| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01450162 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 08/27/2026 | 09/01/2026 | Contractor NEW YORK DESIGN & CONST | CONSTRUCT INTERIOR NON LOAD BEARING PARTITIONS ON THE 2ND, 3RD AND 4TH FLOORS. NO CHANGE IN OCCUPANCY, USE OR EGRESS. |
| M01389746 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 05/18/2026 | 08/27/2026 | Design S.M. BERGER ARCHITECTURE PC Owner NEW MUSEUM Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | Construct Interior non load bearing partitions for fit out of new offices on the B1 (Cellar Mezz) and F5 levels (5th fl.) per plans filed.… |
| M00223256 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 10/29/2019 | 08/26/2026 | Design OVE ARUP & PARTNERS PC Owner NEW MUSEUM Contractor SCIAME CONSTRUCTION LLC Filer RPO INC. | STRUCTURAL REINFORCEMENT INCONJUNCTION WITH PROPOSED 7 STORY ENLARGEMENT TO EXISTING 8 STORY BUILDING FILED UNDER ALT I APPLICATION 12120511… |
| M08048035 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 12/05/2022 | 06/09/2026 | Contractor MC SUPERSTRUCTURE INC | INSTALLATION OF 300 PSF SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CH… |
| M08040215 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 11/21/2022 | 05/12/2026 | Contractor MC SUPERSTRUCTURE INC | INSTALLATION OF PYLWOOD FENCE AS PER PLANS. PLYWOOD FENCE SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE NO CHANGE IN USE, EGRESS OR OCCUPAN… |
| M01294455 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 11/13/2025 | 04/08/2026 | Design SIMPSON GUMPERTZ & HEGER Contractor DUN-RITE SPECIALIZED CARR Filer JAM CONSULTANTS, INC. | Fabrication of the 4th floor armature and 3rd floor support per plans filed herewith. No change to use, egress or occupancy. |
| Name | Projects together | Most recent |
|---|---|---|
| S.M. Berger Architecture | 10 | 05/18/2026 |
| Ove Arup & Partners | 6 | 05/06/2026 |
| Black Sheep Engineering Group | 2 | 10/20/2025 |
| FL&M Engineering Design & Inspection | 2 | 12/05/2022 |
| Crimson Engineering | 1 | 10/20/2025 |
| IW Architecture | 1 | 03/10/2026 |
| Levin Engineering | 1 | 07/08/2024 |
| MRA Engineering | 1 | 10/22/2025 |
| PCS Engineering | 1 | 10/29/2025 |
| Sandeep Gunnala Engineering | 1 | 02/10/2026 |
| Simpson Gumpertz & Heger | 1 | 11/13/2025 |
| Valjato Engineering | 1 | 09/17/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| New York Design & Construction | 11 | 08/27/2026 |
| Sciame Construction | 5 | 05/06/2026 |
| CS Bridge | 2 | 10/20/2025 |
| MC Superstructure | 2 | 12/05/2022 |
| Real Plumbing | 2 | 08/26/2025 |
| Tri Borough Scaffolding | 2 | 12/05/2022 |
| Champion Combustion | 1 | 01/22/2026 |
| Dun-Rite Specialized Carr | 1 | 11/13/2025 |
| East Coast Facades | 1 | 10/29/2025 |
| L.S. Sign Co | 1 | 03/10/2026 |
| Par Plumbing Co | 1 | 12/15/2025 |
| Peak Fire Protection | 1 | 08/26/2025 |
| Pro Star Plumbing, Heating & Mechanical | 1 | 06/26/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| New Museum | 18 | 05/18/2026 |
| New Museum of Contemporary Art | 2 | 02/03/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| Jam Consultants | 11 | 05/18/2026 |
| Levin Engineering | 1 | 07/08/2024 |
| Louis Striar | 1 | 03/10/2026 |
| MRA Engineering | 1 | 10/22/2025 |
| Rpo | 1 | 05/06/2026 |
| Rigging Consultants | 1 | 10/29/2025 |
| Sandeep Gunnala Engineering | 1 | 02/10/2026 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01450162 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 08/27/2026 | 09/01/2026 | Contractor NEW YORK DESIGN & CONST | CONSTRUCT INTERIOR NON LOAD BEARING PARTITIONS ON THE 2ND, 3RD AND 4TH FLOORS. NO CHANGE IN OCCUPANCY, USE OR EGRESS. |
