| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01043466 ↗ | 640 COLUMBIA STREET BROOKLYN | Alteration | Signed-off | 06/05/2024 | 06/18/2024 | Owner CBRE Contractor BOUND CONSTRUCTION CORP Filer JAM CONSULTANTS, INC. | Installation of new conveyor, spiral conveyors, crossover stair, induction & transport lanes, structural supports. The removal of segments o… |
| B01020292 ↗ | 640 COLUMBIA STREET BROOKLYN | Alteration | Signed-off | 06/13/2024 | 06/17/2024 | Design SAL FATEEN ENGINEERING Contractor BOUND CONSTRUCTION CORP | The removal/relocation of existing conveyors. The installation of new conveyors, compressor system, and safety fence as shown on plans submi… |
| B00914640 ↗ | 640 COLUMBIA STREET BROOKLYN | Alteration | Signed-off | 08/11/2023 | 08/31/2023 | Design ECLIPSE ENGINEERING Owner CBRE Contractor OPC MANAGEMENT INC Filer JAM CONSULTANTS, INC. | Structural work filed for anchoring shelving only as shown on drawings submitted herewith, No change in use. egress or occupancy. |
| Name | Projects together | Most recent |
|---|---|---|
| Eclipse Engineering | 1 | 08/11/2023 |
| Sal Fateen Engineering | 1 | 06/13/2024 |
| T & Z Consulting Services | 1 | 07/24/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| Bound Construction | 2 | 07/24/2024 |
| Opc Management | 1 | 08/11/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| CBRE | 2 | 07/24/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| Jam Consultants | 2 | 07/24/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01043466 ↗ | 640 COLUMBIA STREET BROOKLYN | Alteration | Signed-off | 06/05/2024 | 06/18/2024 | Owner CBRE Contractor BOUND CONSTRUCTION CORP Filer JAM CONSULTANTS, INC. | Installation of new conveyor, spiral conveyors, crossover stair, induction & transport lanes, structural supports. The removal of segments o… |
| B01020292 ↗ | 640 COLUMBIA STREET BROOKLYN | Alteration | Signed-off | 06/13/2024 | 06/17/2024 | Design SAL FATEEN ENGINEERING Contractor BOUND CONSTRUCTION CORP | The removal/relocation of existing conveyors. The installation of new conveyors, compressor system, and safety fence as shown on plans submi… |
| B00914640 ↗ | 640 COLUMBIA STREET BROOKLYN | Alteration | Signed-off | 08/11/2023 | 08/31/2023 | Design ECLIPSE ENGINEERING Owner CBRE Contractor OPC MANAGEMENT INC Filer JAM CONSULTANTS, INC. | Structural work filed for anchoring shelving only as shown on drawings submitted herewith, No change in use. egress or occupancy. |
| Building | Filings | Most Recent |
|---|---|---|
| 640 COLUMBIA STREET ↗ | 3 | 07/24/2024 |