| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01321119 ↗ | 75-15 195 STREET QUEENS | ALT-CO - New Building with Existing Elements to Remain | Permit Issued | 12/27/2025 | 08/26/2026 | Design NS ENGINEERING, P.C. Contractor H BUILDING MANAGEMENT INC | PROPOSED CONSTRUCTION OF A NEW TWO-STORY, ONE-FAMILY FRAME BUILDING WITH CELLAR AND ATTIC, WITH EXISTING ELEMENTS TO REMAIN. |
| Q01353674 ↗ | 143-23 ROSE AVENUE QUEENS | Alteration | Permit Issued | 03/05/2026 | 04/17/2026 | Design NS ENGINEERING, P.C. Contractor KANARIS CONTRACTING CORP | PROPOSED RESTORATION OF EXISTING PARTIALLY FIRE DAMAGED 2 STORY BUILDING WITH CELLAR CONTAINING A SINGLE FAMILY DWELLING. NO CHANGE IN USE, … |
| Q01275599 ↗ | 142-05 184 STREET QUEENS | Alteration | Signed-off | 11/14/2025 | 12/29/2025 | Design NS ENGINEERING, P.C. Owner KINGSLAND PROPERTIES Contractor JVR PLBG AND HEATING INC | Application filed in conjunction with Alteration CO-Application Q01260275-I1 for the installation of plumbing fixtures and plumbing piping i… |
| Q01260275 ↗ | 142-05 184 STREET QUEENS | Alteration CO | Permit Issued | 08/21/2025 | 10/22/2025 | Design NS ENGINEERING, P.C. Owner KINGSLAND PROPERTIES Contractor BILLY BUILDERS INC | CONVERSION OF AN EXIST. 1 STORY, 1 FAMILY BRICK/FRAME BUILDING W/ CELLAR TO A 2 STORY, 2 FAMILY DWELLING WITH HORIZONTAL & VERTICAL EXTENSIO… |
| Q01104299 ↗ | 75-15 195 STREET QUEENS | Alteration CO | Permit Issued | 09/30/2024 | 07/17/2025 | Design NS ENGINEERING, P.C. Contractor H BUILDING MANAGEMENT INC Filer HN REPUBLIC LLC | EXIST. 2 STORY, 1 FAMILY FRAME BUILDING W/ CELLAR. PROPOSED INTERIOR RENOVATION, VERTICAL AND HORIZONTAL EXTENSION AT SIDE & REAR. RESOLVE D… |
| Q01121881 ↗ | 71-33 260 STREET QUEENS | Alteration | Signed-off | 10/07/2024 | 03/27/2025 | Design NS ENGINEERING, P.C. Contractor MAHI PAINTING INC | PROPOSED NEW 10' X 10' WOODEN DECK ADDITION AT FRONT YARD OF SECOND FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Name | Projects together | Most recent |
|---|---|---|
| NS ENGINEERING, P.C. | 10 | 08/24/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| H BUILDING MANAGEMENT INC | 3 | 08/24/2026 |
| AKEM CONSTRUCTION INC | 1 | 12/14/2023 |
| BILLY BUILDERS INC | 1 | 05/26/2026 |
| CREATIVE BUILDING MANAGEM | 1 | 08/21/2024 |
| KANARIS CONTRACTING CORP | 1 | 03/05/2026 |
| MAHI PAINTING INC | 1 | 02/06/2025 |
| PLUMB-IT MECHANICAL INC | 1 | 11/14/2025 |
| WATERMARK PLUMBING CORP | 1 | 07/02/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| KINGSLAND PROPERTIES | 2 | 05/26/2026 |
| GLEN OAKS VILLAGE OWNERS, INC. | 1 | 02/06/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| HN REPUBLIC LLC | 1 | 04/18/2025 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01321119 ↗ | 75-15 195 STREET QUEENS | ALT-CO - New Building with Existing Elements to Remain | Permit Issued | 12/27/2025 | 08/26/2026 | Design NS ENGINEERING, P.C. Contractor H BUILDING MANAGEMENT INC | PROPOSED CONSTRUCTION OF A NEW TWO-STORY, ONE-FAMILY FRAME BUILDING WITH CELLAR AND ATTIC, WITH EXISTING ELEMENTS TO REMAIN. |
| Q01353674 ↗ | 143-23 ROSE AVENUE QUEENS | Alteration | Permit Issued | 03/05/2026 | 04/17/2026 | Design NS ENGINEERING, P.C. Contractor KANARIS CONTRACTING CORP | PROPOSED RESTORATION OF EXISTING PARTIALLY FIRE DAMAGED 2 STORY BUILDING WITH CELLAR CONTAINING A SINGLE FAMILY DWELLING. NO CHANGE IN USE, … |
| Q01275599 ↗ | 142-05 184 STREET QUEENS | Alteration | Signed-off | 11/14/2025 | 12/29/2025 | Design NS ENGINEERING, P.C. Owner KINGSLAND PROPERTIES Contractor JVR PLBG AND HEATING INC | Application filed in conjunction with Alteration CO-Application Q01260275-I1 for the installation of plumbing fixtures and plumbing piping i… |
| Q01260275 ↗ | 142-05 184 STREET QUEENS | Alteration CO | Permit Issued | 08/21/2025 | 10/22/2025 | Design NS ENGINEERING, P.C. Owner KINGSLAND PROPERTIES Contractor BILLY BUILDERS INC | CONVERSION OF AN EXIST. 1 STORY, 1 FAMILY BRICK/FRAME BUILDING W/ CELLAR TO A 2 STORY, 2 FAMILY DWELLING WITH HORIZONTAL & VERTICAL EXTENSIO… |
| Q01104299 ↗ | 75-15 195 STREET QUEENS | Alteration CO | Permit Issued | 09/30/2024 | 07/17/2025 | Design NS ENGINEERING, P.C. Contractor H BUILDING MANAGEMENT INC Filer HN REPUBLIC LLC | EXIST. 2 STORY, 1 FAMILY FRAME BUILDING W/ CELLAR. PROPOSED INTERIOR RENOVATION, VERTICAL AND HORIZONTAL EXTENSION AT SIDE & REAR. RESOLVE D… |
| Q01121881 ↗ | 71-33 260 STREET QUEENS | Alteration | Signed-off | 10/07/2024 | 03/27/2025 | Design NS ENGINEERING, P.C. Contractor MAHI PAINTING INC | PROPOSED NEW 10' X 10' WOODEN DECK ADDITION AT FRONT YARD OF SECOND FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01068253 ↗ | 82-16 251 STREET QUEENS | Alteration | Signed-off | 08/21/2024 | 01/13/2025 | Design NS ENGINEERING, P.C. Contractor CREATIVE BUILDING MANAGEM | LEGALIZATION OF REMOVAL OF EXISTING KITCHEN CABINETS AND PARTITIONS IN THE CELLAR TO COMPLY WITH VIOLATIONS #34557639K & #34557638Z, AND REV… |
| Q00922836 ↗ | 75-15 195 STREET QUEENS | Alteration | Permit Issued | 09/20/2023 | 12/04/2024 | Design NS ENGINEERING, P.C. Contractor H BUILDING MANAGEMENT INC | EXISTING 2-STORY, 1 FAMILY FRAME BUILDING WITH CELLAR. PROPOSED INTERIOR RENOVATION AND LEGALIZATION OF HORIZONTAL AND VERTICAL EXTENSION AT… |
