| Owner | Filings | Most Recent |
|---|---|---|
| OAK DEVELOPERS | 18 | 07/25/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| C&P DESIGN CONSULTANTS | 4 | 04/22/2026 |
| STANLEY KREBUSHEVSKI | 2 | 02/18/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| OAK DEVELOPERS,LLC | General Contractor | 4 | 07/25/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 2 | 06/28/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 5 | 04/22/2026 |
| SRA PLANNING & EXPEDITING | 5677 | 1 | 12/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | OAK DEVELOPERS,LLC | 07/24/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | OAK DEVELOPERS,LLC | 06/09/2026 |
| DOB NOW | Curb Cut | Permit Issued | OAK DEVELOPERS,LLC | 06/09/2026 |
| DOB NOW | Plumbing | Permit Issued | QUALITY PLUMBING, INC | 01/20/2026 |
| DOB NOW | Plumbing | Permit Issued | FLOW-RIGHT PLBG & HTG COR | 12/26/2025 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 12/26/2025 |
| DOB NOW | General Construction | Permit Issued | OAK DEVELOPERS,LLC | 11/25/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2026 | Permit Issued | FLOW-RIGHT PLBG & HTG COR | Plumbing-Sprinkler, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/26/2025 | Complete | TRUE ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2026 | Permit Issued | OAK DEVELOPERS,LLC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/11/2026 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 08/11/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/10/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/03/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/09/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 03/04/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/02/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/25/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/04/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 08/26/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 03/10/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/10/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/13/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/22/2026 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 04/22/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 04/22/2026 | Ventilation and air distribution system | Stanislav Pilipenko | energy_progress |
| 04/22/2026 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 04/22/2026 | Duct leakage testing, insulation and design | Stanislav Pilipenko | energy_progress |
| 04/22/2026 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 04/22/2026 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 04/22/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 04/22/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 02/27/2026 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Air barrier — testing | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Interior lighting power | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Subgrade Inspections | Stanislav Pilipenko | special |
| 02/27/2026 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Metering | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Electric vehicle service equipment requirements | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 02/27/2026 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 02/27/2026 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 02/27/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 02/27/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |