| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M08031432 ↗ | 114 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/23/2022 | 12/05/2022 | Design MG ENGINEERING D.P.C. Contractor PREFERRED SPKLR AND MECH | Sprinkler modifications to take place on the 11th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| M08031428 ↗ | 114 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/23/2022 | 11/29/2022 | Design MG ENGINEERING D.P.C. Contractor UNITY CONSTRUCTION GROUP Filer RIZZO GROUP | Mechanical modifications to take place on the 11th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| M08031425 ↗ | 114 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/21/2022 | 11/28/2022 | Contractor UNITY CONSTRUCTION GROUP Filer RIZZO GROUP | General Construction to take place on the 11th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| Name | Projects together | Most recent |
|---|---|---|
| MG Engineering | 2 | 11/23/2022 |
| Spectorgroup Architecture | 1 | 11/21/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| Unity Construction Group | 2 | 11/23/2022 |
| Preferred Sprinkler and Mechanical | 1 | 11/23/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| Rizzo Group | 2 | 11/23/2022 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M08031432 ↗ | 114 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/23/2022 | 12/05/2022 | Design MG ENGINEERING D.P.C. Contractor PREFERRED SPKLR AND MECH | Sprinkler modifications to take place on the 11th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| M08031428 ↗ | 114 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/23/2022 | 11/29/2022 | Design MG ENGINEERING D.P.C. Contractor UNITY CONSTRUCTION GROUP Filer RIZZO GROUP | Mechanical modifications to take place on the 11th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| M08031425 ↗ | 114 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/21/2022 | 11/28/2022 | Contractor UNITY CONSTRUCTION GROUP Filer RIZZO GROUP | General Construction to take place on the 11th floor as per drawings filed herewith. No change in use, egress, or occupancy. |
| Building | Filings | Most Recent |
|---|---|---|
| 114 5TH AVENUE ↗ | 3 | 11/23/2022 |