| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/30/2025 | Permit Issued | FINE MECHANICAL CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | Permit Issued | D AND H ELECTRICAL CONST | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| OUR ISLAND PROPERTY MNGNT | 11 | 08/20/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STANLEY M. KREBUSHEVSKI, R.A. | 6 | 12/30/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| OUR ISLAND PROPERTY MANAG | General Contractor | 2 | 08/18/2026 |
| FINE MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 08/20/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 5 | 12/30/2025 |
| SRA PLANNING & EXPEDITING | 5677 | 1 | 10/07/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | QUALITY PLUMBING, INC | 08/19/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | OUR ISLAND PROPERTY MANAG | 07/10/2026 |
| DOB NOW | Plumbing | Permit Issued | FINE MECHANICAL CORP | 02/19/2026 |
| DOB NOW | Foundation | Permit Issued | OUR ISLAND PROPERTY MANAG | 12/22/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/02/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 09/01/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/28/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/18/2026 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 03/18/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 03/18/2026 | Final | Stanislav Pilipenko | progress |
| 03/18/2026 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 03/18/2026 | Footing and Foundation | Stanislav Pilipenko | progress |
| 03/18/2026 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 03/18/2026 | Air barrier — testing | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Electric vehicle service equipment requirements | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Interior lighting power | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Metering | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 03/18/2026 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 03/18/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 03/18/2026 | Subgrade Inspections | Stanislav Pilipenko | special |
| 12/24/2025 | Interior lighting power | Stanislav Pilipenko | energy_progress |
| 12/24/2025 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 12/24/2025 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 12/24/2025 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 12/24/2025 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |