Building Lifecycle
All (52)Filed (1)Objection (30)Special Inspection (21)
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/15/2026
Objection resolved — Resolved
07/15/2026
Objection resolved — Resolved
07/15/2026
Objection resolved — Resolved
07/15/2026
Objection resolved — Resolved
07/15/2026
Objection resolved — Resolved
07/15/2026
Objection resolved — Resolved
07/15/2026
Objection resolved — Open
07/15/2026
Objection resolved — Resolved
06/22/2026
Objection raised — Zoning
06/22/2026
Objection raised — Zoning
06/22/2026
Objection raised — Zoning
06/22/2026
Objection raised — Fire_Protection
06/22/2026
Objection raised — Structural
06/22/2026
Objection raised — Scope
06/22/2026
Objection raised — Zoning
06/22/2026
Objection raised — Zoning
06/22/2026
Objection raised — Zoning
06/22/2026
Objection raised — Zoning
06/22/2026
Objection raised — Fire_Protection
06/22/2026
Objection raised — Fire_Protection
06/22/2026
Objection raised — Scope
06/22/2026
Objection raised — Inspections
06/22/2026
Objection raised — Energy
05/20/2026
Filed — New Building
THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT A DETACHED TWO FAMILY BUILDING.
S01403981-I1
05/19/2026
Special inspection requirement — Metering
05/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/19/2026
Special inspection requirement — Post-installed Anchors
05/19/2026
Special inspection requirement — Designated Seismic System
05/19/2026
Special inspection requirement — Structural Steel - Details
05/19/2026
Special inspection requirement — Wood – Seismic Resistance
05/19/2026
Special inspection requirement — Energy Code Compliance Inspections
05/19/2026
Special inspection requirement — Fire-Resistance Rated Construction
05/19/2026
Special inspection requirement — Protection of exposed foundation insulation
05/19/2026
Special inspection requirement — Concrete - Cast-In-Place
05/19/2026
Special inspection requirement — Air barrier — testing
05/19/2026
Special inspection requirement — Permanent certificate
05/19/2026
Special inspection requirement — Fenestration air leakage
05/19/2026
Special inspection requirement — Air barrier - visual inspection
05/19/2026
Special inspection requirement — Fenestration areas
05/19/2026
Special inspection requirement — Electric vehicle service equipment requirements
05/19/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
05/19/2026
Special inspection requirement — Insulation placement and R values
05/19/2026
Special inspection requirement — Interior lighting power
05/18/2026
Special inspection requirement — Final
05/18/2026
Special inspection requirement — Footing and Foundation
Nothing on file for this building.
1 job · most recent 05/20/2026
Steel Concrete Wood
FiledStatusContractorScope
05/20/2026——Steel, Concrete, Wood
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
05/19/2026Metering—energy_progress
05/19/2026Fire-Resistant Penetrations and Joints—special
05/19/2026Post-installed Anchors—special
05/19/2026Designated Seismic System—special
05/19/2026Structural Steel - Details—special
05/19/2026Wood – Seismic Resistance—special
05/19/2026Energy Code Compliance Inspections—progress
05/19/2026Fire-Resistance Rated Construction—progress
05/19/2026Protection of exposed foundation insulation—energy_progress
05/19/2026Concrete - Cast-In-Place—special
05/19/2026Air barrier — testing —energy_progress
05/19/2026Permanent certificate—energy_progress
05/19/2026Fenestration air leakage—energy_progress
05/19/2026Air barrier - visual inspection—energy_progress
05/19/2026Fenestration areas—energy_progress
05/19/2026Electric vehicle service equipment requirements—energy_progress
05/19/2026Fenestration and door U-factor and product ratings—energy_progress
05/19/2026Insulation placement and R values—energy_progress
05/19/2026Interior lighting power—energy_progress
05/18/2026Final—progress
05/18/2026Footing and Foundation—progress
Nothing on file for this building.