| Job | Address | Type | Status | Filed | Latest permit | Description |
|---|---|---|---|---|---|---|
| B08050677 ↗ | 5423 1 AVENUE BROOKLYN | New Building | Permit Issued | 12/20/2022 | 09/22/2026 | STRUCTURAL INSTALLATION AS PER SHOWN ON PLANS FILED HEREWITH IN CONJUNCTION WITH NEW BUILDING APPLICATION B08050677-I1 |
| M00587493 ↗ | 497 WEST STREET MANHATTAN | New Building | Permit Issued | 09/02/2021 | 08/14/2026 | Support of excavation work in conjunction with New Building M00587493-I1 |
| B00645685 ↗ | 544 CARROLL STREET BROOKLYN | New Building | Permit Issued | 12/14/2021 | 07/07/2026 | FOUNDATION ELEMENTS FOR 421A. NEW BUILDING APPLICATION B00645685-I1, FOUNDATION APPLICATION B00645685-S2. |
| M00505081 ↗ | 665 5 AVENUE MANHATTAN | New Building | Permit Issued | 06/23/2021 | 12/16/2025 | Support of Excavation in conjunction with New Building. |
| B00637594 ↗ | 204 4 AVENUE BROOKLYN | New Building | Permit Issued | 12/08/2021 | 04/01/2025 | FILING HEREWITH SUPPORT OF EXCAVATION IN CONJUNCTION WITH NEW BUILDING AS PER PLANS. |
| M00776019 ↗ | 2491 8 AVENUE MANHATTAN | Alteration | Signed-off | 09/13/2022 | 06/30/2023 | PAA is being field to revise the original filing to reflect that the scope of work is not an asbestos project as defined the regulation of N… |
| Job | Address | Type | Status | Filed | Latest permit | Description |
|---|---|---|---|---|---|---|
| B08050677 ↗ | 5423 1 AVENUE BROOKLYN | New Building | Permit Issued | 12/20/2022 | 09/22/2026 | STRUCTURAL INSTALLATION AS PER SHOWN ON PLANS FILED HEREWITH IN CONJUNCTION WITH NEW BUILDING APPLICATION B08050677-I1 |
| M00587493 ↗ | 497 WEST STREET MANHATTAN | New Building | Permit Issued | 09/02/2021 | 08/14/2026 | Support of excavation work in conjunction with New Building M00587493-I1 |
| B00645685 ↗ | 544 CARROLL STREET BROOKLYN | New Building | Permit Issued | 12/14/2021 | 07/07/2026 | FOUNDATION ELEMENTS FOR 421A. NEW BUILDING APPLICATION B00645685-I1, FOUNDATION APPLICATION B00645685-S2. |
| M00505081 ↗ | 665 5 AVENUE MANHATTAN | New Building | Permit Issued | 06/23/2021 | 12/16/2025 | Support of Excavation in conjunction with New Building. |
| B00637594 ↗ | 204 4 AVENUE BROOKLYN | New Building | Permit Issued | 12/08/2021 | 04/01/2025 | FILING HEREWITH SUPPORT OF EXCAVATION IN CONJUNCTION WITH NEW BUILDING AS PER PLANS. |
| M00776019 ↗ | 2491 8 AVENUE MANHATTAN | Alteration | Signed-off | 09/13/2022 | 06/30/2023 | PAA is being field to revise the original filing to reflect that the scope of work is not an asbestos project as defined the regulation of N… |
| M00875687 ↗ | 161 WILLIAM MANHATTAN | Alteration | Signed-off | 05/25/2023 | 05/31/2023 | Emergency work. Install structural tiebacks along western wall of 161 William Street on floors 1-5. Work done under emergency conditions du… |
| M00870920 ↗ | 55 ANN STREET MANHATTAN | Alteration | Signed-off | 05/09/2023 | 05/11/2023 | Temporary shoring and bracing @ Exp 4 party wall from sub-cellar to roof level, Per Immediate Emergency Declaration (IED) |
| Q00244785 ↗ | 23-20 JACKSON AVENUE QUEENS | Alteration | Signed-off | 10/21/2019 | 12/22/2021 | Foundation work in connection with the New Building. No change in use, egress or occupancy. |
| Name | Jobs together | Most recent |
|---|---|---|
| THORNTON TOMASETTI | 6 | 08/06/2026 |
| JX FLAME SOLUTION INC | 2 | 08/17/2026 |
| L+Z ARCHITECTURE, D.P.C. | 2 | 08/17/2026 |
| MRCE | 2 | 08/17/2026 |
| VENTROP ENGINEERING CONSULTING GROU | 2 | 08/17/2026 |
| WSP | 2 | 08/17/2026 |
| AAI ARCHITECTS, P.C. | 1 | 06/04/2026 |
| AKRF, INC. | 1 | 08/20/2026 |
