| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2026 | Signed-off | SUPERIOR PLUMBING & HEATI | Plumbing-Sprinkler, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/04/2026 | Complete | S.T.K. ELECTRICAL CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2026 | Signed-off | A. FONTANA & SONS LLC | Concrete, Wood |
| Owner | Filings | Most Recent |
|---|---|---|
| FONTANA AND SONS, LLC | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LAWRENCE MANDARINO ARCHITECT | 3 | 04/29/2026 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 04/23/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| APRILE BONAMO FILING REP | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A. FONTANA & SONS LLC | General Contractor | 4 | 09/07/2026 |
| SUPERIOR PLUMBING & HEATING | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 1 | 02/20/2026 |
| LAWRENCE MANDARINO ARCHIT | 724 | 2 | 02/20/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | A. FONTANA & SONS LLC | 09/03/2026 |
| DOB NOW | Plumbing | Signed-off | SUPERIOR PLUMBING & HEATING | 06/05/2026 |
| DOB NOW | Plumbing | Signed-off | SUPERIOR PLUMBING & HEATI | 03/05/2026 |
| DOB NOW | Structural | Signed-off | A. FONTANA & SONS LLC | 02/23/2026 |
| DOB NOW | Structural | Signed-off | A. FONTANA & SONS LLC | 02/23/2026 |
| DOB NOW | General Construction | Permit Issued | A. FONTANA & SONS LLC | 02/19/2026 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/21/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/18/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/18/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/29/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/20/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/24/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/18/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/11/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/25/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/29/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/30/2026 | Metering | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Maintenance information | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Air barrier - visual inspection | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Insulation placement and R values | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Electric vehicle service equipment requirements | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Concrete - Cast-In-Place | Lawrence Mandarino | special |
| 01/30/2026 | Fire-Resistant Penetrations and Joints | Lawrence Mandarino | special |
| 01/30/2026 | Subgrade Inspections | Lawrence Mandarino | special |
| 01/30/2026 | Energy Code Compliance Inspections | Lawrence Mandarino | progress |
| 01/30/2026 | Fire-Resistance Rated Construction | Lawrence Mandarino | progress |
| 01/30/2026 | Structural Wood Frame | Lawrence Mandarino | progress |
| 01/30/2026 | Permanent certificate | Lawrence Mandarino | energy_progress |
| 01/30/2026 | HVAC-R and service water heating equipment | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Fenestration air leakage | Lawrence Mandarino | energy_progress |
| 01/30/2026 | HVAC-R and service water heating system controls | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Air barrier — testing | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Lighting controls | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Lighting in dwelling units | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Fenestration and door U-factor and product ratings | Lawrence Mandarino | energy_progress |
| 01/30/2026 | Fenestration areas | Lawrence Mandarino | energy_progress |
| 01/27/2026 | Wood – Prefabricated I-Joists | Lawrence Mandarino | special |
| 01/27/2026 | Construction Utilizing CLT or SCL, Type IV | Lawrence Mandarino | special |
| 01/16/2026 | Final | Lawrence Mandarino | progress |
| 01/16/2026 | Footing and Foundation | Lawrence Mandarino | progress |