| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01323961 | 1028 5TH AVENUE MANHATTAN | Alteration | Filed — no permit on record | 06/12/2026 | — | Owner MARYMOUNT SCHOOL OF NY Filer BOYD CONSULTING, INC | — |
| M01323803 | 1026 5TH AVENUE MANHATTAN | Alteration | Filed — no permit on record | 05/20/2026 | — | Owner MARYMOUNT SCHOOL OF NY Filer BOYD CONSULTING, INC | — |
| M01324033 | 1027 5TH AVENUE MANHATTAN | Alteration | Filed — no permit on record | 05/20/2026 | — | Owner MARYMOUNT SCHOOL OF NY Filer BOYD CONSULTING, INC | — |
| M01307139 | 1026 5TH AVENUE MANHATTAN | Alteration | Permit Issued | 11/13/2025 | 02/12/2026 | Design NEW AGE ENGINEERING PLLC Owner MARYMOUNT SCHOOL OF NY Contractor MC GOWAN BUILDERS INC Filer JM ZONING, LLC. | REPLACE HVAC ROOFTOP UNITS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. |
| M00513266 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 10/06/2021 | 06/28/2023 | Design PHILIP HABIB & ASSOCIATES Contractor TRITON CONSTRUCTION CO., Filer JM ZONING, LLC. | FILING HEREWITH CURB CUT AS PER PLANS N CONJUNCTION WITH NEW BUILDING. |
| M00868730 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 05/04/2023 | 06/01/2023 | Design COSENTINI ASSOCIATES Owner MARYMOUNT SCHOOL OF NY Contractor STUART N SCHWARTZ Filer JM ZONING, LLC. | REFILING OF APPROVED APPLICATION # M08040006 WITH CORRECT EQUIPMENT SCHEDULE. INSTALLATION OF FUEL STORAGE FOR GENERATOR IN CONJUNCTION WITH… |
| Name | Projects together | Most recent |
|---|---|---|
| Walter B. Melvin Architects | 3 | 06/12/2026 |
| Cosentini Associates | 2 | 07/19/2023 |
| Asif Jamil, RA | 1 | 07/15/2019 |
| Gga Studios | 1 | 05/19/2023 |
| KZ Engineering | 1 | 02/16/2022 |
| New Age Engineering | 1 | 02/06/2026 |
| Philip Habib & Associates | 1 | 10/06/2021 |
| Robert Germain Jr. PE | 1 | 05/03/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| Triton Construction Co | 2 | 05/19/2023 |
| Canido Basonas Construction | 1 | 07/15/2019 |
| CS Bridge | 1 | 02/16/2022 |
| Home Crafts | 1 | 05/03/2023 |
| MC Gowan Builders | 1 | 02/06/2026 |
| Stat Fire Sprinkler NYC | 1 | 07/19/2023 |
| Stuart N Schwartz | 1 | 05/04/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| Marymount School of New York | 5 | 07/19/2023 |
| Marymount School of NY | 5 | 06/12/2026 |
| Canido Basonas Construction | 1 | 07/15/2019 |
| Name | Projects together | Most recent |
|---|---|---|
| Boyd Consulting | 3 | 06/12/2026 |
| JM Zoning | 3 | 02/06/2026 |
| Domani Consulting | 1 | 05/19/2023 |
| Synergy Building Consultants | 1 | 02/16/2022 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01323961 | 1028 5TH AVENUE MANHATTAN | Alteration | Filed — no permit on record | 06/12/2026 | — | Owner MARYMOUNT SCHOOL OF NY Filer BOYD CONSULTING, INC | — |
| M01323803 | 1026 5TH AVENUE MANHATTAN | Alteration | Filed — no permit on record | 05/20/2026 | — | Owner MARYMOUNT SCHOOL OF NY Filer BOYD CONSULTING, INC | — |
| M01324033 | 1027 5TH AVENUE MANHATTAN | Alteration | Filed — no permit on record | 05/20/2026 | — | Owner MARYMOUNT SCHOOL OF NY Filer BOYD CONSULTING, INC | — |
| M01307139 | 1026 5TH AVENUE MANHATTAN | Alteration | Permit Issued | 11/13/2025 | 02/12/2026 | Design NEW AGE ENGINEERING PLLC Owner MARYMOUNT SCHOOL OF NY Contractor MC GOWAN BUILDERS INC Filer JM ZONING, LLC. | REPLACE HVAC ROOFTOP UNITS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. |
| M00513266 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 10/06/2021 | 06/28/2023 | Design PHILIP HABIB & ASSOCIATES Contractor TRITON CONSTRUCTION CO., Filer JM ZONING, LLC. | FILING HEREWITH CURB CUT AS PER PLANS N CONJUNCTION WITH NEW BUILDING. |
| M00868730 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 05/04/2023 | 06/01/2023 | Design COSENTINI ASSOCIATES Owner MARYMOUNT SCHOOL OF NY Contractor STUART N SCHWARTZ Filer JM ZONING, LLC. | REFILING OF APPROVED APPLICATION # M08040006 WITH CORRECT EQUIPMENT SCHEDULE. INSTALLATION OF FUEL STORAGE FOR GENERATOR IN CONJUNCTION WITH… |
| M00864923 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 05/04/2023 | 05/16/2023 | Design GGA STUDIOS, DPC Contractor TRITON CONSTRUCTION CO., Filer DOMANI CONSULTING | Alteration application filed herewith for interior temporary 2 hr. rated walls in conjunction with occupant protection plan for first TCO ph… |
| M00863331 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 05/03/2023 | 05/05/2023 | Design ROBERT GERMAIN JR. PE Contractor HOME CRAFTS | INSTALL (1) NEW GAS FIRED DIRECT VENT FIREPLACE ON GROUND FLOOR. ALL STRUCTUAL DETAILS SUPPORTS, GAS, ETC. FILED UNDER NB 12189864. NO CHA… |
| M00356663 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 11/12/2020 | 04/11/2023 | Design COSENTINI ASSOCIATES Contractor STAT FIRE SPRINKLER NYC C Filer JM ZONING, LLC. | FILING HEREWITH INSTALLATION OF NEW SPRINKLER & STANDPIPE SYSTEM IN CONJUNCTION WITH NB APPLICATION AS PER PLANS. |
| M00675455 | 115 EAST 97TH STREET MANHATTAN | Alteration | Signed-off | 02/16/2022 | 02/17/2022 | Design KZ ENGINEERING, P.C Contractor CS BRIDGE CORP | Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, eg… |
| M00193333 | 1026 5TH AVENUE MANHATTAN | Alteration | Permit Issued | 07/15/2019 | 08/01/2019 | Design ASIF JAMIL, RA Owner CANIDO BASONAS CONSTRUCTION CORP Contractor CANIDO BASONAS CONSTRUCTI | ERECT, MAINTAIN & DISMANTLE OF SCAFFOLD FOR FAADE REPAIRS AS PER DRAWINGS ATTACHED HEREWITH |
| Building | Filings | Most Recent |
|---|---|---|
| 1028 5TH AVENUE ↗ | 1 | 06/12/2026 |
| 1026 5TH AVENUE ↗ | 3 | 05/20/2026 |
| 1027 5TH AVENUE ↗ | 1 | 05/20/2026 |
| 115 EAST 97TH STREET ↗ | 6 | 07/19/2023 |