| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00456660 ↗ | 141-15 72 CRESCENT QUEENS | Alteration | Permit Issued | 02/11/2021 | 11/20/2023 | Design TOPOS DESIGNS, INC. Contractor SCAMPA CONTRACTING, CORP Filer PAUL MOK, P.E., PC | WE ARE REMOVING AND REPLACING PLUMBING FIXTURES AND ADDING NEW THREE PIECE BATHROOMS ON THE FIRST AND SECOND FLOOR. WE ARE ALSO REMOVING AND… |
| Q00506371 ↗ | 53-02 BROWVALE LANE QUEENS | Alteration CO | Filed — no permit on record | 04/27/2021 | — | Design TOPOS DESIGNS, INC. | — |
| Q00358735 ↗ | 25-14 BROADWAY QUEENS | Alteration | Permit Issued | 06/19/2020 | 03/30/2021 | Design TOPOS DESIGNS, INC. Contractor AFGO MECHANICAL SVCS | We propose to renovate existing Club (Community Facility U.G.4) on the 3rd floor. No change in use, occupancy or egress. |
| Q00435335 ↗ | 31-16 30 AVENUE QUEENS | Alteration | Filed — no permit on record | 02/11/2021 | — | Design TOPOS DESIGNS, INC. | — |
| Name | Projects together | Most recent |
|---|---|---|
| STAVROS I. MALLIAROS, P.E., P.C. | 1 | 10/31/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| AFGO MECHANICAL SVCS INC | 1 | 02/04/2021 |
| GA INDUSTRIES INC | 1 | 02/04/2021 |
| PLBG P & H INC | 1 | 10/31/2024 |
| SCAMPA CONTRACTING, CORP | 1 | 10/31/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| PAUL MOK, P.E., PC | 1 | 10/31/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00456660 ↗ | 141-15 72 CRESCENT QUEENS | Alteration | Permit Issued | 02/11/2021 | 11/20/2023 | Design TOPOS DESIGNS, INC. Contractor SCAMPA CONTRACTING, CORP Filer PAUL MOK, P.E., PC | WE ARE REMOVING AND REPLACING PLUMBING FIXTURES AND ADDING NEW THREE PIECE BATHROOMS ON THE FIRST AND SECOND FLOOR. WE ARE ALSO REMOVING AND… |
| Q00506371 ↗ | 53-02 BROWVALE LANE QUEENS | Alteration CO | Filed — no permit on record | 04/27/2021 | — | Design TOPOS DESIGNS, INC. | — |
| Q00358735 ↗ | 25-14 BROADWAY QUEENS | Alteration | Permit Issued | 06/19/2020 | 03/30/2021 | Design TOPOS DESIGNS, INC. Contractor AFGO MECHANICAL SVCS | We propose to renovate existing Club (Community Facility U.G.4) on the 3rd floor. No change in use, occupancy or egress. |
| Q00435335 ↗ | 31-16 30 AVENUE QUEENS | Alteration | Filed — no permit on record | 02/11/2021 | — | Design TOPOS DESIGNS, INC. | — |
| Building | Filings | Most Recent |
|---|---|---|
| 141-15 72 CRESCENT ↗ | 2 | 01/13/2023 |
| 53-02 BROWVALE LANE ↗ | 1 | 04/27/2021 |
| 31-16 30 AVENUE ↗ | 1 | 02/11/2021 |
| 25-14 BROADWAY ↗ | 1 | 06/19/2020 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 11/04/2022 | Fenestration and door U-factor and product ratings | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 11/04/2022 | Insulation placement and R values | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 11/04/2022 | Fenestration areas | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 11/04/2022 | Fenestration air leakage | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 11/04/2022 | Fire-Resistant Penetrations and Joints | 141-15 72 CRESCENT | Amalia Bournias | special |
| 11/04/2022 | Energy Code Compliance | 141-15 72 CRESCENT | Amalia Bournias | progress |
| 06/10/2022 | Fenestration air leakage | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 06/10/2022 | Fenestration and door U-factor and product ratings | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 06/10/2022 | Insulation placement and R values | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 06/10/2022 | Fire-Resistant Penetrations and Joints | 141-15 72 CRESCENT | Amalia Bournias | special |
| 06/10/2022 | Energy Code Compliance | 141-15 72 CRESCENT | Amalia Bournias | progress |
| 06/10/2022 | Fenestration areas | 141-15 72 CRESCENT | Amalia Bournias | energy_progress |
| 04/23/2021 | Fenestration and door U-factor and product ratings | 53-02 BROWVALE LANE | Amalia Bournias | energy_progress |
| 04/23/2021 | Air barrier - visual inspection | 53-02 BROWVALE LANE | Amalia Bournias | energy_progress |
| 04/23/2021 | Lighting in dwelling units | 53-02 BROWVALE LANE | Amalia Bournias | energy_progress |
| 04/23/2021 | Fenestration areas | 53-02 BROWVALE LANE | Amalia Bournias | energy_progress |
| 04/23/2021 | Insulation placement and R values | 53-02 BROWVALE LANE | Amalia Bournias | energy_progress |
| 04/23/2021 | Structural Stability – Alterations of existing buildings | 53-02 BROWVALE LANE | Amalia Bournias | special |
| 04/23/2021 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | 53-02 BROWVALE LANE | Amalia Bournias | special |
| 04/23/2021 | Concrete - Cast-In-Place | 53-02 BROWVALE LANE | Amalia Bournias | special |
| 04/19/2021 | Energy Code Compliance Inspections | 53-02 BROWVALE LANE | Amalia Bournias | progress |