| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| X01363985 ↗ | 617 REISS PLACE BRONX | Alteration | Signed-off | 02/28/2026 | 03/13/2026 | Design OKG ENGINEERS, PLLC Contractor ADNET ENTERPRISES | INSTALLATION OF METAL COPING IN THE REAR PARAPET WALL AND STUCCO WORK IN THE RIGHT SIDE OF THE WALL (EAST ELEVATION) AS PER PLANS SUBMITTED … |
| B00764352 ↗ | 1498 FULTON STREET BROOKLYN | Alteration | Signed-off | 07/05/2022 | 08/01/2025 | Design OKG ENGINEERS, PLLC Contractor ADNET ENTERPRISES | Plumbing work associated with Replacement of Existing HVAC Units with (2) 10-Ton HVAC Units filed under B00764352-I1. No Change… |
| Name | Projects together | Most recent |
|---|---|---|
| ADNET ENTERPRISES LLC | 2 | 02/28/2026 |
| GENET PLBG AND HTG CORP | 1 | 07/16/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| X01363985 ↗ | 617 REISS PLACE BRONX | Alteration | Signed-off | 02/28/2026 | 03/13/2026 | Design OKG ENGINEERS, PLLC Contractor ADNET ENTERPRISES | INSTALLATION OF METAL COPING IN THE REAR PARAPET WALL AND STUCCO WORK IN THE RIGHT SIDE OF THE WALL (EAST ELEVATION) AS PER PLANS SUBMITTED … |
| B00764352 ↗ | 1498 FULTON STREET BROOKLYN | Alteration | Signed-off | 07/05/2022 | 08/01/2025 | Design OKG ENGINEERS, PLLC Contractor ADNET ENTERPRISES | Plumbing work associated with Replacement of Existing HVAC Units with (2) 10-Ton HVAC Units filed under B00764352-I1. No Change… |
| Building | Filings | Most Recent |
|---|---|---|
| 617 REISS PLACE ↗ | 1 | 02/28/2026 |
| 1498 FULTON STREET ↗ | 1 | 07/05/2022 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 06/24/2022 | Energy Code Compliance Inspections | 1498 FULTON STREET | OSEI GYEBI | progress |
| 06/24/2022 | Final | 1498 FULTON STREET | OSEI GYEBI | progress |
| 06/24/2022 | HVAC-R and service water heating system controls | 1498 FULTON STREET | OSEI GYEBI | energy_progress |
| 06/24/2022 | Maintenance information | 1498 FULTON STREET | OSEI GYEBI | energy_progress |
| 06/24/2022 | HVAC-R and service water piping design and insulation | 1498 FULTON STREET | OSEI GYEBI | energy_progress |
| 06/24/2022 | HVAC-R and service water heating equipment | 1498 FULTON STREET | OSEI GYEBI | energy_progress |
| 06/24/2022 | Mechanical Systems | 1498 FULTON STREET | OSEI GYEBI | special |