| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B00914271 ↗ | 1073 WILLOUGHBY AVENUE BROOKLYN | Full Demolition | Signed-off | 11/28/2023 | 01/02/2025 | Contractor RED BRICK PROPERTY MNGMT | Demo of two story structure |
| S00725833 ↗ | 315 MAJOR AVENUE STATEN ISLAND | Alteration | Permit Issued | 05/16/2022 | 08/28/2022 | Contractor VERITAS SERVICES, INC Filer HAIDER ENGINEERING, P.E. | Alteration Application: Temporary Shoring to be Installed at Rear Yard to Support Retaining wall at 920 Hylan Boulevard to Address IED. |
| B00405885 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 10/08/2020 | 10/08/2021 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SUPPORTED SCAFFOLD: TO BE ERECTED AROUND DESIGNATED BUILDING PERIMETER TO UNDERGO CONSTRUCTION … |
| B00405918 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 10/08/2020 | 10/08/2021 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SUPPORTED SCAFFOLD: TO BE ERECTED AROUND DESIGNATED BUILDING PERIMETER TO UNDERGO CONSTRUCTION … |
| B00380510 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 08/06/2020 | 08/25/2021 | Contractor BILLY ENTERPRISES INC | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SHED: 8'-0 HIGH SIDEWALK SHED TO BE ERECTED AROUND THE DESIGNATED PERIMETER OF BUILDING TO UND… |
| B00380914 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 08/06/2020 | 08/24/2021 | Contractor BILLY ENTERPRISES INC | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SHED: 8'-0 HIGH SIDEWALK SHED TO BE ERECTED AROUND THE DESIGNATED PERIMETER OF BUILDING TO UND… |
| Person | Filings | Most recent |
|---|---|---|
| GHOUSE ISMAIL | 12 | 04/26/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| BILLY ENTERPRISES INC | 11 | 10/13/2020 |
| LCS RESTORATION CORP | 3 | 11/12/2020 |
| MCKENNEY CONSTRUCTION LLC | 1 | 11/28/2023 |
| RED BRICK PROPERTY MNGMT | 1 | 11/28/2023 |
| VERITAS SERVICES, INC | 1 | 05/16/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| BILLY ENTERPRISES INC | 7 | 10/13/2020 |
| BONA LLC | 2 | 11/12/2020 |
| AKI RENOVATIONS GROUP INC | 1 | 05/03/2021 |
| LCS RESTORATION CORP | 1 | 11/12/2020 |
| Name | Projects together | Most recent |
|---|---|---|
| HAIDER ENGINEERING, P.E. | 2 | 05/16/2022 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B00914271 ↗ | 1073 WILLOUGHBY AVENUE BROOKLYN | Full Demolition | Signed-off | 11/28/2023 | 01/02/2025 | Contractor RED BRICK PROPERTY MNGMT | Demo of two story structure |
| S00725833 ↗ | 315 MAJOR AVENUE STATEN ISLAND | Alteration | Permit Issued | 05/16/2022 | 08/28/2022 | Contractor VERITAS SERVICES, INC Filer HAIDER ENGINEERING, P.E. | Alteration Application: Temporary Shoring to be Installed at Rear Yard to Support Retaining wall at 920 Hylan Boulevard to Address IED. |
| B00405885 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 10/08/2020 | 10/08/2021 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SUPPORTED SCAFFOLD: TO BE ERECTED AROUND DESIGNATED BUILDING PERIMETER TO UNDERGO CONSTRUCTION … |
| B00405918 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 10/08/2020 | 10/08/2021 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SUPPORTED SCAFFOLD: TO BE ERECTED AROUND DESIGNATED BUILDING PERIMETER TO UNDERGO CONSTRUCTION … |
| B00380510 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 08/06/2020 | 08/25/2021 | Contractor BILLY ENTERPRISES INC | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SHED: 8'-0 HIGH SIDEWALK SHED TO BE ERECTED AROUND THE DESIGNATED PERIMETER OF BUILDING TO UND… |
