| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01204077 ↗ | 171 VARICK STREET MANHATTAN | Alteration CO | Permit Issued | 06/05/2025 | 07/21/2025 | Owner TISHMAN SPEYER Contractor STRUCTURE TONE, LLC Filer BROOKBRIDGE CONSULTING | Architectural work for new Place of Assembly on 5th and 6th floors. |
| M01204085 ↗ | 171 VARICK STREET MANHATTAN | No Work | Filed — no permit on record | 06/02/2025 | — | — | |
| M01166667 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 04/02/2025 | 04/04/2025 | Design STUDIO HUJI Contractor SIGNS CAD CORP | INSTALL AN ILLUMINATED WALL SIGN A @VARICK STREET ELEVATION |
| M01166674 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 04/02/2025 | 04/04/2025 | Design STUDIO HUJI Owner TISHMAN SPEYER Contractor SIGNS CAD CORP Filer SIGNS CAD CORP | INSTALL AN ILLUMINATED WALL SIGN B @CHARLTON STREET ELEVATION |
| M01083565 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 08/16/2024 | 03/10/2025 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Contractor A&A PLUMBING CORP Filer RIZZO GROUP | Installation of new plumbing fixtures and associated piping on the 5th and 6th floors (ROKT) as per plans. No change to use, egress or occup… |
| M01083569 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Permit Issued | 08/16/2024 | 03/04/2025 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Contractor CAPITOL FIRE SPRINKLER CO Filer RIZZO GROUP | Modifications to the existing sprinkler system on the 5th and 6th floors (ROKT) as per plans. No change to use, egress or occupancy. |
| Name | Projects together | Most recent |
|---|---|---|
| AMA CONSULTING ENGINEERS, PC | 5 | 01/14/2026 |
| MARCO GIARDINA ARCHITECTURE, PLLC | 3 | 12/15/2025 |
| STUDIO HUJI | 2 | 04/02/2025 |
| THE EIPEL ENGINEERING GROUP, D.P.C. | 1 | 11/23/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| STRUCTURE TONE, LLC | 3 | 01/08/2026 |
| SIGNS CAD CORP | 2 | 04/02/2025 |
| A & M WARSHAW PLBG & HTG | 1 | 02/21/2023 |
| A&A PLUMBING CORP | 1 | 04/15/2025 |
| BUILDOPS INC | 1 | 11/23/2021 |
| CAPITOL FIRE SPRINKLER CO | 1 | 01/14/2026 |
| CM PLUMBING INC | 1 | 02/21/2023 |
| V. BARILE, INC | 1 | 09/05/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| TISHMAN SPEYER | 9 | 01/14/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| RIZZO GROUP | 5 | 01/14/2026 |
| BROOKBRIDGE CONSULTING | 2 | 12/15/2025 |
| SIGNS CAD CORP | 1 | 04/02/2025 |
| WALTER T. GORMAN, PE, PC | 1 | 11/23/2021 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01204077 ↗ | 171 VARICK STREET MANHATTAN | Alteration CO | Permit Issued | 06/05/2025 | 07/21/2025 | Owner TISHMAN SPEYER Contractor STRUCTURE TONE, LLC Filer BROOKBRIDGE CONSULTING | Architectural work for new Place of Assembly on 5th and 6th floors. |
| M01204085 ↗ | 171 VARICK STREET MANHATTAN | No Work | Filed — no permit on record | 06/02/2025 | — | — | |
| M01166667 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 04/02/2025 | 04/04/2025 | Design STUDIO HUJI Contractor SIGNS CAD CORP | INSTALL AN ILLUMINATED WALL SIGN A @VARICK STREET ELEVATION |
| M01166674 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 04/02/2025 | 04/04/2025 | Design STUDIO HUJI Owner TISHMAN SPEYER Contractor SIGNS CAD CORP Filer SIGNS CAD CORP | INSTALL AN ILLUMINATED WALL SIGN B @CHARLTON STREET ELEVATION |
| M01083565 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 08/16/2024 | 03/10/2025 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Contractor A&A PLUMBING CORP Filer RIZZO GROUP | Installation of new plumbing fixtures and associated piping on the 5th and 6th floors (ROKT) as per plans. No change to use, egress or occup… |
| M01083569 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Permit Issued | 08/16/2024 | 03/04/2025 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Contractor CAPITOL FIRE SPRINKLER CO Filer RIZZO GROUP | Modifications to the existing sprinkler system on the 5th and 6th floors (ROKT) as per plans. No change to use, egress or occupancy. |
| M01083562 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Permit Issued | 08/15/2024 | 02/26/2025 | Owner TISHMAN SPEYER Contractor STRUCTURE TONE, LLC Filer RIZZO GROUP | Installation of new partitions, doors, suspended ceilings and finishes on the 5th and 6th floors (ROKT) as per plans. No change to use, egre… |
| M01083564 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Permit Issued | 08/20/2024 | 02/26/2025 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Contractor STRUCTURE TONE, LLC Filer RIZZO GROUP | Modifications to the existing HVAC system on the 5th, 6th and roof floors (ROKT) as per plans. No change to use, egress or occupancy. |
| M00822730 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 02/21/2023 | 04/04/2023 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Contractor A & M WARSHAW PLBG & HTG Filer RIZZO GROUP | Install (1) CM, (1) DW, (5) sinks, (8) WCs, (8) Lavs, (3) FD and associated CW/sanitary piping on 7 & 8th Floors; Install (3) HWH on the 7th… |
| M00822786 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Permit Issued | 02/21/2023 | 03/31/2023 | Design AMA CONSULTING ENGINEERS, PC Owner TISHMAN SPEYER Contractor A&M WARSHAW SERVICES LLC Filer BROOKBRIDGE CONSULTING | Modifications to existing Sprinkler System: Install (154) new SP heads, Removal ( 152 ) on the 7th Floor and Install (125) new SP, Removal (… |
| M00607996 ↗ | 171 VARICK STREET MANHATTAN | Alteration | Signed-off | 11/23/2021 | 07/19/2022 | Owner TISHMAN SPEYER Contractor BUILDOPS INC Filer WALTER T. GORMAN, PE, PC | Structural work on roof and roof deck as per plans. No change to use, egress or occupancy. |
| Building | Filings | Most Recent |
|---|---|---|
| 171 VARICK STREET ↗ | 11 | 01/14/2026 |