| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01001566 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 02/20/2024 | 08/06/2026 | Design HC PEC Contractor PJP INSTALLERS INC | INSTALLATION OF SIDEWAL SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01306539 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 10/24/2025 | 10/27/2025 | Design HC PEC Contractor PJP INSTALLERS INC | INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01306628 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 10/24/2025 | 10/27/2025 | Contractor PJP INSTALLERS INC | Installation of debris chute submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy wit… |
| M01306632 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 10/24/2025 | 10/27/2025 | Design HC PEC Contractor PJP INSTALLERS INC | Installation of temporary ground protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egr… |
| M01201656 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Signed-off | 05/01/2025 | 06/06/2025 | Design NORFAST ENGINEERING PLLC Contractor NICHOLSON & GALLOWAY, INC. | Remove brick facade and replace with slate rainscreen. No change to structural system |
| M00724359 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Signed-off | 04/25/2022 | 04/06/2023 | Contractor TISHMAN INTERIORS CORP Filer MBE CODE & ZONING LLC | FILING HEREWITH OCCUPANT PROTECTION PLANS FOR TEMPORARY CORRIDOR ENCLOSURE IN CONJUCTION WITH NB#121204017 & EGRESS #121188286 |
| Name | Projects together | Most recent |
|---|---|---|
| HC PEC | 3 | 10/24/2025 |
| ALTIERISEBORWIEBER LLC | 1 | 11/05/2020 |
| DSENY ENGINEERING SERVICES, PC | 1 | 06/28/2021 |
| GREEN RIVER ENVIRONMENTAL ENGINEERI | 1 | 04/25/2022 |
| NORFAST ENGINEERING PLLC | 1 | 05/01/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| PJP INSTALLERS INC | 4 | 10/24/2025 |
| LONG ISLAND CONCRETE INC | 1 | 06/28/2021 |
| NICHOLSON & GALLOWAY, INC | 1 | 05/01/2025 |
| RICHTER & RATNER CONTRACT | 1 | 11/05/2020 |
| TISHMAN INTERIORS CORP | 1 | 04/25/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| DSENY ENGINEERING SERVICES,PC | 1 | 06/28/2021 |
| MBE CODE & ZONING LLC | 1 | 04/25/2022 |
| NORFAST CONSULTING GROUP INC. | 1 | 05/01/2025 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01001566 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 02/20/2024 | 08/06/2026 | Design HC PEC Contractor PJP INSTALLERS INC | INSTALLATION OF SIDEWAL SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01306539 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 10/24/2025 | 10/27/2025 | Design HC PEC Contractor PJP INSTALLERS INC | INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01306628 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 10/24/2025 | 10/27/2025 | Contractor PJP INSTALLERS INC | Installation of debris chute submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy wit… |
| M01306632 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Permit Issued | 10/24/2025 | 10/27/2025 | Design HC PEC Contractor PJP INSTALLERS INC | Installation of temporary ground protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egr… |
| M01201656 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Signed-off | 05/01/2025 | 06/06/2025 | Design NORFAST ENGINEERING PLLC Contractor NICHOLSON & GALLOWAY, INC. | Remove brick facade and replace with slate rainscreen. No change to structural system |
| M00724359 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Signed-off | 04/25/2022 | 04/06/2023 | Contractor TISHMAN INTERIORS CORP Filer MBE CODE & ZONING LLC | FILING HEREWITH OCCUPANT PROTECTION PLANS FOR TEMPORARY CORRIDOR ENCLOSURE IN CONJUCTION WITH NB#121204017 & EGRESS #121188286 |
| M00489315 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Signed-off | 06/28/2021 | 02/16/2022 | Contractor LONG ISLAND CONCRETE INC | SF/GILDER CENTER - FOR TEMPORARY CONSTRUCTION EQUIPMENT (Scaffold)SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH DOB NUMBER 121204… |
| M00410603 ↗ | 200 CENTRAL PARK WEST MANHATTAN | Alteration | Signed-off | 11/05/2020 | 06/03/2021 | Design ALTIERISEBORWIEBER LLC Contractor RICHTER & RATNER CONTRACTING Filer MBE CODE & ZONING LLC | Install ductwork and units as shown on drawings filed herewith. No change in use, egress or occupancy. |
| Building | Filings | Most Recent |
|---|---|---|
| 200 CENTRAL PARK WEST ↗ | 7 | 10/24/2025 |
| 200 CENTRAL PARK WEST ↗ | 1 | 06/28/2021 |