| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00947267 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 05/28/2025 | 05/29/2025 | Design LEVIN ENGINEERING PLLC Owner QUEENS BALLPARK COMPANY Contractor SIRINA FIRE PROT CORP | MODIFICATION OF AN EXISTING SPRINKLER SYSTEM ON THE 2ND FLOOR - PLAYER'S FAMILY ROOM AREA AT CITIFIELD STADIUM AS PER PLANS SUBMITTED, NO CH… |
| Q01167886 ↗ | 41 SEAVER WAY QUEENS | Alteration | Permit Issued | 02/02/2025 | 02/07/2025 | Design LANGAN ENGINEERING Contractor TURNER CONSTRUCTION COMPANY | FILING HEREWITH INSTALLATION OF PRE-CONSTRUCTION TEST PILES AND TEST PITS WITH SITE RESTORATION AS PER PLANS. NO CHANGE IN USE, EGRESS OR O… |
| Q00913982 ↗ | 41 SEAVER WAY QUEENS | Alteration | Permit Issued | 08/17/2023 | 09/18/2023 | Design SHOP ARCHITECTS Owner QUEENS BALLPARK COMPANY Contractor HUNTER ROBERTS CONSTRUCTION | Interior renovation as per plans filed herewith. |
| Q00871158 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 05/08/2023 | 05/10/2023 | Design LEVIN ENGINEERING PLLC Owner QUEENS BALLPARK COMPANY Contractor SIRINA FIRE PROT CORP | MODIFICATION OF AN EXISTING SPRINKLER SYSTEM ON THE 1ST FLOOR AT THE ROTUNDA TICKET OFFICE AS PER PLANS SUBMITTED HEREWITH, NO CHANGE IN USE… |
| Q00676299 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 04/07/2022 | 04/21/2023 | Design ME ENGINEERS Owner QUEENS BALLPARK COMPANY Contractor REBOSIO CONSTRUCTION SVC | Modification to Mechanical systems as per plans filed herewith. No Change in use occupancy or egress. |
| Q08004395 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 11/15/2022 | 02/09/2023 | Design THORNTON TOMASETTI Owner QUEENS BALLPARK COMPANY Contractor SHAWMUT WOODWORKING & SUPPLY | Steel modifications to sign structures (score board) |
| Name | Projects together | Most recent |
|---|---|---|
| Levin Engineering | 3 | 05/28/2025 |
| Gensler | 1 | 11/04/2022 |
| Langan Engineering | 1 | 02/02/2025 |
| Me Engineers | 1 | 04/07/2022 |
| Populous | 1 | 11/17/2022 |
| Shop Architects | 1 | 08/17/2023 |
| Thornton Tomasetti | 1 | 11/15/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| Sirina Fire Protection | 3 | 05/28/2025 |
| Rebosio Construction Service | 2 | 11/04/2022 |
| Samsung Electronics Ameri | 2 | 11/17/2022 |
| Shawmut Woodworking & Sup | 2 | 11/15/2022 |
| Hunter Roberts Construction | 1 | 08/17/2023 |
| Turner Construction Company | 1 | 02/02/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| Queens Ballpark Company | 6 | 05/28/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| A1 Expediting Service | 4 | 08/17/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00947267 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 05/28/2025 | 05/29/2025 | Design LEVIN ENGINEERING PLLC Owner QUEENS BALLPARK COMPANY Contractor SIRINA FIRE PROT CORP | MODIFICATION OF AN EXISTING SPRINKLER SYSTEM ON THE 2ND FLOOR - PLAYER'S FAMILY ROOM AREA AT CITIFIELD STADIUM AS PER PLANS SUBMITTED, NO CH… |
| Q01167886 ↗ | 41 SEAVER WAY QUEENS | Alteration | Permit Issued | 02/02/2025 | 02/07/2025 | Design LANGAN ENGINEERING Contractor TURNER CONSTRUCTION COMPANY | FILING HEREWITH INSTALLATION OF PRE-CONSTRUCTION TEST PILES AND TEST PITS WITH SITE RESTORATION AS PER PLANS. NO CHANGE IN USE, EGRESS OR O… |
| Q00913982 ↗ | 41 SEAVER WAY QUEENS | Alteration | Permit Issued | 08/17/2023 | 09/18/2023 | Design SHOP ARCHITECTS Owner QUEENS BALLPARK COMPANY Contractor HUNTER ROBERTS CONSTRUCTION | Interior renovation as per plans filed herewith. |
| Q00871158 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 05/08/2023 | 05/10/2023 | Design LEVIN ENGINEERING PLLC Owner QUEENS BALLPARK COMPANY Contractor SIRINA FIRE PROT CORP | MODIFICATION OF AN EXISTING SPRINKLER SYSTEM ON THE 1ST FLOOR AT THE ROTUNDA TICKET OFFICE AS PER PLANS SUBMITTED HEREWITH, NO CHANGE IN USE… |
| Q00676299 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 04/07/2022 | 04/21/2023 | Design ME ENGINEERS Owner QUEENS BALLPARK COMPANY Contractor REBOSIO CONSTRUCTION SVC | Modification to Mechanical systems as per plans filed herewith. No Change in use occupancy or egress. |
| Q08004395 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 11/15/2022 | 02/09/2023 | Design THORNTON TOMASETTI Owner QUEENS BALLPARK COMPANY Contractor SHAWMUT WOODWORKING & SUPPLY | Steel modifications to sign structures (score board) |
| Q08025759 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 11/04/2022 | 12/08/2022 | Design GENSLER Owner QUEENS BALLPARK COMPANY Contractor REBOSIO CONSTRUCTION SVC | Removal and Installation of non-bearing interior and exterior non-bearing partitions as per plans. NO CHANGE OF USE, EGRESS, OR OCCUPANCY. … |
| Q08020393 ↗ | 41 SEAVER WAY QUEENS | Alteration | Signed-off | 11/17/2022 | 11/29/2022 | Design POPULOUS, INC. Contractor SAMSUNG ELECTRONICS AMERI | New and expanded extent of catwalks, ships ladder, modified guard rails, removal and modifications to existing fixed ad panels filed in conj… |
| Q00754256 ↗ | 41 SEAVER WAY QUEENS | Alteration | Permit Issued | 08/27/2022 | 08/29/2022 | Design LEVIN ENGINEERING PLLC Contractor SIRINA FIRE PROT CORP | MODIFICATION OF AN EXISTING SPRINKLER SYSTEM ON THE 3RD FLOOR AT THE CITI FIELD STADIUM AS PER PLANS SUBMITTED HEREWITH, NO CHANGE IN USE, E… |
| Building | Filings | Most Recent |
|---|---|---|
| 41 SEAVER WAY ↗ | 9 | 05/28/2025 |