| B00380914 ↗ | 55 SHEFFIELD AVENUE BROOKLYN | Alteration | Signed-off | 08/06/2020 | 08/24/2021 | Contractor BILLY ENTERPRISES INC | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SHED: 8'-0 HIGH SIDEWALK SHED TO BE ERECTED AROUND THE DESIGNATED PERIMETER OF BUILDING TO UND… |
| B00368156 ↗ | 486 COURT STREET BROOKLYN | Alteration | Permit Issued | 07/10/2020 | 07/30/2021 | Contractor BILLY ENTERPRISES INC | 8'-0 HIGH SIDEWALK SHED TO BE ERECTED ALONG THE DESIGNATED PERIMETERS OF THE NEW BUILDING CONSTRUCTION. |
| Q00487725 ↗ | 35-01 36 AVENUE QUEENS | Alteration | Filed — no permit on record | 05/03/2021 | — | Filer HAIDER ENGINEERING, P.E. | — |
| B00419526 ↗ | 263 SKILLMAN STREET BROOKLYN | Alteration | Signed-off | 11/12/2020 | 12/11/2020 | Owner BONA LLC Contractor LCS RESTORATION CORP Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SUPPORTED SCAFFOLD: PROPOSED INSTALLATION OF SCAFFOLDING ONTO BUILDING PERIMETER COMMENCING ON … |
| B00414332 ↗ | 263 SKILLMAN STREET BROOKLYN | Alteration | Signed-off | 11/12/2020 | 11/17/2020 | Owner LCS RESTORATION CORP Contractor LCS RESTORATION CORP Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SUPPORTED SCAFFOLD: PROPOSED INSTALLATION OF SCAFFOLDING ONTO BUILDING PERIMETER COMMENCING ON … |
| B00419540 ↗ | 263 SKILLMAN STREET BROOKLYN | Alteration | Signed-off | 11/10/2020 | 11/13/2020 | Owner BONA LLC Contractor LCS RESTORATION CORP Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SIDEWALK SHED: PROPOSED INSTALLATION OF SHED ONTO BUILDING STREET FRONTAGE ON GROUND LEVEL / GR… |
| B00405990 ↗ | 30 EAST 98 STREET BROOKLYN | Alteration | Signed-off | 10/13/2020 | 10/20/2020 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SUPPORTED SCAFFOLD: TO BE ERECTED AROUND DESIGNATED BUILDING PERIMETER UNDER CONSTRUCTION. NO C… |
| X00373983 ↗ | 3362 BOSTON ROAD BRONX | Alteration | Signed-off | 07/28/2020 | 07/28/2020 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SCAFFOLD: PROPOSED INSTALLATION OF SUPPORTED SCAFFOLD. NO CHANGE IN USE OCCUPANCY OR EGRESS UND… |
| M00374926 ↗ | 3780 BROADWAY MANHATTAN | Alteration | Signed-off | 07/24/2020 | 07/24/2020 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SHED: 14'-0 HIGH SIDEWALK SHED TO BE ERECTED AROUND THE DESIGNATED PERIMETER OF BUILDING TO UN… |
| X00367983 ↗ | 951 OLMSTEAD AVENUE BRONX | Alteration | Signed-off | 07/14/2020 | 07/15/2020 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | ALTERATION TYPE 3 - CONSTRUCTION EQUIPMENT - SCAFFOLD: PROPOSED INSTALLATION OF PIPE SCAFFOLD NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER TH… |
| X00365965 ↗ | 951 OLMSTEAD AVENUE BRONX | Alteration | Signed-off | 07/08/2020 | 07/09/2020 | Owner BILLY ENTERPRISES INC Contractor BILLY ENTERPRISES INC Filer HAIDER ENGINEERING, P.E. | 8'-0 HIGH SIDEWALK SHED TO BE ERECTED ALONG THE DESIGNATED PERIMETER OF THE NEW BUILDING CONSTRUCTION. |
| B00002440 ↗ | 123 MELROSE STREET BROOKLYN | Alteration | Signed-off | 11/15/2017 | 02/27/2018 | Contractor BILLY ENTERPRISES INC | INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. ALL WORK SHALL BE ACCORDING TO CHAPTER #33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRE… |
| Building | Filings | Most Recent |
|---|---|---|
| 315 MAJOR AVENUE ↗ | 1 | 04/26/2022 |
| 35-01 36 AVENUE ↗ | 1 | 03/17/2021 |
| 263 SKILLMAN STREET ↗ | 3 | 10/26/2020 |
| 3780 BROADWAY ↗ | 1 | 07/23/2020 |
| 3362 BOSTON ROAD ↗ | 1 | 07/21/2020 |
| 951 OLMSTEAD AVENUE ↗ | 2 | 07/08/2020 |
| 55 SHEFFIELD AVENUE ↗ | 3 | — |
| 55 SHEFFIELD AVENUE ↗ | 3 | — |
| 123 MELROSE STREET ↗ | 1 | — |
| 486 COURT STREET ↗ | 1 | — |
| 30 EAST 98 STREET ↗ | 1 | — |
| 1073 WILLOUGHBY AVENUE ↗ | 1 | — |