| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01420111 | 22 EAST 93RD STREET MANHATTAN | Alteration CO | Filed — no permit on record | 09/15/2026 | — | Design CES ENGINEERING LLC | — |
| M00931188 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/15/2023 | 06/09/2025 | Contractor A. PETER LUGER CONST INC Filer BOYD CONSULTING, INC | Filing initial filing for facade, exterior and masonry repairs as per drawings. No change in use, egress or occupancy is involved under this… |
| M01010236 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 04/11/2024 | 04/03/2025 | Design RIGID STRUCTURAL DESIGN, LLC Contractor A. PETER LUGER CONST INC | INSTALLATION OF 259 LF HEAVY DUTY SIDEWALK SHED RATED FOR 300 PSF & 600 PSF MATERIAL & DEBRIS STORAGE AS PER PLANS. NO CHANGE TO EGRESS, USE… |
| M01010242 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 04/29/2024 | 04/03/2025 | Design RIGID STRUCTURAL DESIGN, LLC Contractor A. PETER LUGER CONST INC | Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use… |
| M01010247 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 04/11/2024 | 04/03/2025 | Design RIGID STRUCTURAL DESIGN, LLC Contractor A. PETER LUGER CONST INC | Installation of a temporarily Material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, eg… |
| M01020163 | 1109 5TH AVENUE MANHATTAN | Alteration CO | Permit Issued | 04/08/2024 | 01/21/2025 | Design ALTIERISEBORWIEBER LLC Contractor CONSIGLI CONSTRUCTION CO Filer JM ZONING, LLC. | Structural application filed related to Alteration CO M01020163-S1 application filed for the increase floor occupancy at the fourth floor. |
| Name | Projects together | Most recent |
|---|---|---|
| Rigid Structural Design | 3 | 04/29/2024 |
| Kohler Ronan | 2 | 08/27/2021 |
| M.arch Architects | 2 | 06/19/2020 |
| Altieriseborwieber | 1 | 01/14/2026 |
| CES Engineering | 1 | 09/15/2026 |
| Hope Dana | 1 | 09/15/2026 |
| Martos Engineering | 1 | 09/15/2026 |
| Method Design Architecture + Urbani | 1 | 01/14/2026 |
| Tohfaz Uddin PE | 1 | 12/03/2024 |
| TYLin | 1 | 01/14/2026 |
| Walter B. Melvin Architects | 1 | 07/17/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| West New York Restoration | 6 | 07/17/2025 |
| Consigli Construction Co | 1 | 01/14/2026 |
| Fresh Meadow Mechanical Plumbing | 1 | 08/27/2021 |
| Fresh Meadow Mechanical | 1 | 10/26/2019 |
| Magic Mechanical | 1 | 01/14/2026 |
| Parkview P&H | 1 | 01/14/2026 |
| Spring Scaffolding | 1 | 12/03/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| West New York Restoration of CT | 1 | 06/19/2020 |
| Name | Projects together | Most recent |
|---|---|---|
| Boyd Consulting | 1 | 07/17/2025 |
| J. Callahan Consulting | 1 | 09/15/2026 |
| JM Zoning | 1 | 01/14/2026 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01420111 | 22 EAST 93RD STREET MANHATTAN | Alteration CO | Filed — no permit on record | 09/15/2026 | — | Design CES ENGINEERING LLC | — |
| M00931188 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 11/15/2023 | 06/09/2025 | Contractor A. PETER LUGER CONST INC Filer BOYD CONSULTING, INC | Filing initial filing for facade, exterior and masonry repairs as per drawings. No change in use, egress or occupancy is involved under this… |
| M01010236 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 04/11/2024 | 04/03/2025 | Design RIGID STRUCTURAL DESIGN, LLC Contractor A. PETER LUGER CONST INC | INSTALLATION OF 259 LF HEAVY DUTY SIDEWALK SHED RATED FOR 300 PSF & 600 PSF MATERIAL & DEBRIS STORAGE AS PER PLANS. NO CHANGE TO EGRESS, USE… |
| M01010242 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 04/29/2024 | 04/03/2025 | Design RIGID STRUCTURAL DESIGN, LLC Contractor A. PETER LUGER CONST INC | Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use… |
| M01010247 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 04/11/2024 | 04/03/2025 | Design RIGID STRUCTURAL DESIGN, LLC Contractor A. PETER LUGER CONST INC | Installation of a temporarily Material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, eg… |
| M01020163 | 1109 5TH AVENUE MANHATTAN | Alteration CO | Permit Issued | 04/08/2024 | 01/21/2025 | Design ALTIERISEBORWIEBER LLC Contractor CONSIGLI CONSTRUCTION CO Filer JM ZONING, LLC. | Structural application filed related to Alteration CO M01020163-S1 application filed for the increase floor occupancy at the fourth floor. |
| M01149617 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 12/03/2024 | 12/03/2024 | Design TOHFAZ UDDIN PE PC Contractor SPRING SCAFFOLDING LLC | INSTALLATION OF TEMPORARY WORK PLATFORM AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY. THE WORK PLATFORM ON THE 3RD FLOOR FROM THE GROU… |
| M00232314 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 10/29/2019 | 07/14/2021 | Design KOHLER RONAN, LLC Contractor MICHAEL BURNS P&H CORP Filer NYCCODE LLC | Replacement of one existing steam boiler, addition of two new condensing boilers. Work includes upgrades to the existing steam system piping… |
| M00359756 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 06/19/2020 | 04/28/2021 | Design M.ARCH ARCHITECTS Owner WEST NEW YORK RESTORATION OF CT, IN Contractor A. PETER LUGER CONST INC | INSTALLATION OF HEAVY DUTY SIDEWALK SHED, +/- 128' long x 8'-10' high x 12'-22' wide, AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY. |
| M00359767 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 06/19/2020 | 04/23/2021 | Design M.ARCH ARCHITECTS Contractor A. PETER LUGER CONST INC | INSTALLATION OF STEEL PIPE SCAFFOLDING, +/- 101' long x +/- 60' high, AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY. |
| M00227080 | 1109 5TH AVENUE MANHATTAN | Alteration | Signed-off | 10/26/2019 | 07/06/2020 | Design KOHLER RONAN, LLC Contractor FRESH MEADOW MECHANICAL C Filer NYCCODE LLC | Interior Renovation associated with Mechanical Scope - Chiller upgrade. No change of use, egress or occupancy. |
| Building | Filings | Most Recent |
|---|---|---|
| 22 EAST 93RD STREET ↗ | 1 | 09/15/2026 |
| 1109 5TH AVENUE ↗ | 10 | 01/14/2026 |