| ANCORA ENGINEERING, PLLC | 1 | 08/06/2026 |
| BKSK ARCHITECTS, LLP | 1 | 08/06/2026 |
| ENNEAD ARCHITECTS | 1 | 08/20/2026 |
| FNA ENGINEERING SERVICES PC | 1 | 08/20/2026 |
| GEA CONSULTING ENGINEERS | 1 | 08/06/2026 |
| GZA GEOENVIRONMENTAL OF NEW YORK | 1 | 08/06/2026 |
| JAROS BAUM & BOLLES | 1 | 08/20/2026 |
| KONOSKI ENGINEERING PLLC | 1 | 08/20/2026 |
| LANGAN ENGINEERING | 1 | 06/04/2026 |
| OVE ARUP & PARTNERS PC | 1 | 06/04/2026 |
| PHILIP HABIB & ASSOCIATES | 1 | 08/06/2026 |
| SEVERUD ASSOCIATES | 1 | 08/20/2026 |
| Name | Jobs together | Most recent |
|---|---|---|
| LEEDING BUILDERS GROUP LL | 2 | 08/17/2026 |
| STATE CONTRACTING CORP NY | 2 | 05/25/2023 |
| TT MECHANICAL CORP | 2 | 08/17/2026 |
| ALMAR PLUMBING & HTG CORP | 1 | 08/20/2026 |
| C C CONTROLLED COMBUSTION | 1 | 06/04/2026 |
| DONATO PLUMBING GROUP INC | 1 | 08/06/2026 |
| JCC CONSTRUCTION CORP | 1 | 08/20/2026 |
| KG SPRINKLER CORP | 1 | 08/06/2026 |
| PAVARINI MCGOVERN LLC | 1 | 06/04/2026 |
| RB HTG CONSULTING GROUP | 1 | 08/20/2026 |
| SHR GROUP INC | 1 | 12/05/2022 |
| SUFFOLK CONSTRUCTION COMP | 1 | 08/20/2026 |
| THE VOREA CONSTRUCTION CO | 1 | 01/02/2020 |
| TITANIUM CONSTRUCTION SER | 1 | 08/06/2026 |
| Name | Jobs together | Most recent |
|---|---|---|
| AVERY HALL INVESTMENTS | 2 | 08/17/2026 |
| 161 WILLIAM STREET,LLC | 1 | 05/25/2023 |
| ROLEX REALTY COMPANY, LLC | 1 | 06/04/2026 |
| ROLEX USA | 1 | 06/04/2026 |
| TERI NICHOLS IFM LLC | 1 | 08/20/2026 |
| THE VOREA CONSTRUCTION COMPANIES LL | 1 | 01/02/2020 |
| WEBB & BROOKER INC | 1 | 12/05/2022 |
| Name | Jobs together | Most recent |
|---|---|---|
| JM ZONING, LLC. | 2 | 08/17/2026 |
| A1 EXPEDITING SERVICE CORP. | 1 | 06/04/2026 |
| DVA Advisors | 1 | 08/06/2026 |
| JAM CONSULTANTS, INC. | 1 | 05/25/2023 |
| OUTSOURCE CONSULTANTS, INC. | 1 | 08/20/2026 |
| THORNTON TOMASETTI | 1 | 12/05/2022 |
| WILLIAM VITACCO ASSOCIATES | 1 | 08/06/2026 |
| Building | Filings | Most Recent |
|---|---|---|
| 204 4 AVENUE ↗ | 5 | 06/25/2026 |
| 544 CARROLL STREET ↗ | 6 | 05/19/2026 |
| 665 5 AVENUE ↗ | 6 | 05/11/2026 |
| 5423 1 AVENUE ↗ | 2 | 02/04/2026 |
| 497 WEST STREET ↗ | 2 | 04/24/2025 |
| 161 WILLIAM ↗ | 1 | 05/25/2023 |
| 55 ANN STREET ↗ | 1 | 05/09/2023 |
| 2491 8 AVENUE ↗ | 2 | 12/05/2022 |
| 23-20 JACKSON AVENUE ↗ | 1 | 10/21/2019 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 06/16/2026 | Fenestration areas | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Vestibules | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Insulation placement and R values | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Fenestration and door U-factor and product ratings | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Air barrier continuity plan testing | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Air barrier - visual inspection | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Protection of exposed foundation insulation | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Fenestration air leakage | 204 4 AVENUE | Walter Hartnett | energy_progress |
| 06/16/2026 | Fire-Resistance Rated Construction | 204 4 AVENUE | AILANTO DANIEL MINAWI | progress |
| 06/16/2026 | Wall Panels, Curtain Walls, and Veneers | 204 4 AVENUE | Walter Hartnett | special |
| 06/16/2026 | Masonry | 204 4 AVENUE | AILANTO DANIEL MINAWI | special |
| 06/16/2026 | Fire-Resistant Penetrations and Joints | 204 4 AVENUE | AILANTO DANIEL MINAWI | special |
| 06/16/2026 | Exterior Insulation and Finish Systems (EIFS) | 204 4 AVENUE | AILANTO DANIEL MINAWI | special |
