting controls
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Insulation placement and R values
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Lighting in dwelling units
CHUNG CHING JEN
08/19/2026
Special inspection requirement — Metering
CHUNG CHING JEN
08/17/2026
Permit issued — Construction Fence
S01288577-I1-FN
07/07/2026
Permit issued — General Construction
S01159694-I1-GC
06/11/2026
Permit issued — General Construction
S01159694-I1-FO
06/04/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/07/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/22/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/22/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/22/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/23/2025
Permit issued — Construction Fence
S01288577-I1-FN
09/18/2025
Filed — Alteration
Herewith filed for the installation of an 8 ft temporay plywood construction fence.
S01288577-I1
01/07/2025
Objection raised — Scope
12/23/2024
Filed — New Building
NEW TWO-STORY TWO-FAMILY BUILDING, OBTAIN A NEW C/O.
S01159694-I1
12/23/2024
Special inspection requirement — Concrete - Cast-In-Place
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Masonry
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Final
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Footing and Foundation
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Permanent certificate
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Fenestration air leakage
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Fenestration areas
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Air barrier — testing
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Lighting controls
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Insulation placement and R values
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Lighting in dwelling units
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Air barrier - visual inspection
CHUNG CHING JEN
12/23/2024
Special inspection requirement — Metering
CHUNG CHING JEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedL&L CONSTRUCTION DEVELOP08/17/2026
DOB NOWGeneral ConstructionPermit IssuedL&L CONSTRUCTION DEVELOP07/07/2026
DOB NOWGeneral ConstructionPermit IssuedJJK BUILDING CONSULTING06/11/2026
DOB NOWConstruction FencePermit IssuedNY DRILLING INC09/23/2025
1 project · most recent 08/19/2026
FiledStatusContractorScope
08/19/2026Permit IssuedL&L CONSTRUCTION DEVELOP2 scope_items
1 project · most recent 09/18/2025
Fence
FiledStatusContractorScope
09/18/2025Permit IssuedL&L CONSTRUCTION DEVELOPFence
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
06/04/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/07/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/22/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/22/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/22/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
08/19/2026Concrete - Cast-In-PlaceCHUNG CHING JENspecial
08/19/2026Fire-Resistant Penetrations and JointsCHUNG CHING JENspecial
08/19/2026MasonryCHUNG CHING JENspecial
08/19/2026FinalCHUNG CHING JENprogress
08/19/2026Footing and FoundationCHUNG CHING JENprogress
08/19/2026Air barrier — testing CHUNG CHING JENenergy_progress
08/19/2026Fenestration areasCHUNG CHING JENenergy_progress
08/19/2026Air barrier - visual inspectionCHUNG CHING JENenergy_progress
08/19/2026Fenestration air leakageCHUNG CHING JENenergy_progress
08/19/2026Permanent certificateCHUNG CHING JENenergy_progress
08/19/2026Fenestration and door U-factor and product ratingsCHUNG CHING JENenergy_progress
08/19/2026Lighting controlsCHUNG CHING JENenergy_progress
08/19/2026Insulation placement and R valuesCHUNG CHING JENenergy_progress
08/19/2026Lighting in dwelling unitsCHUNG CHING JENenergy_progress
08/19/2026MeteringCHUNG CHING JENenergy_progress
12/23/2024Concrete - Cast-In-PlaceCHUNG CHING JENspecial
12/23/2024Fire-Resistant Penetrations and JointsCHUNG CHING JENspecial
12/23/2024MasonryCHUNG CHING JENspecial
12/23/2024FinalCHUNG CHING JENprogress
12/23/2024Footing and FoundationCHUNG CHING JENprogress
12/23/2024Permanent certificateCHUNG CHING JENenergy_progress
12/23/2024Fenestration air leakageCHUNG CHING JENenergy_progress
12/23/2024Fenestration areasCHUNG CHING JENenergy_progress
12/23/2024Air barrier — testing CHUNG CHING JENenergy_progress
12/23/2024Lighting controlsCHUNG CHING JENenergy_progress
Latest 25 of 30.
▾Documents — 35 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/20/2026S01159694-P1Request digital key ↗
08/18/2026S01288577-I1Request digital key ↗
08/15/2026S01159694-I1Request digital key ↗
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
02/19/2026540269403Open ↗
▸Zoning, Tax Lot & Property Records8
▸DOB NOWZD1: DOB Zoning Diagram3
08/20/2026S01159694-P1Open ↗
08/15/2026S01159694-I1Open ↗
08/13/2026S01159694-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/20/2026S01159694-P1Open ↗
08/13/2026S01159694-I1Open ↗
▸DOB NOWRestrictive Declaration/Easement 12
08/20/2026S01159694-P1Open ↗
08/13/2026S01159694-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S01159694-I1Open ↗
▸Seals & Professional Certifications11
▸DOB NOWProgress Inspector Seal & Signature4
08/27/2026S01159694-P1Open ↗
08/27/2026S01159694-P1Open ↗
08/27/2026S01159694-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/20/2026S01159694-P1Open ↗
08/20/2026S01159694-I1Open ↗
08/13/2026S01288577-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026S01159694-P1Open ↗
08/27/2026S01159694-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
02/19/2026540269403Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/19/2026540269403Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026S01159694-I1Open ↗
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/20/2026S01159694-P1Open ↗
08/13/2026S01159694-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/15/2026S01159694-I1Open ↗
▸Inspections & Test Reports1
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026S01159694-I1Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
02/19/2026540269403Open ↗
▸Other Documents6
▸DOB NOWSite Survey: Initial2
08/20/2026S01159694-P1Open ↗
08/13/2026S01159694-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/20/2026S01159694-P1Open ↗
08/13/2026S01159694-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/20/2026S01159694-P1Open ↗
08/15/2026S01159694-I1Open ↗