| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | Permit Issued | MPC PLUMBING & HEATING IN | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Permit Issued | LMS ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | Permit Issued | FAS BUILDING CORP | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | Permit Issued | FAS BUILDING CORP | Earthwork |
| Owner | Filings | Most Recent |
|---|---|---|
| ANNADALE ROAD DEVELOPMENT LLC | 4 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| C&P DESIGN CONSULTANTS | 3 | 07/27/2026 |
| STANLEY M. KREBUSHEVSKI, R.A. | 1 | 02/03/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FAS BUILDING CORP | General Contractor | 2 | 06/27/2026 |
| MPC PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 4 | 07/27/2026 |
| SRA PLANNING & EXPEDITING | 5677 | 3 | 07/27/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | FAS BUILDING CORP | 05/08/2026 |
| DOB NOW | Plumbing | Permit Issued | MPC PLUMBING & HEATING IN | 03/27/2026 |
| DOB NOW | General Construction | Permit Issued | FAS BUILDING CORP | 03/02/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/29/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 07/29/2026 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 07/29/2026 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 07/29/2026 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 07/29/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 07/29/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 07/29/2026 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 07/29/2026 | Sprinkler Systems | Stanislav Pilipenko | special |
| 07/29/2026 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | WILLIAM MONTAGUE | special |
| 07/29/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Stanislav Pilipenko | special |
| 07/27/2026 | Sprinkler Systems | Stanislav Pilipenko | special |
| 07/24/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Stanislav Pilipenko | special |
| 07/24/2026 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 07/24/2026 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 07/24/2026 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 07/24/2026 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 07/24/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 07/24/2026 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 07/24/2026 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | WILLIAM MONTAGUE | special |
| 07/24/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 03/23/2026 | Ventilation and air distribution system | Stanislav Pilipenko | energy_progress |
| 03/23/2026 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 03/23/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 03/23/2026 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 03/23/2026 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |