Back
Tenant
Miraj Islamic School
Tenant
2 projects with open permitsSTATEN ISLAND · 10
1 building
10
Total Filings
10
Projects on File
1
Buildings Worked
2
Projects w/ Open Permits
Tenant
Primary Trade
Activity
Projects by first filing month10 projects all-time
0123Mar '18 · 1May '20 · 1Aug '20 · 1Oct '20 · 2Aug '21 · 2May '24 · 1Aug '24 · 1Aug '26 · 120192020202120222023202420252026
bars = month · line = 3-mo average
Portfolio status
Browse projects →
Open permit220%
Signed off880%
By project type
Alteration10
Most active buildings
All buildings →
307 VICTORY BOULEVARDSTATEN ISLAND · 2 open · latest 10/13/2026
10 projects
Key relationships
Everyone →
Design firms
Filing representatives
Owners
4 projects
Most recent projects
All projects →
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
S01440206307 VICTORY BOULEVARD
STATEN ISLAND
AlterationPermit Issued08/10/202610/13/2026Replace (2) existing 15-ton gas/electric packaged rooftop units in kind with (2) new 15-ton units (R-454B, 220 MBH gas input each) in same l…
S01028615307 VICTORY BOULEVARD
STATEN ISLAND
AlterationPermit Issued08/29/202412/18/2025INSTALLATION OF FIRE SPRINKLER SYSTEM WITH VALVES AND METERS FOR SAME FOR NEW ADDITION ON EXISTING BUILDING.
S00890667307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off05/01/202406/18/2025Herewith filing for installation of HVAC system through out building.
S00566927307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off08/02/202105/04/2023
Owner SKYLINE SCAFFOLDING GROUP
INSTALLATION OF HEAVY DUTY SIDEWALK SHED DURING BLDG ALTERATION, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE …
S00567504307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off08/02/202105/04/2023
Owner SKYLINE SCAFFOLDING GROUP
INSTALLATION OF PLYWOOD FENCE AS PER DRAWINGS. PLYWOOD FENCE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS U…
S00313853307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off10/30/202010/01/2021
Owner AT&T
Installation of gas piping as per plans. No change to occupancy, use or egress.
Counts cover all 10 projects (10 DOB NOW). Dated by first filing; BIS projects by first permit issuance.
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
KMB Design Group309/01/2026
Joel Phagoo P.E208/02/2021
Azimuth Engineering105/18/2020
Marcy Engineering108/10/2026
Socotec106/11/2026
Tectonic Engineering103/19/2018
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Digital Construction Technologies208/31/2026
Skyline Scaffolding Group208/02/2021
Command Cooling108/10/2026
Dependable Mechanical108/29/2024
Dependable Mechanical108/29/2024
Overland Contracting105/18/2020
P.A.C. Heating109/01/2026
Sken Services106/11/2026
Wireless Network Group103/19/2018
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
AT&T409/01/2026
Skyline Scaffolding Group208/02/2021
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
A1 Expediting Service208/02/2021
Costa Architecture & Engineering106/11/2026
10 DOB NOW projects, anchored the same way as Buildings Worked. Status is the project's permit state today: open = at least one permit currently issued. BIS projects show their raw permit status and are not counted as open.
All 10Open permit 2Signed off 8
10 projects
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
S01440206307 VICTORY BOULEVARD
STATEN ISLAND
AlterationPermit Issued08/10/202610/13/2026Replace (2) existing 15-ton gas/electric packaged rooftop units in kind with (2) new 15-ton units (R-454B, 220 MBH gas input each) in same l…
S01028615307 VICTORY BOULEVARD
STATEN ISLAND
AlterationPermit Issued08/29/202412/18/2025INSTALLATION OF FIRE SPRINKLER SYSTEM WITH VALVES AND METERS FOR SAME FOR NEW ADDITION ON EXISTING BUILDING.
S00890667307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off05/01/202406/18/2025Herewith filing for installation of HVAC system through out building.
S00566927307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off08/02/202105/04/2023
Owner SKYLINE SCAFFOLDING GROUP
INSTALLATION OF HEAVY DUTY SIDEWALK SHED DURING BLDG ALTERATION, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE …
S00567504307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off08/02/202105/04/2023
Owner SKYLINE SCAFFOLDING GROUP
INSTALLATION OF PLYWOOD FENCE AS PER DRAWINGS. PLYWOOD FENCE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS U…
S00313853307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off10/30/202010/01/2021
Owner AT&T
Installation of gas piping as per plans. No change to occupancy, use or egress.
S00344156307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off05/18/202002/23/2021
Owner AT&T
AT&T - Replacement of antennas with installation/replacement of RRH units. Relocation of existing sector. Retrofit/installation of cabinet…
S00313901307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off08/28/202011/19/2020
Owner AT&T
Replacement of existing HVAC system with installation of new louvers and DAC in exisitng equipment shelter on grade. No change to occupancy…
S00313822307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off10/30/202011/18/2020
Owner AT&T
Installation of non-emergency gas fired generator with gas booster pump on roof. No change to occupancy, use, or egress.
S00021092307 VICTORY BOULEVARD
STATEN ISLAND
AlterationSigned-off03/19/201810/30/2018AT&T WIRELESS. Replacement of existing telecommunications antennas with replacement/installation of RRH units on roof. Retrofit of cabinets …
Click a row for this entity's own projects, plans and documents at that building.
BuildingFilingsMost Recent
307 VICTORY BOULEVARD ↗1009/01/2026
▾Documents — 82 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch9
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems4
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
▸DOB NOWPlans/Sketch - Antenna1
▸Seals & Professional Certifications51
▸DOB NOWProgress Inspector Seal & Signature22
10/04/2026S00313901-I1 · 307 VICTORY BOULEVARDOpen ↗
10/04/2026S00313901-I1 · 307 VICTORY BOULEVARDOpen ↗
10/04/2026S00313901-I1 · 307 VICTORY BOULEVARDOpen ↗
Showing 3 of 22 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature18
10/04/2026S00313853-P1 · 307 VICTORY BOULEVARDOpen ↗
10/04/2026S00313822-P1 · 307 VICTORY BOULEVARDOpen ↗
10/04/2026S00313901-P1 · 307 VICTORY BOULEVARDOpen ↗
Showing 3 of 18 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
10/04/2026S00313822-P1 · 307 VICTORY BOULEVARDOpen ↗
10/04/2026S00313901-I1 · 307 VICTORY BOULEVARDOpen ↗
10/04/2026S00313901-I1 · 307 VICTORY BOULEVARDOpen ↗
Showing 3 of 11 on file for this type
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/26/2026S00021092-I1 · 307 VICTORY BOULEVARDOpen ↗
08/26/2026S00313901-P1 · 307 VICTORY BOULEVARDOpen ↗
08/25/2026S00313853-P1 · 307 VICTORY BOULEVARDOpen ↗
Showing 3 of 8 on file for this type
▸Approvals, Objections & Sign-offs7
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/16/2026S01440206-I1 · 307 VICTORY BOULEVARDOpen ↗
08/13/2026S00566927-I1 · 307 VICTORY BOULEVARDOpen ↗
08/13/2026S00567504-I1 · 307 VICTORY BOULEVARDOpen ↗
Showing 3 of 7 on file for this type