QUEENS · 3
1 building
3
Total Filings
3
Projects on File
1
Buildings Worked
0
Projects w/ Open Permits
Owner
Primary Trade
Activity
Projects by first filing month3 projects all-time
0123Nov '21 · 2Aug '22 · 1Nov '21Dec '21Jan '22Feb '22Mar '22Apr '22May '22Jun '22Jul '22Aug '22
bars = month · line = 3-mo average
Portfolio status
Browse projects →
Signed off3100%
By project type
Alteration3
Most active buildings
All buildings →
22-30 COLLEGE POINT BOULEVARDQUEENS · latest 09/07/2022
3 projects
Key relationships
Everyone →
Design firms
3 projects
Contractors
Most recent projects
All projects →
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
Q00698379 ↗22-30 COLLEGE POINT BOULEVARD
QUEENS
AlterationSigned-off08/17/202209/07/2022FILE MH WORKTYPE IN CONJUNCTION WITH JOB#Q00637916 & Q00639024
Q00639024 ↗22-30 COLLEGE POINT BOULEVARD
QUEENS
AlterationSigned-off11/30/202112/11/2021FILE PL WORKTYPE IN CONJUCNTION WITH JOB#Q00637916. THIS PLUMBING JOB FOR KITCHEN & FIRE SUPPRESSION SYSTEM GAS SHUT OFF VALVE.
Q00637916 ↗22-30 COLLEGE POINT BOULEVARD
QUEENS
AlterationSigned-off11/30/202112/04/2021INTERIOR RENOVATION OF EXISTING RETAIL STORE AT 1ST FLOOR. PROPOSE PLUMBING & GENERAL CONTRUCTION WORK AS PER PLAN FILED HEREWITH. NO CHANGE…
Counts cover all 3 projects (3 DOB NOW). Dated by first filing; BIS projects by first permit issuance.
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Ameriland Brook308/17/2022
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Splen Construction208/17/2022
MPS Plumbing & Heating104/18/2022
3 DOB NOW projects, anchored the same way as Buildings Worked. Status is the project's permit state today: open = at least one permit currently issued. BIS projects show their raw permit status and are not counted as open.
All 3Signed off 3
3 projects
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
Q00698379 ↗22-30 COLLEGE POINT BOULEVARD
QUEENS
AlterationSigned-off08/17/202209/07/2022FILE MH WORKTYPE IN CONJUNCTION WITH JOB#Q00637916 & Q00639024
Q00639024 ↗22-30 COLLEGE POINT BOULEVARD
QUEENS
AlterationSigned-off11/30/202112/11/2021FILE PL WORKTYPE IN CONJUCNTION WITH JOB#Q00637916. THIS PLUMBING JOB FOR KITCHEN & FIRE SUPPRESSION SYSTEM GAS SHUT OFF VALVE.
Q00637916 ↗22-30 COLLEGE POINT BOULEVARD
QUEENS
AlterationSigned-off11/30/202112/04/2021INTERIOR RENOVATION OF EXISTING RETAIL STORE AT 1ST FLOOR. PROPOSE PLUMBING & GENERAL CONTRUCTION WORK AS PER PLAN FILED HEREWITH. NO CHANGE…
Click a row for this entity's own projects, plans and documents at that building.
BuildingFilingsMost Recent
22-30 COLLEGE POINT BOULEVARD ↗307/15/2022
▾Documents — 16 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications10
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/26/2026Q00639024-P1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
08/26/2026Q00639024-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
08/26/2026Q00637916-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026Q00698379-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
08/28/2026Q00698379-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
08/23/2026Q00637916-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q00698379-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
08/23/2026Q00637916-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026Q00698379-I1 · 22-30 COLLEGE POINT BOULEVARDOpen ↗