| M01389746 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 05/18/2026 | 08/27/2026 | Design S.M. BERGER ARCHITECTURE PC Owner NEW MUSEUM Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | Construct Interior non load bearing partitions for fit out of new offices on the B1 (Cellar Mezz) and F5 levels (5th fl.) per plans filed.… |
| M00223256 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 10/29/2019 | 08/26/2026 | Design OVE ARUP & PARTNERS PC Owner NEW MUSEUM Contractor SCIAME CONSTRUCTION LLC Filer RPO INC. | STRUCTURAL REINFORCEMENT INCONJUNCTION WITH PROPOSED 7 STORY ENLARGEMENT TO EXISTING 8 STORY BUILDING FILED UNDER ALT I APPLICATION 12120511… |
| M08048035 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 12/05/2022 | 06/09/2026 | Contractor MC SUPERSTRUCTURE INC | INSTALLATION OF 300 PSF SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CH… |
| M08040215 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 11/21/2022 | 05/12/2026 | Contractor MC SUPERSTRUCTURE INC | INSTALLATION OF PYLWOOD FENCE AS PER PLANS. PLYWOOD FENCE SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE NO CHANGE IN USE, EGRESS OR OCCUPAN… |
| M01294455 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 11/13/2025 | 04/08/2026 | Design SIMPSON GUMPERTZ & HEGER Contractor DUN-RITE SPECIALIZED CARR Filer JAM CONSULTANTS, INC. | Fabrication of the 4th floor armature and 3rd floor support per plans filed herewith. No change to use, egress or occupancy. |
| M01366173 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 03/10/2026 | 03/13/2026 | Design IW ARCHITECTURE, PLLC Owner NEW MUSEUM Contractor WEINFELD, ELLIOT Filer LOUIS STRIAR INC. | ILLUMINATED NON-ADVERTISING ACCESSORY SIGN - IN PROPERTY LINES - NEW MUSEUM. NO CHANGE OF USE, EGRESS OR OCCUPANCY. |
| M00643694 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 04/27/2022 | 03/04/2026 | Design OVE ARUP & PARTNERS PC Owner NEW MUSEUM Contractor CHAMPION COMBUSTION CORP Filer JAM CONSULTANTS, INC. | Installation of Rooftop day tank per plans filed. |
| M01343939 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 01/28/2026 | 02/02/2026 | Design S.M. BERGER ARCHITECTURE PC Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | Construction of New Walls and built-in Millwork per plans filed herewith . No change to use, egress or occupancy. |
| M01114457 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 10/25/2024 | 12/16/2025 | Owner NEW MUSEUM Contractor SCIAME CONSTRUCTION LLC | NEW FIRE RATED DOOR OPENINGS AT MULTIPLE FLOORS |
| M00229396 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 10/30/2019 | 10/29/2025 | Design OVE ARUP & PARTNERS PC Owner NEW MUSEUM Contractor PAR PLUMBING CO., INC Filer JAM CONSULTANTS, INC. | MODIFICATION TO EXISTING PLUMBING AND GAS FIXTURES RELATED TO BASE BUILDING. |
| M00643685 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 06/26/2024 | 10/24/2025 | Design OVE ARUP & PARTNERS PC Owner NEW MUSEUM Contractor PRO STAR PLBG,HTG&MECH IN Filer JAM CONSULTANTS, INC. | INSTALLATION OF NEW BOILERS IN CONJUNCTION WITH MAJOR ALTERATION. |
| M01306354 ↗ | 231 BOWERY MANHATTAN | Alteration | Permit Issued | 10/22/2025 | 10/23/2025 | Design MRA ENGINEERING P.C. Owner NEW MUSEUM Contractor SCIAME CONSTRUCTION LLC Filer MRA ENGINEERING P.C. | MINI CRANE USED TO HOIST/SET INTERIOR GLASS PANELS |
| M01287442 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 09/17/2025 | 09/22/2025 | Design VALJATO ENGINEERING PC Contractor SCIAME CONSTRUCTION LLC | INSTALLATION OF SPYDER CRANE. THIS APPLICATION INVOLVES NO CHANGE IN USE, OCCUPANCY OR EGRESS. |
| M01075375 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 07/08/2024 | 08/15/2025 | Design LEVIN ENGINEERING PLLC Owner NEW MUSEUM Contractor MEGA PLBG CORP Filer LEVIN ENGINEERING PLLC | INSTALLATION OF NEW TEMPORARY STANDPIPE SYSTEM FOR ENTIRE BUILDING IN CONJUNCTION WITH APPLICATION # M00229467. NO CHANGE IN USE, EGRESS OR … |
