| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00575076 ↗ | 114 5 AVENUE MANHATTAN | Alteration | Signed-off | 10/14/2021 | 04/18/2022 | Design STUDIOS ARCHITECTURE Contractor JRM CONSTRUCTION MGMT LLC | Architectural modifications to take place on the 9th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| M00580053 ↗ | 114 5 AVENUE MANHATTAN | Alteration | Signed-off | 10/13/2021 | 04/18/2022 | Design ROBERT DERECTOR ASSOCIATES Contractor JRM CONSTRUCTION MGMT LLC Filer RIZZO GROUP | Mechanical modifications to take place on the 9th floor as per drawings filed herewith. no change in use, egress, or occupancy. |
| M00580023 ↗ | 114 5 AVENUE MANHATTAN | Alteration | Signed-off | 10/13/2021 | 11/12/2021 | Design ROBERT DERECTOR ASSOCIATES Contractor MANENGEERING BUREAU, INC Filer RIZZO GROUP | Sprinkler modifications to take place on the 9th floor as per drawings filed herewith. no change in use, egress, or occupancy. |
| Name | Projects together | Most recent |
|---|---|---|
| ROBERT DERECTOR ASSOCIATES | 2 | 03/23/2022 |
| STUDIOS ARCHITECTURE | 1 | 10/14/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| JRM CONSTRUCTION MGMT LLC | 2 | 10/14/2021 |
| ABCO PEERLESS SPRINKLER C | 1 | 03/23/2022 |
| PACE PLUMBING CORP | 1 | 03/23/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| RIZZO GROUP | 2 | 03/23/2022 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00575076 ↗ | 114 5 AVENUE MANHATTAN | Alteration | Signed-off | 10/14/2021 | 04/18/2022 | Design STUDIOS ARCHITECTURE Contractor JRM CONSTRUCTION MGMT LLC | Architectural modifications to take place on the 9th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| M00580053 ↗ | 114 5 AVENUE MANHATTAN | Alteration | Signed-off | 10/13/2021 | 04/18/2022 | Design ROBERT DERECTOR ASSOCIATES Contractor JRM CONSTRUCTION MGMT LLC Filer RIZZO GROUP | Mechanical modifications to take place on the 9th floor as per drawings filed herewith. no change in use, egress, or occupancy. |
| M00580023 ↗ | 114 5 AVENUE MANHATTAN | Alteration | Signed-off | 10/13/2021 | 11/12/2021 | Design ROBERT DERECTOR ASSOCIATES Contractor MANENGEERING BUREAU, INC Filer RIZZO GROUP | Sprinkler modifications to take place on the 9th floor as per drawings filed herewith. no change in use, egress, or occupancy. |
| Building | Filings | Most Recent |
|---|---|---|
| 114 5 AVENUE ↗ | 3 | 03/23/2022 |