| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00936163 ↗ | 74-15 NORTHERN BOULEVARD QUEENS | Alteration | Filed — no permit on record | 09/21/2023 | — | Design TEKTON ARCHITECTURE | — |
| Q00660449 ↗ | 5-33 48TH AVENUE QUEENS | Alteration CO | Permit Issued | 02/09/2022 | 03/25/2022 | Design NDKAZALAS ARCHITECTURE P.C. Contractor ILLAN-SP CORP Filer BRIDGE EXPEDITING INC. | CONVERT TWO COMMERCIAL UNITS ON THE FIRST FLOOR INTO FIVE COMMERCIAL UNITS. WORK INCLUDES CHANGE OF OCCUPANCY AND EGRESS. |
| Q00436110 ↗ | 47-09 36 STREET QUEENS | Alteration | Signed-off | 12/04/2020 | 07/16/2021 | Design TEKTON ARCHITECTURE Contractor BYPASS MECHANICAL CORP | FILING TO REMOVE EXISTING BATHROOMS ON 1ST AND 2ND FLOOR AND RELOCATE AS PER PLANS, IN CONJUNCTION WITH BIS APPLICATION 440652535. NO CHANG… |
| Name | Projects together | Most recent |
|---|---|---|
| TEKTON ARCHITECTURE | 2 | 10/05/2023 |
| NDKAZALAS ARCHITECTURE P.C. | 1 | 02/27/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| BYPASS MECHANICAL CORP | 1 | 12/04/2020 |
| ILLAN-SP CORP | 1 | 02/27/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| BRIDGE EXPEDITING INC. | 1 | 02/27/2025 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00936163 ↗ | 74-15 NORTHERN BOULEVARD QUEENS | Alteration | Filed — no permit on record | 09/21/2023 | — | Design TEKTON ARCHITECTURE | — |
| Q00660449 ↗ | 5-33 48TH AVENUE QUEENS | Alteration CO | Permit Issued | 02/09/2022 | 03/25/2022 | Design NDKAZALAS ARCHITECTURE P.C. Contractor ILLAN-SP CORP Filer BRIDGE EXPEDITING INC. | CONVERT TWO COMMERCIAL UNITS ON THE FIRST FLOOR INTO FIVE COMMERCIAL UNITS. WORK INCLUDES CHANGE OF OCCUPANCY AND EGRESS. |
| Q00436110 ↗ | 47-09 36 STREET QUEENS | Alteration | Signed-off | 12/04/2020 | 07/16/2021 | Design TEKTON ARCHITECTURE Contractor BYPASS MECHANICAL CORP | FILING TO REMOVE EXISTING BATHROOMS ON 1ST AND 2ND FLOOR AND RELOCATE AS PER PLANS, IN CONJUNCTION WITH BIS APPLICATION 440652535. NO CHANG… |
| Building | Filings | Most Recent |
|---|---|---|
| 5-33 48TH AVENUE ↗ | 4 | 02/27/2025 |
| 74-15 NORTHERN BOULEVARD ↗ | 1 | 09/21/2023 |
| 47-09 36 STREET ↗ | 1 | 12/04/2020 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 02/25/2025 | Fire-Resistant Penetrations and Joints | 5-33 48TH AVENUE | anastasios tzakas | special |
| 02/25/2025 | Energy Code Compliance Inspections | 5-33 48TH AVENUE | anastasios tzakas | progress |
| 02/25/2025 | Fire-Resistance Rated Construction | 5-33 48TH AVENUE | anastasios tzakas | progress |
| 02/25/2025 | Fenestration air leakage | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 02/25/2025 | Interior lighting power | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 02/25/2025 | Metering | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 02/25/2025 | Air barrier - visual inspection | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 02/25/2025 | Fenestration and door U-factor and product ratings | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 02/25/2025 | Lighting controls | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 02/25/2025 | Fenestration areas | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 06/13/2024 | Interior lighting power | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 06/13/2024 | Fenestration air leakage | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 06/13/2024 | Lighting controls | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 06/13/2024 | Fenestration areas | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 06/13/2024 | Fire-Resistance Rated Construction | 5-33 48TH AVENUE | anastasios tzakas | progress |
| 06/13/2024 | Energy Code Compliance Inspections | 5-33 48TH AVENUE | anastasios tzakas | progress |
| 06/13/2024 | Fire-Resistant Penetrations and Joints | 5-33 48TH AVENUE | anastasios tzakas | special |
| 06/13/2024 | Fenestration and door U-factor and product ratings | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 06/13/2024 | Air barrier - visual inspection | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 06/13/2024 | Metering | 5-33 48TH AVENUE | anastasios tzakas | energy_progress |
| 09/19/2023 | Exterior Insulation and Finish Systems (EIFS) | 74-15 NORTHERN BOULEVARD | anastasios tzakas | special |
| 09/19/2023 | Fire-Resistant Penetrations and Joints | 74-15 NORTHERN BOULEVARD | anastasios tzakas | special |
| 09/19/2023 | Wall Panels, Curtain Walls, and Veneers | 74-15 NORTHERN BOULEVARD | anastasios tzakas | special |
| 06/07/2021 | Fire-Resistant Penetrations and Joints | 47-09 36 STREET | anastasios tzakas | special |
| 12/04/2020 | Maintenance information | 47-09 36 STREET | anastasios tzakas | energy_progress |