| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00766582 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/29/2022 | 01/16/2024 | Design SMALLEY ENGINEERING, P.C. Owner HAPPYROCK PARTNERS, L.P. Contractor J.G.C PLBG & HTG INC Filer JAM CONSULTANTS, INC. | REMOVAL, RELOCATION AND INSTALLATION OF PLUMBING FIXTURES AND INSTALLTION OF GAS METERS. |
| Q00766601 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/28/2022 | 12/22/2022 | Design SMALLEY ENGINEERING, P.C. Owner HAPPYROCK PARTNERS, L.P. Contractor CAPITOL FIRE SPRINKLER CO Filer JAM CONSULTANTS, INC. | REMOVAL, RELOCATION AND INSTALLATION OF SPRINKLER HEADS. |
| Q00766571 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/29/2022 | 10/14/2022 | Design SMALLEY ENGINEERING, P.C. Owner HAPPYROCK PARTNERS, L.P. Contractor COOK & KRUPA LLC Filer JAM CONSULTANTS, INC. | MODIFICATION OF MECHANICAL SYSTEM AND INSTALLATION OF CONDENSING UNIT. |
| Q00767645 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/21/2022 | 10/07/2022 | Design DOUGLAS R. VAGGI, ARCHITECT Owner HAPPYROCK PARTNERS, L.P. Contractor COOK & KRUPA LLC Filer JAM CONSULTANTS, INC. | REMOVAL AND INSTALLATION OF INTERIOR PARTITIONS, FLOORING AND FIXTURES. STRUCTURAL WORK RELATED TO NEW WALL OPENINGS. |
| Q00311078 ↗ | 26-23 18 STREET QUEENS | Alteration | Signed-off | 06/08/2020 | 11/23/2020 | Design DOUGLAS R. VAGGI, ARCHITECT Contractor SAL DAMICO CONSTR Filer JAM CONSULTANTS, INC. | Installation of toilet exhaust in new bathroom on 1st floor and vent ductwork to roof. Construction filed under application # 421958028. Plu… |
| Q00311114 ↗ | 26-23 18 STREET QUEENS | Alteration | Signed-off | 06/03/2020 | 06/24/2020 | Design DOUGLAS R. VAGGI, ARCHITECT Contractor SCHUMACHER & FARLEY P&H C Filer JAM CONSULTANTS, INC. | Installation of (1) toilet and (1) lavatory in new handicap bathroom. Construction filed under separate application # 421958028. Mechanical … |
| Name | Projects together | Most recent |
|---|---|---|
| DOUGLAS R. VAGGI, ARCHITECT | 3 | 12/20/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| COOK & KRUPA LLC | 2 | 12/20/2022 |
| CAPITOL FIRE SPRINKLER CO | 1 | 12/15/2022 |
| J.G.C PLBG & HTG INC | 1 | 01/30/2024 |
| JKT CONSTRUCTION INC | 1 | 11/13/2019 |
| SAL D'AMICO CONSTR. INC | 1 | 06/08/2020 |
| SCHUMACHER & FARLEY P&H C | 1 | 06/03/2020 |
| Name | Projects together | Most recent |
|---|---|---|
| HAPPYROCK PARTNERS, L.P. | 4 | 01/30/2024 |
| CAIOLA REAL ESTATE GROUP | 1 | 11/13/2019 |
| Name | Projects together | Most recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 4 | 01/30/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00766582 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/29/2022 | 01/16/2024 | Design SMALLEY ENGINEERING, P.C. Owner HAPPYROCK PARTNERS, L.P. Contractor J.G.C PLBG & HTG INC Filer JAM CONSULTANTS, INC. | REMOVAL, RELOCATION AND INSTALLATION OF PLUMBING FIXTURES AND INSTALLTION OF GAS METERS. |
| Q00766601 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/28/2022 | 12/22/2022 | Design SMALLEY ENGINEERING, P.C. Owner HAPPYROCK PARTNERS, L.P. Contractor CAPITOL FIRE SPRINKLER CO Filer JAM CONSULTANTS, INC. | REMOVAL, RELOCATION AND INSTALLATION OF SPRINKLER HEADS. |
| Q00766571 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/29/2022 | 10/14/2022 | Design SMALLEY ENGINEERING, P.C. Owner HAPPYROCK PARTNERS, L.P. Contractor COOK & KRUPA LLC Filer JAM CONSULTANTS, INC. | MODIFICATION OF MECHANICAL SYSTEM AND INSTALLATION OF CONDENSING UNIT. |
| Q00767645 ↗ | 60-01 31 AVENUE QUEENS | Alteration | Signed-off | 09/21/2022 | 10/07/2022 | Design DOUGLAS R. VAGGI, ARCHITECT Owner HAPPYROCK PARTNERS, L.P. Contractor COOK & KRUPA LLC Filer JAM CONSULTANTS, INC. | REMOVAL AND INSTALLATION OF INTERIOR PARTITIONS, FLOORING AND FIXTURES. STRUCTURAL WORK RELATED TO NEW WALL OPENINGS. |
| Q00311078 ↗ | 26-23 18 STREET QUEENS | Alteration | Signed-off | 06/08/2020 | 11/23/2020 | Design DOUGLAS R. VAGGI, ARCHITECT Contractor SAL DAMICO CONSTR Filer JAM CONSULTANTS, INC. | Installation of toilet exhaust in new bathroom on 1st floor and vent ductwork to roof. Construction filed under application # 421958028. Plu… |
| Q00311114 ↗ | 26-23 18 STREET QUEENS | Alteration | Signed-off | 06/03/2020 | 06/24/2020 | Design DOUGLAS R. VAGGI, ARCHITECT Contractor SCHUMACHER & FARLEY P&H C Filer JAM CONSULTANTS, INC. | Installation of (1) toilet and (1) lavatory in new handicap bathroom. Construction filed under separate application # 421958028. Mechanical … |
| M00220725 ↗ | 136 WEST 23 STREET MANHATTAN | Alteration | Signed-off | 11/13/2019 | 11/20/2019 | Design SMALLEY ENGINEERING, P.C. Owner CAIOLA REAL ESTATE GROUP Contractor JKT CONSTRUCTION INC Filer JAM CONSULTANTS, INC. | Filing application to obtain correct Equipment Use Cards. All work performed under application #121899945 and #122827913. |