| M01265107 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 08/04/2025 | 08/04/2025 | Owner NEW MUSEUM Contractor CS BRIDGE CORP | Installation of temporary scaffold in the elevator shaft per plan submitted. Work shall comply with 2022 building codes chapter 33. No chang… |
| M01226492 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 06/23/2025 | 06/24/2025 | Design PCS ENGINEERING Owner NEW MUSEUM Contractor EAST COAST FACADES | SUSPENDED SCAFFOLD FOR FACADE RESTORATION AS SHOWN ON PLANS |
| M00229006 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 12/12/2019 | 05/20/2025 | Design OVE ARUP & PARTNERS PC Owner NEW MUSEUM Contractor SCIAME CONSTRUCTION LLC Filer RPO INC. | NEW WORK AND MODIFICATION TO EXISTING HVAC, UNITS, DUCTWORK AND ALL ASSOCIATED PIPING FILED INCONJUNCTION WITH ALT I # 121205114. |
| M01220570 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 05/05/2025 | 05/06/2025 | Owner NEW MUSEUM Contractor CS BRIDGE CORP | Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, eg… |
| M00229467 ↗ | 235 BOWERY MANHATTAN | Alteration | Permit Issued | 12/11/2019 | 05/01/2025 | Design OVE ARUP & PARTNERS PC Contractor REAL PLUMBING CORP | INSTALLATION OF NEW STANDPIPE SYSTEM RELATED TO ALTERATION PER PLANS FILED. |
| M00924289 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 08/24/2023 | 08/28/2023 | Design S.M. BERGER ARCHITECTURE PC Owner NEW MUSEUM Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | Removal and installation of non-load bearing partitions and installation of minor partitions on the 1, 2, 3, & 4 floors. |
| M00875227 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 05/23/2023 | 05/24/2023 | Design S.M. BERGER ARCHITECTURE PC Owner NEW MUSEUM Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | Removal and installation of non-load bearing partitions and installation of minor partitions on the 1, 2, 3, & 4 floors. |
| M00822829 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 02/06/2023 | 02/08/2023 | Design S.M. BERGER ARCHITECTURE PC Contractor NEW YORK DESIGN & CONST | Removal of non-load bearing partitions and installation of minor partitions on 2nd and 3rd floors. |
| M08006792 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 09/27/2022 | 09/29/2022 | Design S.M. BERGER ARCHITECTURE PC Contractor NEW YORK DESIGN & CONST | Removal of non-load bearing partitions and installation of minor partitions on 2nd and 3rd floors. |
| M00728477 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 05/19/2022 | 05/24/2022 | Design S.M. BERGER ARCHITECTURE PC Owner NEW MUSEUM Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | Removal of non-load bearing partitions on the 3rd floor. Minor partition work on floors 1, 2, & 3. |
| M00649190 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 12/17/2021 | 02/28/2022 | Design S.M. BERGER ARCHITECTURE PC Owner NEW MUSEUM Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | HEREWITH FILING APPLICATION FOR THE CONSTRUCTION OF NON LOAD-BEARING INTERIOR PARTITIONS. NO CHANGE TO USE,EGRESS OR OCCUPANCY, |
| M00592900 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 09/17/2021 | 09/20/2021 | Design S.M. BERGER ARCHITECTURE PC Owner NEW MUSEUM Contractor NEW YORK DESIGN & CONST Filer JAM CONSULTANTS, INC. | Removal of existing partitions on the2nd and 3rd floors. Minor partition work on floors 1, 2 & 3. |
| M00525135 ↗ | 235 BOWERY MANHATTAN | Alteration | Signed-off | 05/20/2021 | 07/06/2021 | Design S.M. BERGER ARCHITECTURE PC Contractor NEW YORK DESIGN & CONST | Removal of existing partitions on 3rd floor. Minor partition work on floors 1 through 3 and 5. |
| Building | Filings | Most Recent |
|---|---|---|
| 235 BOWERY ↗ | 27 | 08/27/2026 |
| 231 BOWERY ↗ | 1 | 10/22/2025 |