| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01294861 | 81-02 35 AVENUE QUEENS | Alteration | Permit Issued | 10/08/2025 | 10/09/2025 | Design PAUL PERDEK, PROF. ENG. PLLC Contractor JUNO CONTRACTING | INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01267269 | 81-02 35 AVENUE QUEENS | Alteration | Permit Issued | 08/20/2025 | 08/20/2025 | Design PAUL PERDEK, PROF. ENG. PLLC Owner COMMUNITY CHURCH Contractor JUNO CONTRACTING Filer AE DESIGN SOLUTION INC. | INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01274509 | 81-02 35 AVENUE QUEENS | Alteration | Signed-off | 08/20/2025 | 08/20/2025 | Design KMA DESIGNS LLC Contractor KINGS GROUP NY CORP | INSTALLATION OF HEAVY DUTY SIDEWALK SHED. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION, ALL WORK TO COMPLY WITH CHAPTER 33 O… |
| Q01235734 | 81-02 35 AVENUE QUEENS | Alteration | Permit Issued | 07/28/2025 | 08/12/2025 | Owner COMMUNITY CHURCH Contractor JUNO CONTRACTING | Repairs to church bell tower, including replacement, resetting & repointing of parapet & masonry; replacement of flashing; servicing of beam… |
| Q00469955 | 81-02 35 AVENUE QUEENS | Alteration | Signed-off | 03/09/2021 | 03/16/2021 | Contractor AGEE HEATING SERVICE | CONSTRUCT NEW WALL IN SUB-CELLAR TO CREATE ONE HOUR FIRE RATED BOILER ROOM. |
| Name | Projects together | Most recent |
|---|---|---|
| Paul Perdek, Prof. Engineering | 2 | 10/08/2025 |
| Jonathan Raible Architect | 1 | 07/28/2025 |
| Kma Designs | 1 | 08/20/2025 |
| New York Engineering Associates | 1 | 03/09/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| Juno Contracting | 3 | 10/08/2025 |
| Agee Heating Service | 1 | 03/09/2021 |
| Kings Group NY | 1 | 08/20/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| Community Church | 2 | 08/20/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| AE Design Solution | 1 | 08/20/2025 |
| Agouti Construction Consulting | 1 | 07/28/2025 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01294861 | 81-02 35 AVENUE QUEENS | Alteration | Permit Issued | 10/08/2025 | 10/09/2025 | Design PAUL PERDEK, PROF. ENG. PLLC Contractor JUNO CONTRACTING | INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01267269 | 81-02 35 AVENUE QUEENS | Alteration | Permit Issued | 08/20/2025 | 08/20/2025 | Design PAUL PERDEK, PROF. ENG. PLLC Owner COMMUNITY CHURCH Contractor JUNO CONTRACTING Filer AE DESIGN SOLUTION INC. | INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01274509 | 81-02 35 AVENUE QUEENS | Alteration | Signed-off | 08/20/2025 | 08/20/2025 | Design KMA DESIGNS LLC Contractor KINGS GROUP NY CORP | INSTALLATION OF HEAVY DUTY SIDEWALK SHED. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION, ALL WORK TO COMPLY WITH CHAPTER 33 O… |
| Q01235734 | 81-02 35 AVENUE QUEENS | Alteration | Permit Issued | 07/28/2025 | 08/12/2025 | Owner COMMUNITY CHURCH Contractor JUNO CONTRACTING | Repairs to church bell tower, including replacement, resetting & repointing of parapet & masonry; replacement of flashing; servicing of beam… |
| Q00469955 | 81-02 35 AVENUE QUEENS | Alteration | Signed-off | 03/09/2021 | 03/16/2021 | Contractor AGEE HEATING SERVICE | CONSTRUCT NEW WALL IN SUB-CELLAR TO CREATE ONE HOUR FIRE RATED BOILER ROOM. |
| Building | Filings | Most Recent |
|---|---|---|
| 81-02 35 AVENUE ↗ | 5 | 10/08/2025 |