| Building | Filings | Most Recent |
|---|---|---|
| 60-01 31 AVENUE ↗ | 11 | 01/30/2024 |
| 26-23 18 STREET ↗ | 2 | 06/08/2020 |
| 136 WEST 23 STREET ↗ | 1 | 11/13/2019 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 02/01/2024 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 01/16/2024 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/23/2022 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/23/2022 | Sprinkler Systems | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/22/2022 | Exterior lighting power | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/22/2022 | Interior lighting power | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/22/2022 | Fenestration air leakage | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/22/2022 | Lighting controls | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/22/2022 | Fenestration areas | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/22/2022 | Fenestration and door U-factor and product ratings | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/22/2022 | Energy Code Compliance Inspections | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/22/2022 | Final | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/22/2022 | Fire-Resistance Rated Construction | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/22/2022 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/22/2022 | Structural Stability – Alterations of existing buildings | 60-01 31 AVENUE | Young Suh | special |
| 12/22/2022 | Structural Steel - Details | 60-01 31 AVENUE | Young Suh | special |
| 12/22/2022 | Structural Steel - Welding | 60-01 31 AVENUE | Young Suh | special |
| 12/19/2022 | Fenestration areas | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/19/2022 | Exterior lighting power | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/19/2022 | Interior lighting power | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/19/2022 | Lighting controls | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/19/2022 | Fenestration air leakage | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/19/2022 | Fenestration and door U-factor and product ratings | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/19/2022 | Fire-Resistance Rated Construction | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/19/2022 | Final | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/19/2022 | Energy Code Compliance Inspections | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/19/2022 | Structural Steel - Welding | 60-01 31 AVENUE | Young Suh | special |
| 12/19/2022 | Structural Steel - Details | 60-01 31 AVENUE | Young Suh | special |
| 12/19/2022 | Structural Stability – Alterations of existing buildings | 60-01 31 AVENUE | Young Suh | special |
| 12/19/2022 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/13/2022 | Structural Steel - Welding | 60-01 31 AVENUE | Young Suh | special |
| 12/13/2022 | Energy Code Compliance Inspections | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/13/2022 | Final | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/13/2022 | Fire-Resistance Rated Construction | 60-01 31 AVENUE | DOUGLAS VAGGI | progress |
| 12/13/2022 | Fenestration air leakage | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/13/2022 | Exterior lighting power | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/13/2022 | Fenestration and door U-factor and product ratings | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/13/2022 | Lighting controls | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/13/2022 | Fenestration areas | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/13/2022 | Interior lighting power | 60-01 31 AVENUE | DOUGLAS VAGGI | energy_progress |
| 12/13/2022 | Structural Steel - Details | 60-01 31 AVENUE | Young Suh | special |
| 12/13/2022 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/13/2022 | Structural Stability – Alterations of existing buildings | 60-01 31 AVENUE | Young Suh | special |
| 12/12/2022 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/12/2022 | Sprinkler Systems | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 12/12/2022 | Fire-Resistant Penetrations and Joints | 60-01 31 AVENUE | PHILIP SMALLEY | special |
| 02/06/2020 | Mechanical Systems | 26-23 18 STREET | PHILIP SMALLEY | special |
| 02/06/2020 | Final | 26-23 18 STREET | DOUGLAS VAGGI | progress |
| 02/06/2020 | Shutoff dampers | 26-23 18 STREET | PHILIP SMALLEY | energy_progress |
| 09/03/2019 | Final | 136 WEST 23 STREET | PHILIP SMALLEY | progress |