| Firm | Filings | Most Recent |
|---|---|---|
| JOSEPH M. MORACE, A.I.A., ARCHITECT | 5 | 06/09/2026 |
| PARKER AND WEST ENGINEERING, PLLC | 1 | 01/08/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| APRILE BONAMO FILING REP | 3 | 03/21/2026 |
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MASTER BUILT HOMES INC | General Contractor | 8 | 04/09/2026 |
| SUNRUN SOLAR ELECTL CORP | Electrical | 1 | 03/22/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 04/09/2026 |
| DUO PLUMBING & HTG CORP. | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 3 | 06/09/2026 |
| PARKER AND WEST ENGINEERI | 5272 | 1 | 01/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 01/09/2026 |
| DOB NOW | Curb Cut | Signed-off | MASTER BUILT HOMES INC | 11/24/2025 |
| DOB NOW | Plumbing | Signed-off | DUO PLUMBING & HTG CORP. | 06/11/2025 |
| DOB NOW | General Construction | Signed-off | MASTER BUILT HOMES INC | 05/13/2025 |
| DOB NOW | Earth Work | Signed-off | MASTER BUILT HOMES INC | 05/13/2025 |
| DOB NOW | Earth Work | Signed-off | MASTER BUILT HOMES INC | 05/13/2025 |
| DOB NOW | Earth Work | Permit Issued | MASTER BUILT HOMES INC | 05/13/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MASTER BUILT HOMES INC | 05/13/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Signed-off | DUO PLUMBING & HTG CORP. | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/08/2026 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 09/23/2025 | Complete | B & R ELEC'L CONTR'G, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Signed-off | MASTER BUILT HOMES INC | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Signed-off | MASTER BUILT HOMES INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/03/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 04/03/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/02/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/02/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 12/18/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/25/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/24/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/18/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/16/2026 | Lighting in dwelling units | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Mechanical Systems | Stanislav Pilipenko | special |
| 06/16/2026 | Wood – Prefabricated I-Joists | Stanislav Pilipenko | special |
| 06/16/2026 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 06/16/2026 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 06/16/2026 | Subgrade Inspections | Stanislav Pilipenko | special |
| 06/16/2026 | Footing and Foundation | Stanislav Pilipenko | progress |
| 06/16/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 06/16/2026 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 06/16/2026 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 06/16/2026 | Final | Stanislav Pilipenko | progress |
| 06/16/2026 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Air barrier — testing | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Duct leakage testing, insulation and design | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Protection of exposed foundation insulation | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 06/16/2026 | Interior lighting power | Stanislav Pilipenko | energy_progress |