| Owner | Filings | Most Recent |
|---|---|---|
| JM TRINITY HOLDINGS | 20 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STANLEY M. KREBUSHEVSKI, R.A. | 3 | 01/21/2026 |
| C&P DESIGN CONSULTANTS | 3 | 06/19/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BEYER CONSTRUCTION CORP | General Contractor | 4 | 04/09/2026 |
| RIDGE ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| CAPITAL CONTR P&H CORP | Plumbing | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 4 | 01/21/2026 |
| SRA PLANNING & EXPEDITING | 5677 | 3 | 01/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BEYER CONSTRUCTION | 10/01/2025 |
| DOB NOW | Mechanical Systems | Signed-off | BEYER CONSTRUCTION | 09/25/2025 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 08/15/2025 |
| DOB NOW | Plumbing | Signed-off | CAPITAL CONTR P&H CORP | 06/11/2025 |
| DOB NOW | Foundation | Permit Issued | BEYER CONSTRUCTION | 05/29/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/21/2026 | Signed-off | BEYER CONSTRUCTION CORP | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Apower Condenser: APFH36HP230VAO-R32
Indoor Unit: APF36HP230VAI-R32 36,000 BTU · Heat Pump Outdoor ×4 Aux Cloud Commerce Condenser: ASPR24HPMULO
Indoor Unit: AFEB09HP230V1CH 11,000 BTU · Heat Pump Outdoor ×2 Condenser: ASPR24HPMULO Indoor Unit: AFEB12HP230V1CH 11,000 BTU · Heat Pump Outdoor ×2 Ventilation Broan B130E65RS 70 CFM · Erv ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2026 | Signed-off | CAPITAL CONTR P&H CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2025 | Complete | RIDGE ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2026 | Signed-off | BEYER CONSTRUCTION CORP | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/28/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/08/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/01/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/17/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 09/10/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/31/2026 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Interior lighting power | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Metering | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Electric vehicle service equipment requirements | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Air barrier — testing | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 01/31/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 01/31/2026 | Structural Steel - Welding | WILLIAM MONTAGUE | special |
| 01/31/2026 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 01/31/2026 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 01/31/2026 | Subgrade Inspections | Stanislav Pilipenko | special |
| 01/31/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 01/31/2026 | Final | Stanislav Pilipenko | progress |
| 01/31/2026 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 01/31/2026 | Footing and Foundation | Stanislav Pilipenko | progress |
| 01/31/2026 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 01/20/2026 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 01/20/2026 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 01/20/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 01/20/2026 | Structural Steel - Welding | WILLIAM MONTAGUE | special |