| Q00954828 ↗ | 263-07 79 AVENUE QUEENS | Alteration | Signed-off | 11/09/2023 | 07/24/2024 | Design NS ENGINEERING, P.C. Contractor WATERMARK PLUMBING CORP | Removing an existing unauthorized gas line in the cellar and adding an area drain. |
| Q00954707 ↗ | 263-07 79 AVENUE QUEENS | Alteration | Signed-off | 11/17/2023 | 02/28/2024 | Design NS ENGINEERING, P.C. Contractor AKEM CONSTRUCTION INC | Proposed adding a new concrete block stair to legalize the existing three-fixture bathroom in the cellar. (RCA #4929290) No change in use, b… |
| Building | Filings | Most Recent |
|---|---|---|
| 75-15 195 STREET ↗ | 6 | 08/24/2026 |
| 142-05 184 STREET ↗ | 3 | 05/26/2026 |
| 143-23 ROSE AVENUE ↗ | 1 | 03/05/2026 |
| 71-33 260 STREET ↗ | 1 | 10/07/2024 |
| 82-16 251 STREET ↗ | 1 | 08/21/2024 |
| 263-07 79 AVENUE ↗ | 4 | 07/02/2024 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 08/22/2026 | Concrete - Cast-In-Place | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | Chimneys and vents | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | Structural Wood Frame | 75-15 195 STREET | NAVPREET SINGH | progress |
| 08/22/2026 | Air barrier - visual inspection | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Final | 75-15 195 STREET | NAVPREET SINGH | progress |
| 08/22/2026 | Footing and Foundation | 75-15 195 STREET | NAVPREET SINGH | progress |
| 08/22/2026 | Permanent certificate | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Maintenance information | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Insulation placement and R values | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Air barrier — testing | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Electric vehicle service equipment requirements | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Structural Stability – Alterations of existing buildings | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | Fenestration areas | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Metering | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Energy Code Compliance Inspections | 75-15 195 STREET | NAVPREET SINGH | progress |
| 08/22/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | HVAC-R and service water heating equipment | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Mechanical Systems | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | Heating Systems | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | Fire-Resistant Penetrations and Joints | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | Fenestration air leakage | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Excavations - Sheeting, Shoring, and Bracing | 75-15 195 STREET | NAVPREET SINGH | special |
| 08/22/2026 | Interior lighting power | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Fenestration and door U-factor and product ratings | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Duct leakage testing, insulation and design | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | HVAC-R and service water heating system controls | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Ventilation and air distribution system | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | HVAC-R and service water piping design and insulation | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 08/22/2026 | Fire-Resistance Rated Construction | 75-15 195 STREET | NAVPREET SINGH | progress |
| 07/31/2026 | Fire-Resistance Rated Construction | 75-15 195 STREET | NAVPREET SINGH | progress |
| 07/31/2026 | Maintenance information | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Air barrier - visual inspection | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Interior lighting power | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Ventilation and air distribution system | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Fenestration areas | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Fenestration air leakage | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | HVAC-R and service water heating equipment | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Air barrier — testing | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | HVAC-R and service water heating system controls | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Fenestration and door U-factor and product ratings | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Metering | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Insulation placement and R values | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | HVAC-R and service water piping design and insulation | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Electric vehicle service equipment requirements | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Duct leakage testing, insulation and design | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Permanent certificate | 75-15 195 STREET | NAVPREET SINGH | energy_progress |
| 07/31/2026 | Concrete - Cast-In-Place | 75-15 195 STREET | NAVPREET SINGH | special |
| 07/31/2026 | Excavations - Sheeting, Shoring, and Bracing | 75-15 195 STREET | NAVPREET SINGH | special |
| 07/31/2026 | Structural Stability – Alterations of existing buildings | 75-15 195 STREET | NAVPREET SINGH | special |
| 07/31/2026 | Heating Systems | 75-15 195 STREET | NAVPREET SINGH | special |