| 05/19/2026 | Masonry | 544 CARROLL STREET | AILANTO DANIEL MINAWI | special |
| 05/19/2026 | Wall Panels, Curtain Walls, and Veneers | 544 CARROLL STREET | Walter Hartnett | special |
| 05/19/2026 | Fire-Resistant Penetrations and Joints | 544 CARROLL STREET | AILANTO DANIEL MINAWI | special |
| 05/19/2026 | Exterior Insulation and Finish Systems (EIFS) | 544 CARROLL STREET | AILANTO DANIEL MINAWI | special |
| 05/19/2026 | Fire-Resistance Rated Construction | 544 CARROLL STREET | AILANTO DANIEL MINAWI | progress |
| 05/19/2026 | Fenestration areas | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/19/2026 | Air barrier continuity plan testing | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/19/2026 | Vestibules | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/19/2026 | Air barrier - visual inspection | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/19/2026 | Insulation placement and R values | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/19/2026 | Protection of exposed foundation insulation | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/19/2026 | Fenestration and door U-factor and product ratings | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/19/2026 | Fenestration air leakage | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Fenestration air leakage | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Fire-Resistance Rated Construction | 544 CARROLL STREET | AILANTO DANIEL MINAWI | progress |
| 05/14/2026 | Wall Panels, Curtain Walls, and Veneers | 544 CARROLL STREET | Walter Hartnett | special |
| 05/14/2026 | Masonry | 544 CARROLL STREET | AILANTO DANIEL MINAWI | special |
| 05/14/2026 | Fire-Resistant Penetrations and Joints | 544 CARROLL STREET | AILANTO DANIEL MINAWI | special |
| 05/14/2026 | Exterior Insulation and Finish Systems (EIFS) | 544 CARROLL STREET | AILANTO DANIEL MINAWI | special |
| 05/14/2026 | Fenestration and door U-factor and product ratings | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Fenestration areas | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Air barrier continuity plan testing | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Air barrier - visual inspection | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Insulation placement and R values | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Protection of exposed foundation insulation | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/14/2026 | Vestibules | 544 CARROLL STREET | Walter Hartnett | energy_progress |
| 05/13/2026 | Lowest Floor Elevation | 665 5 AVENUE | ALEXIS SCHLESSINGERMAN | progress |
| 05/13/2026 | Fire-Resistance Rated Construction | 665 5 AVENUE | ALEXIS SCHLESSINGERMAN | progress |
| 05/13/2026 | Luminous Exit Path Markings | 665 5 AVENUE | ALEXIS SCHLESSINGERMAN | special |
| 05/13/2026 | Preliminary | 665 5 AVENUE | ALEXIS SCHLESSINGERMAN | progress |
| 05/13/2026 | Fenestration and door U-factor and product ratings | 665 5 AVENUE | Walter Hartnett | energy_progress |
| 05/13/2026 | Air barrier - visual inspection | 665 5 AVENUE | Walter Hartnett | energy_progress |
| 05/13/2026 | Protection of exposed foundation insulation | 665 5 AVENUE | ALEXIS SCHLESSINGERMAN | energy_progress |
| 05/13/2026 | Maintenance information | 665 5 AVENUE | ALEXIS SCHLESSINGERMAN | energy_progress |
| 05/13/2026 | Exterior lighting power | 665 5 AVENUE | ALEXIS SCHLESSINGERMAN | energy_progress |
| 05/13/2026 | Air barrier continuity plan testing | 665 5 AVENUE | Walter Hartnett | energy_progress |
| 05/13/2026 | Fenestration air leakage | 665 5 AVENUE | Walter Hartnett | energy_progress |