| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01065582 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Permit Issued | 09/22/2025 | 08/27/2026 | Design AMA CONSULTING ENGINEERS, PC Contractor ABCO-PEERLESS SPRKLR CORP | Fit out of the 44th floor complete with new plumbing and piping distribution |
| M01065556 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Permit Issued | 09/24/2025 | 10/03/2025 | Design GENSLER Owner 30 ROCKEFELLER PLAZA Contractor JT MAGEN & COMPANY INC | INSTALLATION OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS FILED HERWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01065572 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 09/22/2025 | 10/03/2025 | Design AMA CONSULTING ENGINEERS, PC Contractor JT MAGEN & COMPANY INC | Fit out of the 44th floor to complete with new duct and piping distribution |
| M01027407 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration CO | Permit Issued | 05/30/2024 | 10/01/2025 | Design GENSLER Contractor JT MAGEN & COMPANY INC | INSTALLATION OF INTERIOR NON-BEARING PARITIONS AND RELATED FINSHES AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE. CHANGE IN OCCUPANCY: MA… |
| M01065557 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 08/28/2024 | 09/24/2025 | Design GENSLER Contractor JT MAGEN & COMPANY INC | INSTALLATION OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS FILED HERWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01065585 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 08/22/2024 | 09/23/2025 | Design AMA CONSULTING ENGINEERS, PC Owner RCPI Landmarks LLC Contractor LAB PLBG & HTG CO INC | Fit out of the 45th floor complete with new plumbing and piping distribution |
| Name | Projects together | Most recent |
|---|---|---|
| AMA CONSULTING ENGINEERS, PC | 4 | 10/01/2025 |
| GENSLER | 3 | 09/24/2025 |
| GILSANZ MURRAY STEFICEK LLP | 1 | 08/09/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| JT MAGEN & COMPANY INC | 6 | 09/24/2025 |
| ABCO-PEERLESS SPRKLR CORP | 2 | 10/01/2025 |
| LAB PLBG & HTG CO INC | 2 | 10/01/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| 30 ROCKEFELLER PLAZA | 2 | 09/24/2025 |
| RCPI Landmarks LLC | 1 | 10/01/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| A1 EXPEDITING SERVICE CORP. | 3 | 10/01/2025 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01065582 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Permit Issued | 09/22/2025 | 08/27/2026 | Design AMA CONSULTING ENGINEERS, PC Contractor ABCO-PEERLESS SPRKLR CORP | Fit out of the 44th floor complete with new plumbing and piping distribution |
| M01065556 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Permit Issued | 09/24/2025 | 10/03/2025 | Design GENSLER Owner 30 ROCKEFELLER PLAZA Contractor JT MAGEN & COMPANY INC | INSTALLATION OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS FILED HERWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01065572 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 09/22/2025 | 10/03/2025 | Design AMA CONSULTING ENGINEERS, PC Contractor JT MAGEN & COMPANY INC | Fit out of the 44th floor to complete with new duct and piping distribution |
| M01027407 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration CO | Permit Issued | 05/30/2024 | 10/01/2025 | Design GENSLER Contractor JT MAGEN & COMPANY INC | INSTALLATION OF INTERIOR NON-BEARING PARITIONS AND RELATED FINSHES AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE. CHANGE IN OCCUPANCY: MA… |
| M01065557 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 08/28/2024 | 09/24/2025 | Design GENSLER Contractor JT MAGEN & COMPANY INC | INSTALLATION OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS FILED HERWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01065585 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 08/22/2024 | 09/23/2025 | Design AMA CONSULTING ENGINEERS, PC Owner RCPI Landmarks LLC Contractor LAB PLBG & HTG CO INC | Fit out of the 45th floor complete with new plumbing and piping distribution |
| M01065562 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 08/09/2024 | 08/07/2025 | Design GILSANZ MURRAY STEFICEK LLP Owner 30 ROCKEFELLER PLAZA Contractor JT MAGEN & COMPANY INC | Structural modifications to existing convenience stair opening, replacement of existing convenience stair, and miscellaneous steel for suppo… |
| M01065565 ↗ | 1250 AVENUE OF THE AMER MANHATTAN | Alteration | Signed-off | 08/22/2024 | 08/26/2024 | Design AMA CONSULTING ENGINEERS, PC Contractor JT MAGEN & COMPANY INC | Fit out of the 45th floor to complete with new duct and piping distribution |
| Building | Filings | Most Recent |
|---|---|---|
| 1250 AVENUE OF THE AMER ↗ | 8 | 10/01/2025 |